THE DOW CHEMICAL COMPANY
TEXAS OPERATIONS ASBESTOS HANDBOOK
I GER
CONTAINS ASBESTOS FIBERS AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD
REVISED, NOVEMBER, 1988
390657
STOOI3U52
THIS MANUAL IS AN UPDATED EDITION OF THE HANDBOOK PREPARED IN 1972 AND REVISED IN 1977, 1979, 1985 AND 1987. THIS EDITION HAS REVISED BY THE ASBESTOS TASK FORCE DURING THE THIRD QUARTER OF 1988.
ASBESTOS TASK FORCE HEMBERS
RED AHLICH DARRYL CRAGAR DONNA HICKS JERRY HINOJOSA BUDDY JACKS
MARK LARSON KERMIT LICKLIDER WALT NOACK MIKE TOWN GEORGE WILLIAMS
390658
INDEX
ST 00 I 3453
SECTION____________________________________IlILf___________________________
I PURPOSE
II HEALTH EFFECTS
III TRAINING PROGRAM MINIMUM REQUIREMENTS
IV DEFINITIONS
V ASBESTOS AWARENESS
VI ASBESTOS MAINTENANCE PROGRAM
VII AS8EST0S WORK IN PUBLIC BUILDINGS
VIII
NOTIFICATION OF DEMOLITION OR RENOVATION WORK
IX HAZARD COMMUNICATION
X PACKAGING FOR DISPOSAL XI MINIMUM REQUIREMENTS
GASKET & PACKING HANDLING
TRANSITE AND ASBESTOS SHINGLES
TRANSITE AND ASBESTOS SHINGLES CUTTING, DRILLING OR ABRADING
GLOVE BAGS
SMALL-SCALE SHORT-DURATION PROJECTS WITHOUT GLOVE BAGS
MINI-ENCLOSURES
LARGE SCALE, LONG DURATION PROJECTS
TYPICAL DECONTAMINATION AREA
NEGATIVE PRESSURE ENCLOSURES
AUTOMOTIVE CLUTCH & BRAKE REPAIR
XII ASBESTOS SAFETY CHECKLIST
XIII
ASBESTOS ABATEMENT AUDIT CHECKLIST
APPENDIX A
APPROVED EQUIPMENT
PAGF
1 2 3 4 7 18 19 20
21 23
24 26
28 30 31
33 34
36 39 40
42 43 45
-i - 390659
ST00 I 3454
SECTION I
PURPOSE
This handbook defines safe handling procedures for asbestos materials used in Texas Operations. The intent is to control personnel exposure to asbestos dust through training, asbestos maintenance programs, safe work procedures, proper use of protective equipment, and by the substitution of non-asbestos containing materials. It is Dow's philosophy to eliminate the use of asbestos where feasible. MAJOR MANAGER APPROVAL IS REQUIRED WHEN USING ASBESTOS MATERIALS IF A SUITABLE ALTERNATE IS KNOWN. Asbestos has been widely used as insulation, structural wallboard, roofing material, etc. Asbestos fibers are currently in use as a mechanical reinforcing matrix in insulation, roofing paper, certain piping systems, gaskets, brake linings, clutch plates, etc. Dow Engineering Specifications were revised in 1970 to exclude asbestos-containing insulation before the enactment of Federal regulations controlling the use and handling of asbestos. The revised OSHA standards (1910.1001 and 1926.58) which became effective July 21, 1986 define the precautions, procedures and controls required for asbestos handling. These standards also define the allowable exposure levels and the manner of determining exposure levels. The National Emission Standard for Hazardous Air Pollutants (NESHAP) also established specific requirements for notification, removal, packaging, transport and disposal of asbestos-containing materials. Violations of these regulations may result in a citation or fine or both. Dow is committed to meeting or exceeding government regulations, to protect the health of personnel.
390660
-1-
SECTION II
HEALTH & ENVIRONMENTAL SCIENCES INFORMATION CENTER
POTENTIAL HEALTH EFFECTS___________________________________________
ASBESTOS;
DR-0027-0713
REVISED: 10/14/88
SYNONYMS
AMPHIBOLE
APPEARANCE: fibrous solid in various colors EXPOSURE GUIDELINES: OSHA PEL is 0.2 fibers (>5 um) per cc. 8 hr. TWA
OSHA General Industry Standard 29CFR1910.1001. OSHA Construction Standard 29CFR1926.58. OSHA Excursion Limit is 1 fiber/cc averaged over a sampling period of 30 minutes. ACGIH TLV is 0.5 fibers (>5 um) per cc for amosite, Ala; 0.2 fibers (>5 um) per cc for crocidolite; 2 fibers (>5 um) per cc for chrysotile and other forms of asbestos, Ala.
ST00I3455
POTENTIAL HEALTH EFFECTS
This section includes possible adverse effects which could occur if this material is not handled in the recommended manner.
EYE - Mechanical injury only.
SKIN - Mechanical injury only. - Skin absorption is unlikely due to physical properties.
INGESTION - Single dose oral LD50 has not been determined. - Amounts ingested incidental to industrial handling are not likely to cause
injury; however ingestion of larger amounts may cause injury.
ACUTE INHALATION EFFECTS - Excessive exposure to dust causes chronic inflammations of lung tissue and
pleural membranes, as well as cancers, in both man and animals.
SUBCHRONIC EFFECTS - Prolonged exposure to asbestos dust has been found to cause pulmonary
fibrosis (asbestosis), which may be disabling and even fatal.
CHRONIC EFFECTS/CARCINOGENICITY - Has been shown to cause cancer in humans. - For hazard communication purposes under OSHA standard 29 CFR part
1910.1200, this chemical is listed as a carcinogen by NTP and IARC.
TERATOGENIC EFFECTS - No relevant information found.
REPRODUCTIVE EFFECTS - No relevant information found.
MUTAGENICITY - Some forms of asbestos have been reported to induce chromosomal changes in
tissue culture.
-2-
390661
ST00I3U5S
SECTION III
ASBESTOS TRAINING PROGRAM MINIMUM REQUIREMENTS
All employees who handle asbestos must be trained before initial assignment and annually thereafter. The OSHA asbestos standards and all training materials are available to employees upon request. Information will be presented in a manner the employee can understand.
The following items must be included in the training program:
1. The health effects associated with asbestos, 2. The relationship between smoking and exposure to asbestos in
producing lung cancer, 3. Methods of recognizing asbestos, 4. The quantity, location, manner of use, release, and storage of
asbestos and the specific nature of operations which could result
in exposure to asbestos, 5. The engineering controls and work practices associated with the
employee's job assignment, 6. The specific procedures implemented to protect employees from
exposure to asbestos, such as appropriate work practices, emergency and clean-up procedures, and personal protective equipment to be used, 7. The purpose, proper use, and limitations of respirators and protective clothing, 8. The purpose and a description of the medical surveillance program required by the OSHA Standard, 9. A review of the OSHA Standard, including appendices.
NOTE:
Training Requirement Guidelines A. Initial Training
1. View Asbestos video tape (VT87-1129B) 2. Complete Asbestos Training Guide (IPT)
B. Annual Retraining 1. View video tape on OSHA standards (VT87-1129A) 2. Complete Asbestos Training Guide (IPT)
Call 409-238-2620 to schedule videotapes and/or 409-238-2467 to obtain the Asbestos Training Guide (IPT).
390662
-3-
STOOI 3457
SECTION IV
DEFINITIONS
ACTION LEVEL
An airborne concentration of asbestos of 0.1 fiber per cubic centimeter (f/cc) of air calculated as an eight (8)-hour time-weighted average.
ASBESTOS
Chrysotile, amosite, crocidolite, tremolite, anthophyl1ite, actinolite, and any of these minerals that has been chemically treated and/or altered.
AUTHORIZED PERSONNEL
Any person authorized by the employer and required by work duties to be present in regulated areas.
CLEAN ROOM
An uncontaminated room having facilities for the storage of employees' street clothing and uncontaminated materials and equipment.
