Document QgQ3ZLMEBKZ13OmxExaGb0mr8
ABD00019053
2003 Internal Health and Safety Audit Aberdeen
Final Report
DRAFT
ABDOOO19054
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT PAGE 2
2/28/03
1. Introduction
This report summarizes the results of the 2003 Internal Health and Safety Audit at the Aberdeen, MS facility conducted on 2/18/03 to 2/20/03
2. Purpose
The internal health and safety audit program covers the health and safety programs and associated procedures of Georgia Gulf Corporation Although a strong emphasis is placed on compliance with applicable regulations and corporate policies, the ultimate goal is continuous improvement of the health and safety management system
The objectives of the audit are to 1 Provide management with a tool to evaluate the continuous improvement of the health and safety program
2 Evaluate the written health and safety management systems to ensure elements required by OSHA regulations are in place
3 Ultimately, improve the health and safety of the workplace environment
This report is not intended to imply legal certification of compliance or noncompliance
3. Scope The Prairie Audit assessed the following modules Fire Prevention and Emergency Action Plans Confined Space Entry Means of Egress Lockout/Tagout Electrical Safety Power Industrial Trucks Hearing Conservation Hazard Communication Walking and Working Surfaces Contractor/Visitor Safety program Personal Protective Equipment Hoisting Equipment Machine Guarding Incident Investigation Chemical Storage Review Audit Action Items
ABDOOO19055
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT PAGE 3
2/28/03
4. General Audit Technique
The audit was conducted on site on 2/18/03 to 2/20/03 The audit included Physical inspections of the facility, Document reviews of written health and safety programs, policies, and procedures as well as safety, administrative, and operating records, Interviews and discussions with facility management, staff, and employees (where applicable), and Verification of the facility's application of, and adherence to applicable OSHA regulations and related and facility policies and procedures
The process by which the audit was conducted is consistent with accepted health and safety auditing protocols and the professional judgment of the audit team members
5. Audit Team
The audit was conducted using an audit team knowledgeable in the topics being audited and the basic audit process The audit team consisted of Dwight Dobbins, Safety Technician (Oklahoma City), Emmitt Cavalier Safety Engineer (Madison) and Fred Wisbar, Safety Engineer (Plaquemine)
6. Follow-Up on Audit Findings
After receiving the audit report, the Plant Manager should ensure that a written plan of action is developed to address the audit findings
The action plan should include A list of corrective actions (or reason why no action is necessary) A timetable for implementation of corrective actions Responsibilities for implementation
Note The corrective actions should be entered into the company tracker and forwarded to the Corporate Audit Coordinator as soon as practical
A status report on progress in achieving the items detailed in the written action plan should be submitted to the Manufacturing Manager and the Corporate Audit Coordinator every quarter until all corrective actions have been completed
ABDOOO19056
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT PAGE 4 7. Audit Opinion
2/28/03
For each module, the auditors developed an opinion as to the implementation of safety management systems at the facility as follows
Module
Hazard Communication Confined Space Entry lockout/Tagout Means of Egress Fire Prevention and Emergency Action Plans Contractor/Visitor safety program Walking and Working Surfaces Power Industrial Trucks Electrical Satety Hearing Conservation Powered Industrial Vehicles Hoisting Equipment Personal Protective Equipment Machine Guarding Incident Investigation Chemical Storage Review Audit Action Items
Requires Significant Improvement
Requires Improvement
Generally Meets
Meets
Substantially Meets
Description of Audit Opinion Categories:
Substantially Meets Governmental and Internal Requirements The audit results substantiate a high degree of compliance The facility is in compliance with most of the applicable requirements reviewed but only a few requirements were not satisfied These departures are considered to represent isolated exceptions in an otherwise effective compliance program
Meets Governmental and Internal Requirements The facility is judged to meet all (or virtually all) applicable items included in the audit scope For those very few requirements where isolated exceptions are noted, these departures are determined to be occasional and anomalous and are considered inconsequential in comparison to the overall level of compliance achieved It is intended for locations that are found to be in full compliance with applicable requirements
