Document RJZdwn586Bng6g7ebmbnRbOpB

Frank Conner and H. D. Stein, East Works Q. R. Reeder April 30. 1956 Enclosed is a photo-static copy of Purchase Order No. GSE 40885-C dated April 27, 1956 from Armco Steel Corporation covering the following: ''Make the necessary changes, alterations and new construction required for the elevator shaft, pit and pent house for the new elevator in the General Office on Curtis Street. The elevator will be furnished and Installed by others. See estimate SCE 473. The estimated cost of this works is: ARMCO L& M TOTAL $1,481.00 $32,912.00 $34,393.00 The estimated cost for the construction is $20, 558. 00 for which we are to receive a fixed fee of $1,481.00 which Is to be billed to Armco Steel Corporation at the rate of 4 1/2% of expenditures until 90% is billed; the final 10% to be billed upon completion of all work. For accounting purposes this work will be covered under Contract No. 382 the same as other work orders with the exception that this carry the fixed fee covered above. Mr. J. H. Stalker has been instructed to send to each of you a copy of the above estimates. QRR pjh cc: J. B. Stalker APR 3 01956 QRR Q. R. Reeder McGCon 2869 ARMCO STEEL CORPORATION DATE GENERAL PURCHASING DIVISION MIDDLETOWN, OHIO 4/27/56 jm PURCHASE ORDER No. gse 40685 -c SHOW THIS NUMBER ON ALL INVOICES. PACKAGES, SHIPPING PAPERS B CORRES- PONDENCE. GSE-40685-C n MCGRAW CONSTRUCTION COMPANY FIRST NATIONAL BANK BLDG. MIDDLETOWN, OHIO n SHIP TO: ARMCO STEEL CORPORATION ROUTED l_ QUOTATION QUANTITY F.O.B. SHIPPING POINT _i DATE REQUIRED DESCRIPTION TERNS COMMODITY REG REQ. NO. CONSTRUCTION FINAL CHARGE GSE-447 C-8602 MAT'L INDEX PRICE "MAKE THE NECESSARY CHANGES, ALTERATIONS AND NEW CONSTRUCTION REQUIRED-FOR THE ELEVATOR SHAFT, PIT AND PENT HOUSE FOR THE NEW ELEVATOR IN THE GENERAL OFFICE ON CURTIS STREET. -THE ELEVATOR WILL-BE FURNISHED AND INSTALLED BY OTHERS.--SEE ESTIMATE. NO. GE 473o THE ESTIMATED GOST OF THIS WCRKS IS .... EXPENSE ARMCO 1,431 L &M 32,912 TOTAL 34,393 FEE 1,481 TOTAL MCGRAW FEE TO BE PAID $1,481 GENERAL OFFICE NORTH WING ELEVATOR SHAFT IMPORTANT MAIL THE FOLLOWING TO: GENERAL PURCHASING DIVISION, MIDDLETOWN, OHIO ARMCO STEEL CORPORATION MIDDLETOWN, OHIO J. S. THOMAS ACKNOWLEDGMENT - ACKNOWLEDGE IMMEDIATELY - SPECIFY EXACT SHIPPING DATE GENERAL PURCHASING DIVISION S/N. B/L - IMMEDIATELY FOR EACH SHIPMENT (ALSO ONE COPY TO CONSIGNEE) INVOICE - RENDER IN DUPLICATE ON DAY OF SHIPMENT McGCon 2870 TERMS/CONDITIONS - SUBJECT TO TERMS & CONDITIONS ON REVERSE SIDE HEREOF. G - 5760 40685 II I II I I i V4 . *' Armco Steel Corporation GENERAL ENGINEERING DEPT. MIDDLETOWN, OHIO DIVISION .. ."'eSHESAEJD^ICE ........ DEPT. . .................. EST. No.. . GE-A73.. SUBJECT tXPERSE 1TELS - IJBTALLATIDN OP ......................................... SHEET No.............