COMPETENT PERSON
One who has been trained and retrained annually in an EPA approved course and is capable of identifying existing asbestos hazards in the workplace and has the authority to take prompt corrective measures to eliminate them. The duties of the competent person include at least the following: establishing the negative-pressure enclosure, ensuring its integrity, and controlling entry to and exit from the enclosure; supervising any employee exposure monitoring required by the standard; ensuring that all employees working within such an enclosure wear the appropriate personal protective equipment, are trained in the use of appropriate methods of exposure control, and use the hygiene facilities and decontamination procedures specified in the standard; and ensuring that engineering controls in use are in proper operating condition and are functioning properly.
DECONTAMINATION AREA
An enclosed area consisting of an equipment room, shower area, and clean room, which is used for the decontamination of workers, materials, and equipment contaminated with asbestos. The decontamination area may be adjacent and connected to the regulated area or located remotely.
DEMOLITION
The wrecking or taking out of any load-supporting structural member and any related razing, removing, or stripping of asbestos.
*
-4- 390663
ST00I3458
SECTION IV
DEFINITIONS
EMPLOYEE EXPOSURE
Exposure to airborne asbestos that would occur if the employee were not using respiratory protective equipment.
EQUIPMENT ROOM (CHANGE ROOM)
A contaminated room located within the decontamination area that is supplied with impermeable bags or containers for the disposal of contaminated protective clothing and equipment.
EXCURSION LIMIT (EL)
An airborne concentration of asbestos of 1.0 fiber per cubic centimeter (f/cc) of air as averaged over a sampling period of thirty (30) minutes.
Eim
A particulate form of asbestos 5 micrometers or longer, with a length-to-diameter ratio of at least 3 to 1.
FRIABLE ASBESTOS
Any material that when broken, crushed or pulverized releases asbestos fibers.
HIGH-EFFICIENCY PARTICULATE AIR (HEPA1 FILTER
A filter capable of trapping and retaining at least 99.97 percent of all monodispersed particles of 0.3 micrometers in diameter or larger.
MINI-ENCLOSURE
An enclosure constructed of 6-mil polyethylene sheeting to restrict access to the area where small-scale, short duration asbestos maintenance or renovation work is to be performed. The enclosure must have a contiguous change room.
NEGATIVE PRESSURE ENCLOSURE
An enclosure for large-scale long duration projects constructed of 6-mil polyethylene sheeting and equipped with a ventilation system (which discharges through a HEPA filter) capable of creating a negative pressure of 0.02 inches of water inside the enclosure. Where feasible, a decontamination area should be contiguous to the enclosure and should be the only means of egress.
PERMISSIBLE EXPOSURE LIMIT (PEL)
No employee shall be exposed to an airborne concentration of asbestos in excess of 0.2 fibers per cubic centimeter of air as an eight-hour time-weighted average (8 hr. TWA).
-5- 390664
STOOI 3459
SECTION IV DEFINITIONS
REGULATED AREA An area established by the employer to demarcate areas where airborne concentrations of asbestos exceed or can reasonably be expected to exceed the permissible exposure limit. The regulated area may take the form of a temporary enclosure, or an area demarcated to restrict access and minimize the number of employees potentially exposed to asbestos.
REMOVAL
The taking out or stripping of asbestos or materials containing asbestos. RENOVATION The modifying of any existing structure, or portion thereof, where exposure to airborne asbestos may result. REPAIR Overhauling, rebuilding, reconstructing, or reconditioning of structures or substrates where asbestos is present.
SMALL-SCALE. SHORT-DURATION ACTIVITIES The tasks such as, but not limited to: the removal of small quantities of asbestos-containing insulation on pipes prior to repair; the removal of small quantities of asbestos-containing insulation on beams or above ceilings; the replacement of an asbestos-containing gasket when mechanical removal is required; the installation or removal of a small section of drywall material containing asbestos; or the installation of electrical conduits, pipe, or cable through or proximate to asbestos-containing materials. SURFACTANTS Chemicals added to water to improve its wetting ability.
-6- 390665
STOOI3L60
ASBESTOS AWARENESS HANDLING REQUIREMENTS
OWNER RESPONSIBILITY*
INSPECT ALL AREAS
I
TAKE SAMPLES OF SUSPECT MATERIALS
ANO SENO TO ANALYTICAL SERVICES
409-238-1199
ASBESTOS CONTENT >0.1X
DOCUMENT RESULTS ANO RETAIN RECORDS
I
TRAIN PERSONNEL ON ASBESTOS SECTION III TOAH
FURTHER INSPECT FOR MATERIAL CONDITION ANO VISUAL FIBER RELEASE
ASBESTOS CONTENT
<0.1%
I
DOCUMENT RESULTS ANO RETAIN RECOROS
I
NO FURTHER ACTION
REQUIRED
MATERIAL IN POOR CONOITION OR VISUAL FIBER RELEASE
EVALUATE ANO DECIDE FOR REMOVAL AND/OR REPAIR
I
CONTACT INSULATION SERVICES 409-238-7036 OR INDUSTRIAL HYGIENE SERVICES 409-238-1281 FOR ASSISTANCE
MAJOR REMOVAL/DEMOLITION OR RENOVATION REQUIRED
NAME PROJECT SUPERVISOR. SCOPE. JOB. ANO (IF REQUIREO) PREPARE NOTIFICATION LETTER TOAH SECTION VII
I
PROJECT SUPERVISOR SHALL: CONTACT ENVIRONMENTAL SERVICES 409-238-2414 25 DAYS BEFORE WORK TO BEGIN
I
CONTACT INSULATION SERVICES TO SID JOB OR ARRANGE FOR DOW PERSONNEL
WHEN CONTRACT AWAROEO. CONTACT ENVIRONMENTAL SERVICES 409-238-2414 ANO IDENTIFY SUCCESSFUL BIDDER
I
HAVE PRE-JOB REVIEW WITH SAFETY DIRECTOR. OWNER REPRESENTATIVE. CONTRACTOR COMPETENT PERSON. INDUSTRIAL HYGIENE. OOW OR CONTRACTOR PERSONNEL TO DO JOB
I
OECIDE ON JOB PROCEDURES AND ARRANGE AUDIT ANO MONITORING. COMPLETE AS8EST0S SAFETY CHECKLIST.
OWNER SHALL OOCUMENT ANO RETAIN RECORD IF ALL ASBESTOS REMCVED.
I
DOCUMENT ANO SET UP MAINTENANCE PROGRAM IF ANY ASBESTOS REMAINING
MATERIAL IN 6000 CONOITION, NO FIBER RELEASE
OOCUMENT. LABEL ANO SET UP MAINTENANCE PROGRAM TOAH SECTION VI
--------------- 1
MINOR REMOVAL ANO/OR REPAIR REQUIRED
REVIEW SECTION X TOAH TO SEE IF JOB FALLS INTO GLOVE BAG OR SMALL-SCALE. SHORTOURATION ACTIVITY. IF SO USE CORRECT ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
OOCUMENT REMAINING ASBESTOS & SET-UP MAINTENANCE PROGRAM
REFERENCES
1. TEXAS OPERATIONS SAFETY STANDARD TI2
2. TEXAS OPERATIONS ASBESTOS HANOBOOK (TOAH)
3. EA-56U PURPLE 3CCK 4. OSHA STANDARDS 29CFR
1910.1001 & 29CFR 1926.58 5. ENVIRONMENTAL STANOARO ES-3U
390666
-7-
ST00 I 346 I
SECTION V
ASBESTOS AWARENESS
ASBESTOS DO'S AND DON'TS
This section is provided as general guidance when working with or near asbestos-containing materials.
DO
1. Get positive identification. Sample and have analysis performed at Analytical Services, phone 409-238-1199.
2. Take sufficient samples. Some vessels, equipment, etc. may contain more than one type of insulation. Asbestos materials may be covered by refractory, siding, or insulation.
3. Consult the appropriate section of this handbook if asbestos is present. Materials containing more than 0.1% by weight must be handled as asbestos.
4. Put all asbestos waste (old insulation, transite, mastic, dust collector solids, disposable clothing, gaskets, packing, shingles, Haveg piping, furnace refractories, pump packing, pipe gaskets, brake shoes, etc.) in approved containers for disposal. The containers must be properly labeled to warn of the asbestos hazard and sent to the designated asbestos landfill.