Generally Meets Governmental and Internal Requirements Except as Noted Several exceptions to applicable requirements are noted These exceptions are more than isolated anomalies and reflect weakness in the design and/or implementation of compliance programs
Requires Improvement to Meet Governmental and Internal Requirements Several exceptions to applicable requirements are noted and some of the exceptions reflect the absence of required programs, significant departures from established criteria, or lapses in program implementation
ABDOOO19057
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
2/28/03
PAGES
Requires Significant Improvement to Meet Governmental and Internal Requirements Many exceptions to applicable requirements are noted, including several significant departures from established criteria, the absence of several required programs, or prolonged inattention to the resolution of previously identified issues
8 Specific Audit Findings
8.1 Fire Prevention and Emergency Action Plans 29 CFR 1910.155 8 1 1 Consider repairing the 2" mam sprinkler pipe that is protecting the reactors (break is on deck under the condenser RX 700) as soon as practical This is a critical line of defense for our reactors 29 CFR1910 38 (b)(2)(i)
8.2 Means of Egress 29 CFR 1910.35 8 2 1 Consider reviewing exit signs in the plant Some need to be installed and some need to be repaired 29CFR 1910 36 822
8.3 Electrical Safety 29 CFR 1910.333 83 1 Consider reattaching the ground on vessel 87-475 29 CFR1910 106 (e)(6)(H) 8 3 2 Consider labeling electrical box on 2nd floor and roof of compound plant 29CFR 1910 303(f) 8 3 3 Consider putting appropriate covers on conduits in the following locations Compound plant - Bagging area by forklift entrance top north and south side 29 CFR 1910 305(b)(2) 8 3 4 Consider a proper plug on an electrical box over the #8 bird It is presently covered by electrical tape 29 CFR1910 305 (b)(2) 8 3 5 Consider replacing a missing breaker cover (B-13) on what appears to be a live system XXXXXXXX 8 3 6 Consider removing old wiring and capping conduits in the old sample line area 8 3 7 Consider removing or replacing temporary wiring (extension cord) with permanent wiring by substation #5 XXXXXXXX 8 3 8 Consider establishing a PM/inspection program for GFCI At the time of this audit proof could not be established of testing GFCI 29 CFR 1910119
ABDOOO19058
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
2/28/03
PAGE 6
8.4 Powered Industrial Vehicles
29 CFR 1910.178
8 7 1 Consider developing and documenting monthly inspections of cranes
critical items (i e brakes, crane hooks) Documentation could not be
provided at the time of this audit Also noted was a missing safety latch
on the Grove crane 29 CFR1910 180 (d)(6)
8 7 2 Consider installing a load rating on both sides of your cranes 29
CFR1910 179 (b)(8)
8 7 3 Consider establishing a daily documented inspection program for
forklifts, cranes, man lifts, pallet jacks and industrial vehicles Although a
inspection system is on the back of some forklifts there is evidence
showing that inspections are not being done (forklift M39712 with out a
horn) (missing inspection cards - M391006, M39712, M39712, 50,
M391006, M39356 and M390094) Pallet jacks are not under any type
of inspection program or repair program
8 7 4 Rail car unloading PA was not chocked properly Other incidents of not
chocking or chocking improperly were noted during this inspection
CFR1910 1 78 (k)(2)
8.7.5 Consider developing a monthly inspection and certification program for
the crane's running ropes CFR1910 180 (g)(1)
8.5 Confined Space Entry
29 CFR 1910.146
8 5 1 Consider reviewing the status of what makes a Permit Required
Confined Space Several Confined Spaces appeared questionable i e
boiler entry, hydro blasting the condensers on the reactors 29 CFR
1910 146
8.6 Lockout/Tagout (Control of Hazardous Energy) 29 CFR 1910.147 8 6 1 Consider reviewing lockout tagging procedures In MCC (compound) lock was noted with out identification 29 CFR 1910 147
8.8 Hearing Conservation
29 CFR 1910.95
8 8 1 Consider ensuring the noise level drawing on site At the time of the
audit this record could not be produced 29 CFR 1910 95(b)(1)
8 8 2 Consider placing hearing protection signs where needed 29 CFR
1910 95(b)(1)
ABDOOO19059
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
2/28/03
PAGE 7