* ... .ELEVATOR ^T. .OJEPICE............. ..................................................JOB No.................................... MATE BY. . WARPJHS................. NOTED BY.................................................. DATE . . March. 14,. 1956. IB&D 1 ^ACCT NO. DESCRIPTION EQUIPMENT LABOR MATERIAL 3180 Removal, replacements & Alterations - Detail of Expense Sheet Piling Remove Stairs 420 S .F. $3./.50 L .s. .Remove Concrete 10 C .Y. $20,/ Remove Tile & Tile Partitions L.S. 'Remove Steelox Wall & Roof L.S. * Remove & Reaet Window,Doors L.S. ' r"- Shoring L.S. Brickwork , 3 M $125./$65. Stonework Concrete Block 34 C.F. $4./$6. 100 Ea. $.40/$.40 Hollow Tile - Partitions 600 Ea. $.50/ .40 Tile Work - Lavatory 380 S.F, $2./l.50 Floors - Concrete 560 S.F. $.50/,25 Floors - Rubber Tile 250 S.F. $.25/.80 Steel Ladder 1 Ea. I30./150. Steel Grating 125 S.F. $3./2. Vk Wire Grill Sheet Metal.Work Toilet Partitions y Carpentry 1 Ea. $25.A5. L.S. L.S. L.S. Plastering 210 S.Y. $9./l. Electrical Work L.S. Plumbing l.s. Insulation of Piping L.S. Insulation of Steelox 600 S.F. $.10/10 Painting L.S. Replace Blacktop 50 S.Y. $.20/1.80 Hoist, Incl. Erection 120 Hrs. $4.20/. 50 Compressor 160 Hrs. Truck Crane 40 Hrs. S6./9.50 Truck 120 Hrs. $2.25/2. Clean-up & Safety Protc* ction L.S. 1 i ! i ! I !! i f. i Bldg, Changes Including Elevator Pit Excavation & Backfill 120 C.Y. $7./ Formwork 2000 S.F. S1./.30 Reinforcing Steel 3000 Lb. $.07/.07 Concrete 50 C.Y. S4./9. Structural Steel 5 T. $150./300. Steelox Penthouse L.S. Steel Access Door 1 Ea. $30./60. Hollow Metal Doors 2 Ea. $40./l50. TOTALS I 1,260 800 200 280 300 225 400 375 136 40 ! 300 760 280 63 30 1 375 25 I 50 750 ;! 1,890 900 800 200 60 345 10 504 520 240 270 250 210 200 195 204 40 240 570 140 200 150 250 15 725 125 210 600 400 100 60 255 90 60 80 380 240 100 840 2,000 . 210 200 750 800 30 80 $ 17,548 600 210 450 1,500 400 60 300 $ 9,359 McGCon 2872 I! ! Armco Steel Corporation GENERAL ENGINEERING DEPT. MIDDLETOWN, OHIO DIVISION___ GiEERAL OFFICE........... DEPT............................................................. EST. No.. . OE-473............. SUBJECT........ vV. ,v.r.IIST&LUTJ-JlJ.Q?................................................... SHEET No............................ ^ ........ AT. GE:: HAL. CFFJC?.................................................................................. JOB No...........2................. IkTIMATE BY__FAR? f-yTHS.................... NOTED BY.................................................. DATE . . Iferch. U,. 1956. acc' MO DESCRIPTION EQUIPMENT I ti MATERIAL Overhead - 5% of L. & f.!. Taxes and Insurance - of I.. Small Tools - 3% of L, Contingencies - 10^ Fee - /&% TOTAL EXPENSE - $34,393 I -5602 CAPITAL ESTIVATE Elevator by Armco TOTAL CAPITAL - $33,000 1,141 !j $ 13,639 VA6 r 'if. 8 11,: 11 li 1,431 !i $ 1,431 ! 1,869 $ 00,558 ! | 11"3 Ji 8 12,3'4 ! $ 3?,000 McGCon 2873 :i