5. Inform all personnel in the general area that asbestos work is in progress.
DO NOT
1. Use materials containing asbestos (i.e. insulation, fireproofing, transite siding, Haveg piping, weatherproofing, and cooling tower materials) where an adequate alternate exists. MAJOR MANAGER APPROVAL IS REQUIRED WHEN USING ASBESTOS MATERIALS IF A SUITABLE ALTERNATE IS KNOWN.
2. Use asbestos labeled bags for disposal of general trash because of landfill permit requirements.
3. Sandblast or hydroblast materials containing asbestos. When sandblasting or hydroblasting adjacent areas, protect the asbestos materials from overblast. Examples of items to be protected are transite walls, pipe insulation, fireproofing, etc.
4. Use compressed air to remove asbestos materials. For example, do not clean brake drums and clutch housings with compressed air. This procedure may fill the surrounding atmosphere with asbestos fibers. An acceptable method is to use an approved vacuum. Dispose of the debris in approved containers and send to the designated asbestos landfill.
390667
-8-
4
Z 9 *ie i o o is
SECTION V
ASBESTOS DO'S AND DON'TS (Cont'd)
5. Eat, drink, smoke, chew gum/tobacco products, or apply cosmetics in a regulated area or a decontamination area.
6. Dry sweep asbestos materials. 7. Spray asbestos-containing materials. 8. Use hand-operated or power-operated tools (such as but not limited
to saws, scorers, abrasive wheels and drills) without local exhaust ventilation if the use of these tools would cause asbestos exposures to personnel in excess of 0.2 fiber cc. 8 hr. TWA. 9. Hang plants or pictures on structures covered with asbestos-containing materials. 10. Sand asbestos-containing floor tiles. 11. Damage asbestos-containing materials while moving furniture or other objects. 12. Install curtains, drapes, or dividers in such a way that they damage asbestos-containing materials. 13. Dust floors, ceilings, moldings or other surfaces in asbestos-contaminated environments with a dry brush. 14. Use an ordinary vacuum to clean up asbestos-containing debris. 15. Remove ceiling tiles below asbestos-containing materials without wearing the proper respiratory protection, clearing the area of other people, and observing asbestos removal waste disposal procedures. 16. Remove contaminated ventilation system filters without wetting. Do not shake.
NOTE: Items 5 through 16 are directly from the OSHA Asbestos Regulations.
-9- 390668
C9J|*EI 001S
!
SECTION V
SOME ASBESTOS-CONTAINING MATERIALS IN BUILDINGS
SUBDIVISIONGENERIC NAME
AS8ESTQS(%) DATES OF USE BIN0ER/SI7TNG
Surfacing material sprayed-or troweled-on
1-95
Preformed thermal batts, blocks, and insulating products pipe covering
85% magnesia
15
calcium silicate
6-8
Textiles
cloth
blankets(fire) felts:
blue stripe red stripe green stripe sheets cord/rope/yarn tubing
tape/strip curtains:
theatre,welding
100 90-95
80 90 95 50-95 80-100 80-85 90
60-65
Cementitious concrete-like
Paper products
extrusion panels:
8
corrugated(transite) 20-45
flat (transite)
40-50
flexible
30-50
flexible perforated 30-50
laminated
35-50
(outer surface)
roof tiles
20-30
clapboard and shingles:
clapboard
12-15
siding shingles
12-14
roofing shingles
20-32
pipe
20-15
corrugated:
high temperature
90
moderate temperature 35-70
indented
98
millboard
80-85
1935-1970
sodium silicate, Portland cement, organic binders.
1926-1949 1949-1971
magnesium
carbonate calcium silicate
1910-present 1920-present 1920-present
1920-present 1920-present 1920-present 1920-present 1920-present
1920-present
none
cotton/wool cotton cotton cotton cotton cotton/wool cotton/wool
cotton/wool
1945-present cotton
1965-1977
1930-present 1930-present 1930-present 1930-present 1930-present
Portland cement
Portland cement Portland cement Portland cement Portland cement Portland cement
1930-present Portland cement
1944-1945 unk.-present unk.-present 1935-present
Portland cement Portland cement Portland cement Portland cement
1935-present 1910-present 1935-present
1925-present
sodium silicate starch cotton and organic binder starch,!ime,clay
,44*4
-10-
390669
ST00 I 3464
SECTION V
SOME ASBESTOS-CONTAINING MATERIALS IN BUILDINGS
SUBDIVISIONGENERIC NAME
ASBESTOS!*) OATES OF USE BINDER/SIZING
Roofing felts
smooth surface mineral surface shingles pipeline
10-15 10-15
1 10
Asbestos-containing compounds
caulking putties
30
adhesive(cold applied)i 5-25
joint compound
roofing asphalt
5
mastics
5-25
asphalt tile cement 13-25
roof putty
10-25
plaster/stucco
2-10
spackles
3-5
sealants fire/water 50-55
cement,insulation cement,finishing cement,magnesia
20-100 55 15
Asbestos ebony products
50
Flooring tile and
Sheet Goods
vinyl asbestos tile
21
asphalt/asbestos tile 26-33 sheet goods/resilient 30
Wallcovering
vinyl wallpaper
: 6-8
Paints and coatings roof coatings.......... air tight
--4-7 15
1910-present 1910-present 1971-1974
1920-present
asphalt asphalt asphalt asphalt
1930-present 1945-present 1945-1975 unk.-present 1920-present 1959-present unk.-present unk.-present 1930-1975
1935-present
1900-1973 1920-1973 1926-1950
1930-present
linseed oil asphalt asphalt asphalt asphalt asphalt asphalt Portland cement starch,casein, synthetic resins caster oil or polyisobutylene clay clay magnesium carbonate Portland cement
1950-present
1920-present 1950-present
polyvinyl chloride asphalt dry oils
unk.-present none
'1900-present asphalt "'1940-present^ `asphalt
-
-11-
390670
SECTION V ASBESTOS AWARENESS
SUBJECT: Example pictures of past asbestos uses. Partial listing of examples that we must handle according to the guidance provided in this manual.
co --4 O o
CO jr cn cr
Figure 1. Many of our daily jobs involve repairing flange leaks, replacing valves, etc. The old insulation that is removed In many cases will contain asbestos.
3*
* 1
390671
a
sm
SECTION V
ASBESTOS AWARENESS
SUBJECT: Example pictures of past asbestos uses. Partial listing of examples that we must handle according to the guidance provided in this manual.
ST00I3466
Figure 3. There still remain some asbestos blankets that need disposal.
Figure 4. Also used in past years was fiberglass Insulation mixed with
asbestos fibers.
-13-
390672
SECTION V
ASBESTOS AWARENESS
SUBJECT: Example pictures of past asbestos uses. Partial listing of examples that we must handle according to the guidance provided in this manual.
go
--I a a
co
cr
Figure 5. Structural fireproofing often contained asbestos materials.
-A2.
& m 4
-*
Figure 6. Asbestos insulation blocks in combinations with refractory materials exist in many of our boilers and furnaces.
-14-
390673
STOO13468
SECTION V
ASBESTOS AWARENESS SUBJECT: Example pictures of past asbestos uses. Partial listing of examples that we must handle according to the guidance provided in this manual.
Figure 7. Transite which contains asbestos has been extensively used in the ast in many applications in Texas Operations such as cooling towers, uildings, warehouses, etc. Asbestos is also present in cemesto board and sbestos siding shingles which were also used in various type buildings.
Figure 8. Our most extensive use of asbestos in the older plants was th'e "thousands of square feet used on piping and equipment insulation.
-15-
390674
STOO I 3469
SECTION V ASBESTOS AWARENESS
SUBJECT: Example pictures of asbestos uses must handle according to the guidance provided Partial testing of example that we
in this manual.
Friable, fluffy sprayed-on material
Friable, cementitious sprayed-on or troweled material (acoustical plaster)
*'' '
1
- ^ '** "** >
**| n.'
Nonfriable wallboard with friable sprayed-on material behind
Pipe lagging
390675
Figure 6 Examples of asbestos-containing materials found in buildings
-16-
in i'!
SECTION V ASBESTOS AWARENESS
SUBJECT: Example pictures of asbestos uses. Partial testing of example that we must handle according to the guidance provided in this manual.
0 *1L I 001S
Figure 7 Asbestos-containing material located above a suspended ceiling.
-17-
390676
SECTION VI
ASBESTOS MAINTENANCE PROGRAM MINIMUM REQUIREMENT
An asbestos maintenance program must be initiated in all facilities
that have asbestos-containing materials. Such a program shall include:
1. Inspection of buildings and process areas to determine the presence
or absence of asbestos containing materials.
2. Development of an inventory of all asbestos-containing materials in
the facility. The inventory may be a blueprint, diagram or written
description which identifies the location and approximate amount o
asbestos. Records must be maintained until the asbestos-containlty
materials are removed.
3. Maintenance of all labeling of asbestos-containing materials or
block signs in the facility.
3
4. Prompt clean up of any asbestos contamination.
"^
5! Examination of all asbestos-containing materials semi-annually to;^
detect deterioration. If deterioration is found, the material must
be repaired or removed. Call Insulation Services (409-238-7036
assistance is needed.
6. Written procedures for handling asbestos materials during thi ^
performance of maintenance, demolition
renovation activitjega
*7. Training for personnel who may be required to handle asbestdlSfflp
containing materials as outlined in the Training Section of thiSj
Handbook. (See page 3) 8. Documentation of compliance with this program.
'vfvJj
-18-
390677
STOOI 3472
SECTION VII ASBESTOS WORK IN PUBLIC BUILDINGS
The Texas Department of Health adopted new rules which became effective on October 1, 1988. These rules apply for all asbestos work in "public buildings". "Public buildings" are defined as all buildings "capable of public occupancy" except for "those buildings or oortions of buildings to which all access is strictly and entirely controlled or prohibited because of process or functions dangerous to human health or safety.." The procedures outlined below must be followed for all jobs involving asbestos in public buildings:
1. Notify Environmental Services, (409-238-2414) 2. Contact Insulation Services for assistance in assessing the job
and in locating a licensed contractor to do the work. (409-238-7036)
390678
-19-
STOO I 31*73
SECTION VIII
NOTIFICATION OF DEMOLITION OR RENOVATION WORK It is the responsibility of the superintendent/owner to contact Environmental Services (409*238-2414) 25 days prior to the start of any reportable asbestos project. Jobs to be reported are: (1) Demolition which involves the removal of friable asbestos
material. (2) Renovation in which the cumulative amount of friable asbestos
removed in a calendar year exceeds 260 linear feet on pipe or 160 square feet on other facility components. (3) Any asbestos work in "public buildings" Reference: Texas Operations Environmental Standard ES314
-20- 390679
ST00I3474
SECTION IX
HAZARD COMMUNICATION
1. Labels: Labels may be affixed individually to items or a warning sign may be placed at the entrance to the block or area.
All products that contain asbestos in concentrations that exceed 0.1% by weight must be labeled. Labeling must be done in accordance with the requirements of 29 CFR 1910.1200 (f) of OSHA's Hazard Communication standard.
CONTAINS ASBESTOS HBERS AVOID CREATING DUST CANCER AND LUNG DISEASE HAZARD
14" x 20" Asbestos Hazard Signs
Dow Stock #01-03374-020
3" x 5" Asbestos Hazard Labels
Dow Stock #01-03372
White "Danger" on red oval on a black field - Black block lettering
Banger
SOME MATERIALS IN THIS BLOCK MAY CONTAIN ASBESTOS
(CONSULT SUPERVISION FOR SPECIFIC INFORMATION
WHEN WORKING WITH ASBESTOS AVOID CREATING DUST
ASBESTOS IS 1 CANCER &. LUNG DISEASE HAZARD
14" x 20" Asbestos Hazard Labeling Area Sign
Dow Stock #01-03374-010
White "Danger" on a red oval on a black field - Black block lettering
-21-
390680
SECTION IX
HAZARD COMMUNICATION
2. Regulated Area Sign: Warning signs must be posted to demarcate a regulated area and must be posted at such a distance that an employee can read the signs and take necessary protective steps before entering the regulated area.
ASBESTOS
CANCER AND LUNG DISEASE HAZARD AUTHORIZED PERSONNEL ONLY
RESPIRATORS AND PROTECTIVE CLOTHING ARE REOUIRED'IN THIS AREA
14* x 20" Asbe* Hazard Sign
i4 Dow Stock #01-"
White "Danger a red oval on field - Blac lettering
3. Asbestos Disposal Containers:
All containers used for disposal of asbestos waste must have an app label. Special purpose, 6 mil, polyethylene bags with the approprt t label are available through Dow Stock #17-30522.
-22-
390681
ST00 I 3476
SECTION X
PACKAGING OF ASBESTOS WASTE FOR DISPOSAL
1. The recommended container is a 6-mil thick polyethylene bag. These bags are available through Dow Stock #17-30522. Other acceptable containers are polyethylene lined cardboard containers or polyethylene lined metal containers (drums, dempster boxes, or dino boxes).
2. Polyethylene bags labeled with an approved asbestos label must be used only for bagging asbestos waste.
3. When using bags, minimize the amount of void space or air in the bags to minimize their bursting during stacking and disposal.
4. All containers used for asbestos waste must be sealed to make them leak-tight.
5. Torn bags must be rebagged (double bagged) rather than repaired by taping.
6. Disposable clothing worn during asbestos removal, packaging, and disposal must be placed into properly labeled polyethylene bags and disposed of as asbestos waste.
7. An open-top fiber or steel drum containing a polyethylene liner may be used to accumulate small quantities of bagged and sealed asbestos waste (brake shoes, brake dust, garlock gaskets, etc.). The drum must have an approved warning label, be labeled for asbestos waste use only, and the top must be kept on except during deposit of waste.
8. All dempsters used for unbagged asbestos waste must contain a disposable polyethylene liner obtained from, or approved by, Environmental Operations.
9. Dempster boxes must not be filled higher than the top of the walls.
10. Dempster liners must be lapped over arici secured for temporary closure whenever the job is discontinued for a prolonged period (overnight, holiday, weekend).
11. Dempster liners must be securely closed before transport of the dempsters; the sides and ends are to be lapped over and then secured. Proper lapping and sealing procedures are provided in instructions by Environmental Operations.
12. Tie-downs for dempster liners must not be attached to the dempster boxes.
13. All dempster boxes used for asbestos waste packaging and transport, and all packages of asbestos waste (including dempster liners) must be labeled with an OSHA-approved label.
Note: Call 409-238-1176 for information.
-23-
390682
SECTION XI
ASBESTOS GASKET AND PACKING HANDLING MINIMUM REQUIREMENTS
STORAGE FACILITY
Preformed gaskets, packing and gasket fabrication materials will be stored in a clean storage area. The storage area will be cleaned regularly with a HEPA filter vacuum to prevent accumulation of debris.
REMOVAL
Spiral-wound gasket removal shall comply with the glove bag or small-scale short-duration minimum requirements if wet methods cannot be used.
If other gaskets or packing to be removed are not adhered to the sealing surfaces and can be renr-ed by hand without breaking apart, remove and package for disposal according to Section IX of this manual. If the gasket or packing is adhered to the sealing' surfaces so that mechanical means are used and this operation creates particles in the air or surrounding area, then as a minimum, the asbestos abatement minimum requirements for glove bags or small-scale short-duration jobs shall be used.
All asbestos residue must be removed from gasket sealing surfaces on valve and pipe before transporting from gasket removal site.
CUTTING
GENERAL:
1. Employees who work with asbestos must receive training in asbestos hazards before the initial assignment and annuallythereafter.
2. Personnel in the general area must be notified that asbestos work is in progress.
3. A specific job procedure must exist and be followed.
SAFETY:
1. Safety equipment required by the job location must be worn.' 2. An approved respirator must be worn during cutting and cleanu
Employee must have completed the mandatory fit test. Contacts 409-238-3536 for information. 3. Disposable coveralls with attached boots and hoods must be w' for cutting and cleanup operations. Coverall boots may be wo over shoes or inside rubber boots. If monitoring shows the potential asbestos exposure levels are consistently below 0.1 fiber/cc on an 8 hour TWA or short-term exposures below 1 f/c averaged over a sampling period of 30 minutes, disposable coveralls need not be worn. 4. Vacuum and local exhaust ventilation systems must be equipped with HEPA filters.
-24-
390683
STOOI 3478
.kJ
SECTION XI
ASBESTOS GASKET AND PACKING HANDLING MINIMUM REQUIREMENTS
TY:
5. Personnel monitoring must be done at the beginning of each job '* unless personnel wear supplied air respirators, or previous
personnel monitoring of similar jobs shows short-term exposures i. below 1 fiber/cc averaged over a sampling period of 30 minutes or 8
hour TWA exposure potentials less than 0.1 fiber/cc. Contact Industrial Hygiene Services 409-238-1281 for information. 6. Local exhaust ventilation must be provided for hand operated or z" power operated tools (such as but not limited to saws, scorers, abrasive wheels, and drills). The efficiency of local exhaust i - ventilation systems must be verified by Industrial Hygiene - Services.
eo: >v
WORK AREA:
1. Gasket fabrication area must be identified as an asbestos handling area.
2. Gasket cutting table will be fabricated such that asbestos material or dust cannot collect or contaminate the table.
~-3.~ Work area must be cleaned after each job. Vacuum to remove any loose material or dust. Dispose of any scrap material In a sealed plastic bag with the proper asbestos label and clean unused fabrication material for storage. A job procedure must be followed when changing HEPA filters.
4. Dispose of coveralls and other contaminated clothing using labeled plastic bags.
5. After area is clean, vacuum work clothes and remove and clean respirators for *storage.
^5-
390684
SECTION XI
TRANSITE AND ASBESTOS SHINGLES HANDLING MINIMUM REQUIREMENTS
Transite sheeting or asbestos shingles should not be modified (cut or drilled). An alternate material should replace the transite sheeting or shingles needing modification and any cutting or drilling should be made on the alternate material.
MAJOR MANAGER APPROVAL IS REQUIRED WHEN USING ASBESTOS MATERIALS AS REPLACEMENT FOR TRANSITE SHEETING OR ASBESTOS SHINGLES.
Requirements:
I. A competent person must supervise all large-scale jobs to assure
proper procedures are followed.
2. Employees who work with asbestos must receive training in asbestos
hazards before the initial assignment and annually thereafter.
3. Personnel in the general area must be notified that asbestos work
in progress.
4. A specific job procedure must be written and followed. An asbesto'
safety check list must be completed for each large scale job.
5. Safety equipment required by the job location must be worn.
.6 An approved respirator must be worn. Employees must have completed
the mandatory fit test. Contact 409-238-3536.
7. Disposable coveralls with attached boots and hoods must be worn
during removal and cleanup operations. If the removal is being done
with the use of heavy equipment such as a crane or front-end loader,
the necessary protective clothing should be specified in the job
procedure.
8. Personnel monitoring must be done at the beginning of each job
unless personnel wear supplied air respirators, or previous
personnel monitoring of similar jobs shows short-term
exposure potentials below 1 f/cc averaged over a sampling
period of 30 minutes or 8-hour TWA exposure potentials less than JK
fiber/cc. Contact Industrial Hygiene Services 409-238-1281 .for `
information.
9. Transite and asbestos shingles must be wetted before removal.
10. A regulated area must be established and asbestos warning signs
posted to restrict access to authorized personnel only.
II. Drinking water must be kept outside regulated area.
12. Disposable clothing and respirator must be removed each time befo
exiting the regulated area. A change area must be designated jus!
inside the regulated area.
13. Broken pieces of transite and/or shingles must not be crushed by*t
movement of the heavy equipment.
14 Broken transite and shingles must be wetted before being picked up; Material must be placed into labeled polyethylene bags or contaii
approved by Environmental Operations. Bags or containers must be:
lowered to the ground, not dropped.
*'
15. Before leaving the regulated area at the end of the day or job,
broken transite and shingles must be placed in an approved
container.
16. All equipment removed from the regulated area must be
decontaminated.
-26-
390685
ST00I3480
SECTION XI TRANSITE AND ASBESTOS SHINGLES HANDLING MINIMUM REQUIREMENTS (CONT'D)
17. Disposable coveralls and gloves must be placed in an aDDroved container at the end of the day or job.
18. After work is completed a thorough inspection and cleanuo of thP area must be conducted.
19. All materials used to establish the regulated area must be removed 20. Bags or containers must be transported to the dempster or collection
area.
n
-is
-27- 390686
SECTION XI
TRANSITE AND ASBESTOS SHINGLES CUTTING, DRILLING, OR ABRADING MINIMUM REQUIREMENTS
Transite sheeting or asbestos shingles should not be modified (cut or drilled). An alternate material should replace the transite sheeting or shingles needing modification and any cutting or drilling should be made on the alternate material.
MAJOR MANAGER APPROVAL IS REQUIRED WHEN USING ASBESTOS MATERIALS AS REPLACEMENT FOR TRANSITE SHEETING OR ASBESTOS SHINGLES.
REQUIREMENTS:
1. Employees who work with asbestos must receive training in asbestos hazards before the initial assignment and annually thereafter.
2. Personnel in the general area must be notified that asbestos work is in progress.
3. A specific job procedure must be written and followed. 4. Safety equipment required by the job location must be worn.
5. An approved respirator must be worn. Employees must have completed
the mandatory fit test. Contact 409-238-3536.
6. Disposable coveralls with attached boots and hoods must be worn
during removal, cutting, drilling, abrading and the resulting cleanup. Coverall boots may be worn over work shoes or inside rubber boots. 7. Vacuum and local exhaust ventilation systems must be equipped with HEPA filters.
.8 Personnel monitoring must be done at the beginning of each job
unless personnel wear supplied air respirators, or previous personnel monitoring of similar jobs shows short-term exposures below 1 f/cc averaged over a sampling period of 30 minutes or 8 hour TWA exposure potentials less than 0.1 fiber/cc. Contact Industrial Hygiene Services 409-238-1281 for information. 9. Water for wetting must contain a surfactant. 10. Local exhaust ventilation must be provided for hand operated or power operated tools (such as but not limited to, saws, scorers, abrasive wheels, and drills). The efficiency of the local exhaust ventilation system must be verified by Industrial Hygiene Services 11. A regulated area must be established and asbestos warning signs posted to restrict access to authorized personnel only. 12. Area must be cleaned of existing asbestos contamination and other: debris. 13. Portable objects must be removed to prevent contamination. 14. Coverings must be placed over remaining objects and underneath the; work area. Scaffold landings must be covered. 15. Mini-enclosures or negative pressure enclosures must be used for jobs whenever feasible if the potential exposure level may equal or exceed 1 fiber/cc averaged over a sampling period of 30 minutes or 0.2 fibers/cc 8 hour TWA (local exhaust ventilation or other engineering control methods may eliminate the need for enclosures.)
-28-
390687
STOOI 3482
SECTION XI
TRANSITE AND ASBESTOS SHINGLES HANDLING MINIMUM REQUIREMENTS (CONT'D)
16. Material that is being cut, drilled, etc. must be wetted down and/or local exhaust ventilation used. If wetting is not compatible with the process, or matenais/equipment may oe damaged, or iocai exnaust, ventilation reduces the potential exposure below 1 fiber/cc averaged over a sampling period of 30 minutes or 0.2 fibers/cc as an 8 hour TWA, wetting may be eliminated.
17. Material removed must be placed into labeled polyethylene bags or containers approved by Environmental Operations. Bags or containers must be lowered to the ground, not dropped.
18. After work is completed a thorough inspection and cleanup of the area must be conducted. Vacuum the work area as required.
19. All tools removed from the regulated area must be decontaminated. The specific job procedure for the job must address the decontamination of HEPA vacuum cleaners and changing of the HEPA filter in vacuum cleaners if a vacuum cleaner is used during the job.
20. Disposable coveralls, exposed area of skin and respirator must be - vacuumed and boots must be decontaminated each time before exiting
the regulated area. 21. Disposable coveralls, must be disposed of in a sealed asbestos waste
bag. 22. Work clothes must be vacuum off. 23. All materials used to establish the regulated area must be removed. 24. Bags or containers must be transported to the dempster or collection
area.
-29-
390688
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
GLOVE BAGS.
GENERAL:
1. Employees who work with asbestos must receive training in asbestos hazards before the initial assignment and annually thereafter.
2. A specific job procedure must be written before beginning the job.
SAFETY:
Safety equipment required by the job location must be worn. An approved respirator must be worn during material removal and cleanup. Employee must have completed the mandatory fit test. Contact 409-238-3536 for information. 3. Vacuum equipment must be equipped with a HEPA filter. 4. Water for wetting must contain a surfactant.
REMOVAL:
1. The glove bag must be fitted to the pipe or structure where asbestos work is to be done. Insert the necessary tools into the bag. Attach bag to the pipe or structure and seal all openings with tape. The bottom seam of the bag must also be reinforced with tape to prevent leakage from the bag that may result from a defect in the bottom seam.
2. Anropening must be made in the bag away from the work area. A spray nozzle must be inserted through this opening and the area to be worked sprayed until it is thoroughly wetted. Continue wetting dry material as it is exposed. Dry material in the bottom of the . bag must be wetted. Wetting of materials may be eliminated if { water is not compatible with the process or materials or equipmen* may be seriously damaged.
3. After removal of the layer of asbestos containing materials, the pipe or surface must be cleaned with a wire brush and wet wiped until no traces of asbestos containing material can be seen.
4-. Exposed asbestos must be encapsulated at terminations. 5. Tools must be wetted and cleaned. Place the tools such that they,
may be removed after the bag is twisted and sealed. 6. A vacuum hose must be inserted through the opening used for
wetting and used to remove any air from the bag that may contain asbestos fibers. The bag must be squeezed as close to the top as possible, twisted and sealed with tape to keep the asbestos materials safely in the bottom of the bag. 7. Remove the bag from the work area and remove tools. 8. The top portion of the bag and the opening used for wetting must;' be resealed with tape. 9. Disposal of the glove bag must be in an approved container.
-30-
390689
S I UU I 3481)
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
SMALL-SCALE SHORT-DURATION PROJECTS WHEN GLOVE BAGS ARE NOT USED.
GENERAL:
1. Employees who work with asbestos must receive training in asbestos h?z?rri: before the initial assignment and annually thereafter.
2. Personnel in the general area must be notified that asbestos work is in progress.
3. A specific job procedure must be written before beginning the job.
SAFETY:
1. Safety equipment required by the job location must be worn. 2. An approved respirator must be worn during material removal and
cleanup. Employee must have completed the mandatory fit test. Contact 409-238-3536 for information. 3. Disposable coveralls with attached boots and hoods must be worn during cleanup and removal operations. Coverall boots may be worn over work shoes or inside rubber boots. 4. Vacuum and local exhaust ventilation systems must be equipped with HEPA filters. 5. Personnel monitoring must be done at the beginning of each job unless personnel wear supplied air respirators, or previous personnel monitoring of similar jobs shows short-term exposures below 1 f/cc averaged over a sampling period of 30 minutes or 8 hour TWA exposure potentials less than 0.1 fiber/cc. Contact Industrial Hygiene Services 409-238-1281 for information. 6. Water for wetting must contain a surfactant. 7. Local exhaust ventilation must be provided for hand operated or power operated tools (such as but not limited to, saws, scorers, abrasive wheels, and drills). The efficiency of local exhaust ventilation systems must be verified by Industrial Hygiene Services.
REGULATED AREA:
1. A regulated area must be established and asbestos warning signs posted to restrict access to authorized personnel only.
2. Area must be cleaned of existing asbestos contamination and other debris.
3. Portable objects must be removed to prevent contamination. 4. Coverings must be placed over remaining objects and underneath the
work area. Scaffold landings must be covered. Materials must not be dropped to the ground. Pre-job planning must include provisions for keeping deteriorated material in place after jacketing is removed. . Mini-enclosures or negative pressure enclosures must be used for jobs whenever feasible if the potential exposure level may equal or exceed 1 f/cc averaged over a sampling period of 30 minutes or 0.2 fibers/cc 8 hour TWA (local exhaust ventilation or other engineering controls methods may eliminate the need for end osures.)
-31-
390690
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
SMALL-SCALE SHORT-DURATION PROJECTS WHEN GLOVE BAGS ARE NOT USED (Cont'd)
REMOVAL:
1. The materials must be wet down before, during, and after removal to prevent airborne emissions. Materials must be thoroughly wetted, but not to the point that they crumble and turn to mush. Wetting of material may be eliminated if water is not compatible with the process, or materials/equipment may be seriously damaged, or local exhaust ventilation reduces the potential exposure limit below 1 fiber/cc averaged over a sampling period of 30 minutes or 0.2 fibers/cc as an 8 hour TWA.
2. Material must be removed and placed into labeled polyethylene bags
or containers approved by Environmental Operations. Bags or containers must be lowered to the ground, not dropped. 3. The surface from which asbestos has been removed must be wetted and cleaned. 4. Exposed asbestos must be encapsulated at terminations. 5. After asbestos removal, a thorough inspection and cleanup of the area must be conducted. Pick up and dispose of coverings and odouble bag contaminated or broken bags. Vacuum the work area as required.
.6 All items removed from the regulated area must be decontaminated. A job procedure must be followed when changing HEPA filters. 7. Disposable coveralls, exposed area of skin and respirator must bs
vacuumed and boots must be decontaminated each time before exit! the regulated area.
8. Disposable coveralls must be disposed of in a sealed asbestos
waste bag. 9. Work clothes must be vacuumed off.
10. All materials used to establish the regulated area must be
removed.
11. Bags or containers must be transported to the dempster or
collection area.
-32-
390691
SECTION XI
CONSTRUCTION OF MINI-ENCLOSURES (SMALL-SCALE, SHORT-DURATION JOB)
1. AFFIX 6-MIL THICK POLYETHYLENE SHEETING TO WALLS WITH SPRAY . nur-c Ti U Ck. rvMiwfi T..fl.O. C .
2. COVER THE FLOOR WITH PLASTIC AND SEAL TO THE PLASTIC ON THE WALLS. 3. SEAL ALL PENETRATIONS SUCH AS PIPES OR ELECTRICAL CONDUIT WITH
TAPE. 4. CONSTRUCTION A SMALL CHANGE ROOM OF 6 MIL THICK POLYETHYLENE
PLASTIC CONTIGUOUS TO THE MINI-ENCLOSURE. THE WORKER USES THE CHANGE ROOM TO VACUUM OFF HIS PROTECTIVE COVERALLS AND REMOVE THEM BEFORE LEAVING THE WORK AREA.
TOT VIEW
SCHEMATIC OF MINI-ENCLOSURE
un
CHANGE ROOM
lr
SIDE VIEW
PLASTIC CURTAIN
PLASTIC CURTAIN
VACUUM HOSE
PLASTIC CURTAIN
ST00I3486
I !
-33-
390692
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
LARGE SCALE, LONG DURATION PROJECTS.
GENERAL:
1. The Superintendent/owner must contact Environmental Services (2414) a minimum of 25 days prior to starting asbestos removal work and specify a project supervisor.
2. The project supervisor must provide a written Safe Work procedure specific for each job which includes as a minimum the require ments listed below.
3. The project supervisor must meet with the industrial hygienist, safety director for the area, and personnel performing the job to discuss the Safe Work procedure and arrange for audit and monitoring.
4. The project supervisor must arrange to have a "Competent Person' for the job if the work is performed by Dow employees. If work is contracted, the contractor must provide a "Competent Person" to supervise the job.
5. Employees who work with asbestos must receive training in asbestos hazards before the initial assignment and annually thereafter.
6. Personnel in the general area must be notified that asbestos wor is in progress.
SAFETY:
1. Safety equipment required by the job location must be worn.
.2 An approved respirator must be worn during material removal and
cleanup. Employee must have completed the mandatory fit test. ... Contact 409-238-3536 for information. 3. Disposable coveralls with attached boots and hoods must be worn! during cleanup and removal operations. Coverall boots may be over work shoes or inside rubber boots. 4. "Street clothes" must not be worn underneath disposable coveralls. If work clothing is worn underneath, it must be left in the "dirty room" of the decontamination facilities. Contaminated clothing for laundering must be contained in a sealed asbestos: waste bag and laundered in a manner which will minimize the release of asbestos fibers. Personnel laundering asbestos contaminated clothing must be informed of this requirement.
.6 Vacuum and local exhaust ventilation systems must be equipped
with HEPA filters. Personnel monitoring must be done at the beginning of each jobvunless glove bags are used or personnel wear supplied air respirators or previous personnel monitoring of similar jobs shows short-term exposures below 1 f/cc averaged over a samplin period of 30 minutes or 8 hour TWA exposure potentials less th 0.1 fibers/cc. Contact Industrial Hygiene Services 409-238-128 for information.
8. A decontamination area must be provided. It must be contiguous
to the regulated area if feasible. Egress to the regulated a must be through the decontamination area. 9. Water for wetting must contain a surfactant.
-34-
3906g3
STOO!3488
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
LARGE SCALE, LONG DURATION PROJECTS (Cont'd)
CAFFTV (CONT'Dl
10. Local exhaust ventilation must be provided for hand operated or power operated tools, such as but not limited to, saws, scorers, abrasive wheels, and drills. The efficiency of local exhaust ventilation systems must be verified by Industrial Hygiene Services.
11. An Asbestos Safety Checklist must be completed for each job.
BFGUIATED AREA:
1. A regulated area must be established and asbestos warning signs posted to restrict access to authorized personnel only.
2. Area must be cleaned of existing asbestos contamination and other debris.
3. Portable objects must be removed to prevent contamination. 4. Coverings must be placed over remaining objects and underneath the
work area. Scaffold landings must be covered. Materials must not be dropped to the ground. Pre-job planning must include provisions for keeping deteriorated material in place after jacketing is removed. 5. Glove bags, mini-enclosures or negative pressure enclosures must be used for jobs whenever feasible if the potential exposure level may equal or exceed 1 f/cc averaged over a sampling period of 30 minutes or 0.2 fibers/cc as an 8 hour TWA. (Local exhaust ventilation or other engineering control methods may eliminate the need for enclosures.)
The materials must be wet down before, during, and after removal to prevent airborne emissions. Materials must be thoroughly wetted, but not to the point that they crumble and turn to mush. Wetting of materials may be eliminated if water is not compatible with the process, or materials/equipment may be seriously damaged, or local exhaust ventilation reduces the potential exposure limit below 1 f/cc averaged over a sampling period of 30 minutes or 0.2 fibers/cc as an 8 hour TWA. Material must be removed and placed into labeled polyethylene bags or containers approved by Environmental Operations. Bags or containers must be lowered to the ground, not dropped. The surface from which asbestos has been removed must be wetted and cleaned. Exposed asbestos must be encapsulated at terminations. After asbestos removal, a thorough inspection and cleanup of the area must be conducted. Pick up and dispose of coverings and double bag contaminated or broken bags. Vacuum work area as required. ' All items removed from the regulated area must be decontaminated. A job procedure must be followed when changing HEPA filters. All materials used to establish the regulated area must be removed. Bags or containers must be transported to the dempster or collection area.
-35-
390694
STOOI 3489
SECTION XI TYPICAL DECONTAMINATION'AREA
LAYOUT
WORK AREA DOUBLE FLAP
EQUIPMENT/DIRTY CHANGE ROOM DOUBLE FLAP
SHOWER DOUBLE FLAP
CLEAN ROOM DOUBLE FLAP
f
I
,
-36-
390695
SECTION XI
DECONTAMINATION AREA (CONTIGUOUS TO WORK AREA)
ST00 I 3490
1. REMOVE GROSS CONTAMINATION FROM SUIT. 2. REMOVE PROTECTIVE CLOTHING IN EQUIPMENT/DIRTY CHANGE ROOM
AND DEPOSIT IN LABELED IMPERMEABLE BAGS. 3. WEAR RESPIRATOR INTO SHOWER AREA. 4. SHOWER BEFORE ENTERING CLEAN ROOM. 5. PUT ON STREET CLOTHES. 6. EXIT DECONTAMINATION AREA.
-37-
3^0696
SECTION XI
DECONTAMINATION AREA (At a Remote Location)
1. VACUUM PROTECTIVE --CLOTHING AND EQUIPMENT.
2. REMOVE CONTAMINATED CLOTHING. 3. PUT ON CLEAN SUIT AND PROCEED TO
DECONTAMINATION AREA WEARING RESPIRATOR. 4. DEPOSIT CLOTHING IN DIRTY CHANGE ROOM. 5. WEAR RESPIRATOR INTO SHOWER AREA. 6. SHOWER BEFORE ENTERING CLEAN ROOM. 7. EXIT DECONTAMINATION AREA.
ENTRY
1. ENTER DECONTAMINATION AREA THROUGH CLEAN ROOM.
2. REMOVE AND DEPOSIT "STREET CLOTHES" IN LOCKER
3. PUT ON PROTECTIVE CLOTHING AND RESPIRATORY PROTECTION (STRAPS
UNDER HOOD). 4. PROCEED TO WORK SITE ANO ENTER
ENCLOSURE/REGULATED AREA THROUGH EQUIPMENT ROOM.
390697
-38-
ST00I3492
SECTION XI
EXAMPLES OF NEGATIVE PRESSURE SYSTEMS
Ab
DF, Decontamination Facility; ED, Exhaust Unit; HA, Worker Access; A, Single-room work area with multiple windows; B, Single-room work area with single window near entrance; C, Large single-room work area with windows and auxiliary makeup air source (dotted arrow). Arrows denote direction of air flow. Circled numbers indicate progression of removal sequence.
-39-
390698
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS
AUTOMOTIVE CLUTCH AND BRAKE REPAIR
GENERAL:
1. Employees who work with asbestos must receive training in asbestos hazards before the initial assignment and annually thereafter.
2. Do NOT use compressed air to remove asbestos materials or dust from brake drums or clutch housings.
3. Place polyethylene sheeting underneath the work area.
SAFETY REQUIREMENTS:
1. Safety equipment required by the job location must be worn. 2. An approved respirator must be worn during material removal and
clean up. Employees must have completed the mandatory fit test. Call 409-238-3536 for information. 3. Barricade area with yellow tape or rope to limit access.
REMOVAL
1. Two methods can be used to reduce exposure to asbestos fibers. The Enclosed Cylinder/HEPA Vacuum System Method and a wetting method.
A. The Enclosed Cylinder/HEPA Filter Vacuum System Method consists of three components.
* A wheel-shaped cylinder designed to cover and enclose the wheel assembly
* A compressed-air hose and nozzle that fits into a port in the cylinder, and
* A HEPA-filter vacuum used to evacuate airborne dust generated within the cylinder by the compressed air.
B. The wetting method consists of spraying water containing a surfactant to loosen the asbestos containing residue and to capture the resulting airborne particles in the water mist.
* Begin spraying the asbestos-containing parts at a sufficient distance to ensure that the asbestos particles are not dislodged by the velocity of the water spray.
* When the asbestos particles are thoroughly wetted, the spray will be brought closer to the parts and the parts will be sprayed as necessary to remove grease and other material.
* The parts must then be wiped with disposal rags or towels which must be placed in a labelled plastic bag and sealed-, while they are still wet.
1
390699
-40-
STUD I 34y
SECTION XI
ASBESTOS ABATEMENT MINIMUM REQUIREMENTS AUTOMOTIVE CLUTCH AND BRAKE REPAIR (Cont'd) 2. Replaced brake shoes or pads, clutch plates, disposable rags or
towels, polyethylene sheeting and other contaminated materials for disposal must be handled as asbestos waste. 3. When the job is completed, a thorough inspection must be made to ensure all asbestos contaminated materials have been picked up. Vacuum work area as required. A job procedure must be followed when changing HEPA filters.
:l
fi
-41- 390700
SECTION XII ASBESTOS SAFETY CHECKLIST
JOB DESCRIPTION LOCATION
DATE
PRE-JOB REQUIREMENTS:
1. Environmental Services contacted (ph 409 238-2414)? Yes__ No
Name:
_____
Date:
Dow Project Supervisor:
2. Safe Work Procedure Written? Yes No Date:
3. Project Review Held?
Industrial Hyqienist:
Date:
Safety Director:
Date:
Competent Person:
Date:
Craftsmen:
Date:
Safe Work Procedure Approved:
Yes No
Hygiene Monitoring Required:
Yes No
Audit Required:
Yes No
Auditor Assigned
Phone:
JOB REQUIREMENTS:
1. Safe Work Procedure Reviewed:
Yes No
2. Regulated Area Established and Signs Posted: Yes
No
Negative pressure enclosure established:
Yes No
Decontamination Area Established:
Yes No
3. Personnel Trained:
Yes No
4. Block Personnel Informed:
Yes No
5. Auditor Notified:
Yes No
6. Amended Water Available To Control Dust:
Yes No
7. Has packaging of asbestos debris been
decided upon?
Yes No
8. Has Disposal Of Asbestos Debris Been
Arranged:
Yes No
9. Arrangements For Clean-up Made:
Yes No
10. Safety Equipment Required:
Safety equipment required by the location
Approved respirator current fit test clean shaven
Disposable coveralls with hood and boots qloves
11. Arrangements for laundering work clothes
Yes No
12. Vacuum cleaners and local exhaust ventilation
systems equipped with HEPA filters
Yes No
Note: Work may commence when Safe Work Permit issued.
13. Final cleanup complete
Yes____ No____
14. Job complete: Dow Project Supervisor: Date:
15. Send completed checklist to Industrial Hygiene Services 8-101._
-42-
390?0)
STOOI 3496
SECTION XIII
ASBESTOS ABATEMENT AUDIT CHECKLIST
Job Description
Date:
Location:
Removal by:____________________ Company Name
1. Regulated Area Established and Signs Posted: Polyethylene or other coverings over floor &
objects:
YES NO YES____ NO
2. Decontamination Area Established: Contiguous Remote: Location:
YES NO
Entry to work area only through decontamination
area
YES
NO
3. Negative Pressure Enclosure Established: Floor Covered Walls Covered Area Ventilation OFF All Edges Sealed Penetrations Around Pipes and Conduit Sealed Entry Curtains Negative Pressure Achieved (-0.02" water)
YES NO YES NO YES___ NO YES NO YES NO YES NO YES NO YES NO
Protective Equipment: Disposable Coveralls with Hood and Boots Coveralls Unzipped, Torn, or Cut Coveralls Used One Time Approved Respirator Type Used Clean Shaven Straps Under Hood Safety Equipment Required by Location: Hard Hat Safety Glasses Goggles
YES___ NO YES___ NO___ YES___ NO YES NO
YES___ NO YES___ NO;
YES___ NO YES___ NO YES NO
390702
-43-
SECTION XIII
ASBESTOS ABATEMENT AUDIT CHECKLIST
5. Work Practices: Material Worked Wet Material Kept Wet Until Bagged &Sealed Material Too Wet, Mushy Insulation Broken Intentionally Material Dropped to Ground Removed Material Promptly Bagged Bags Torn or Left Open Visible Emissions HEPA Filtered Vacuum Used Smoking, Eating, Drinking, Chewing, Cosmetics Personnel Decontaminated Each Departure Shower Used by All Personnel Exposed Asbestos at Terminations Sealed with Encapsulant Work Area Cleaned After Completion
6. Personnel Monitoring Initial Monitoring
Daily Monitoring Area Monitoring
Contractor Dow
COMMENTS:___
YES___ NO YES___ NO YES___ NO YES__ NO] YES__ NO] YES__ NO] YES__ NO] YES__ NO] YES__ NO" YES__ NO] YES__ NO] YES__ NO]
YES__ NO i'ES__ NO]
YES__ NO_
YES__ NO YES__ NO]
SIGNATURE: __________________________________________ Industrial Hygienist/Safety Director
cc: Project Supervisor Area Owner Safety Director Industrial Hygienist Manager, Industrial Hygiene Services
Revised 10/20/88 db
390703
-44-
am m m
APPENDIX A RECOMMENDED PROTECTIVE EQUIPMENT
bThuet eisqunipomt ennet cleisstseadrilybetlhowe ohanslybeeeqnuipjumdegnetdatvoaiblaebtlhee. bOestht efrotrypaessbeostfosrepsrpoirteactotiro?n*TM Identified in Appendix C of the Texas Operations Respiratory Protection Manul?
(2/88)- The equipment listed below represents the p?,fer?M
b* on
^Ecquurripemnet nttecwhhnicohlogisy nanodt klinsotweldedgbeeloawt othreintimAeppoenf dpixubClicoaf titohne oRfetshpiisraAtosbr epstoJsoteS
Hsneal should not be purchased or used unless the Texas Operatic Protect?TM
Equipment Committee (1281) has evaluated the equipment.
Protective
HSii. Hed,C1'
inti MWcSSJSS conductednbyCthe^Occupatlonal
v
a a
E.T ll respirators can be ordered through the Dow Stores (3401), or via Purchase Order.
.RESPIRATORY PROTECTION FOR ASBESTOS
OJ
KJd cc
^Airborne Asbestos
Manufacturer
VSP Number
ResDirator
Cartridoe
< 2 fibers/cc
Half-Mask Air Purifying
Is Y.
AO 5 STAR - Silicone small medium large
AO 5 STAR - Rubber small medium large
01-04175-000 01-04175-010 01-04175-020
01-04173-000 01-04173-010 01-04173-020
01-040680-500 01-040680-500
Wilson 6100 - Silicone small medium large
01-04280 01-04282 01-04284
01-04285
MSA Comfo II - Rubber small medium 1 arge
01-04122 01-04124 01-04126
01-04252
-45-
390704
I. RESPIRATORY PROTECTION FOR ASBESTOS (Cont'd)
Airborne Asbestos
Manufacturer
4
4
VSP Number
Respirator
Cartridge
i
< 10 f/cc
Full Face Air Purifying
Scott-O-Vistal Scott-0-V1sta2
Scottoramic AO 7 STAR
01-04335 01-04335 01-04420 01-04190
< 20 f/cc
Powered Air Purifying Respirators
Racal BE7/P3
01-04805
< 200 f/cc
Supplied Air Pressure Demand (Full Face)
Scottoramic
01-04625
Scott-O-Vista
01-04630
SCBA Pressure Demand (Full Scott IIA Scottoramic
(30 minute) Scott 2.2, Scott-O-Vista
(30 minute) Scott 4.5, Scott-O-Vista
(60 minute) Scott Case
Face)
01-04520 01-04510
01-04512
01-04666
II. RESPIRATOR CARTRIDGES FOR A COMBINATION OF ASBESTOS k CHEMICALS
01-04193 01-04196 01-04193 01-040680
01-04810
NA NA
NA NA NA
vi
Respirator Manufacturer American Optical 5 & 7 STARS
MSA Comfo II
Cartridge Protects Aaainst:
Organic vapors & asbestos Acid gases & asbestos Organic vapors, acid gases & asbestos Ammonia, amines & asbestos
Organic vapors & asbestos Acid gases & asbestos Organic vapors, acid gases & asbestos Ammonia, amines & asbestos
Part Number
R51HE R52HE
R53HE R54HE
464029 464028 464027
464026
Supply .a Source j
Safety Shoe 233-0605 3
iZm
Safety Shoe 233-0605 ]
c c
o: jr u: u;
Ijhis Scott-O-Vista facepiece uses a twin cartridge adapter (Scott Part No. 802451-01) which is purchased separately from the facepiece (VSP Number 01-04342)
2jhis Scott-0-Vista facepiece uses a single canister adapter (Scott Part No. 802472-01 which is purchased separately from the facepiece (VSP Number 01-04340).,
-46- 390705
II. RESPIRATOR FOR A COMBINATION OF ASBESTOS & CHEMICALS (Cont'd)
Respirator Manufacturer
Cartridge Protects Aaainst:
Part Number
Supply Source
COtt-0-Vista1 Willson 6100
Organic vapor & asbestos Acid gases & asbestos Organic vapors, acid gases & asbestos Ammonia, amines & asbestos
Organic vapors & asbestos Acid gases & asbestos Organic vapors, acid gases & asbestos Ammonia, amines & asbestos
642-OV-H 642-AG-H
642-OA-H 642-AM-H
T41 T46
T45 T44
Vallen 265-8176
Briggs-Weaver 233-5451 VSP 01-04286
*Thi!
liece uses a twin cartridge adapter Scott (Part 802451-01)
lich is purchased separately from the facepiece itself. (VSP number: 01-04342)
CLOTHING
Tyvek disposable Paper Coveralls with attached Hood and Boots
Small Medium Large Extra Large
01-03551-001 01-03552-001 01-03553-001 01-03554-001