8.9 Hazard Communication 29 CFR 1910.1200 8 9 1 Consider installing HazCom labeling through out the plant there were some vinyl tanks marked but the rest of the plant needs consideration XXXXXXXXX 8 9 2 Consider reviewing drums that are stored in the "old chiller "building Some are marked as water/glycol others are not marked XXXXXXXX 8 9 3 Consider installing a Hearing Protection sign by the door way leading to the compressor area at the compound unit 29 CFR 1910 1200 8 94 Consider placing signs that designate hearing protection required hard hat safety glasses in the appropriate place in the compound area 29 CFR 19101200 8 9 5 Consider removing the lead signs If lead is no longer an issue 29 CFR 1910 1200 8 9 6 Consider replacing the caustic unloading sign It is very worn 29 CFR 19101200 8 9 7 Consider reviewing the use of DMS for MSDS with employees Some employees did not know their password or how to use DMS Most employees knew where the back up copies are stored some did not 29 CFR 1910 1200(h)
8.10
Walking and Working Surfaces 29 CFR 1910.176 8 10 1 Consider repairing in the interlock on the elevator (1st floor) of the make
up area The bottom floor protective cage was open while the elevator was on the 2nd floor Leaving a hazardous open area for someone to walk into 29 CFR1910 23 (a)(2) 8 10 2 Consider installing handrail on top of the Recovery building This is used as a work area were only partial coverage of the roof is guarded by handrails 29CFR1910 23 (a)(3) 8 10 3 Consider installing handrail on top of the "old chiller" building There is access to the roof and handrails guard only part of the roof 29 CFR1910 23 (a)(3) 8 10 4 Consider a total clean up of the "old chiller" building (wet floors, tripping hazards and is used as an "unorganized" storage area 29 CFR1910 23 (c) 29CFR1910 22 (a)(2) 8 10 5 Consider repairing temporary flooring that has foot size holes in the old sample line area 29 CFR1910 23 (a)(8)(i) and (n) 8 10 6 Consider re-stripping the yellow VCM borders 29 CFR1910 23 (a)(3)
8.11 Contractor/Visitor Safety Program
29 CFR 1910.119(h)
8 111 Consider including your contract security in your PSM audit system
29 CFR 1910 119(h)(2)(v)
ABDOOO19060
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
2/28/03
PAGE 8
8.12
Hoisting Equipment 29 CFR 1910.184-219-179 8 12 1 Consider developing and documenting a program for sling inspections
No documentation could be provided at the time of this audit Note Sling in cyclone dryer building area is in very poor shape and should be replaced as soon as practical 29 CFR1910 184(e)(3b)(i)and (n) 8 12 2 Consider reviewing all chain falls through out the plant The auditor noted several hooks with missing safety latches and load rating capacities 29 CFR1910 184 (d)
8.13
Personal Protective Equipment 29 CFR 1910.132 8 13 1 Consider enforcing the clean-shaven policy for permanent employees
several employees were noted with facial hair growth that would not produce a adequate respirator fit 29 CFR 1910 132 8.13.2 Consider enforcing the hearing protection program employees were noted not wearing their hearing protection 29 CFR 1910 132
8.14
8.15 8.16
Machine Guarding 29 CFR 1910.212-217
8 14 1 Consider replacing the protective guards on the Kneader(s) in the
compound plant XXXXXXXXX
8 14 2 Consider reviewing and securing machine guarding on pumps in the
recovery building {West side) XXXXXXXXXXX
8 14 3 Consider replacing the machine guarding on the top of the slurry tank
(SW corner) that has fallen off XXXXXXXX
8 14 4 Consider replacing the guards on the Stearate Feeder to #10 cyclone
XXXXXXXX
8 14 5 Consider a plant review of Machine Guarding XXXXXX
Incident Investigation
29 CFR 1910.119
8 15 1 Consider updating incident investigation form to include the start date
of the investigation
Note This was also a Recommendation from the 2001 PSM audit It was
not one of the recommendations that was audited
Chemical Storage 29 CFR 1910.106
8 16 1 Consider marking the types of hazardous materials stored in the
Hazardous materials storage area (Compound plant) 29 CFR 1910 106
8 16 2 Consider installing a containment area around the chemical storage
area (Compound plant) 29 CFR 1910 106
8.17
Review of Audit Action Items A representative sample (6 of 30) of closed recommendations were picked from the past PMS and Health and Safety audits Out of the 6 that were pick 2 appeared partially completed they are as follows
ABDOOO19061
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
2/28/03
PAGE 9
1 2/2002 H&S audit (no reference available) - 2of 3 were complete Requirements for blue flags and derails on tracks when railcars are connected or personnel must work on or near the railroad tracks Closure comments indicated procedures were revised At the time of this audit supporting evidence could not be provided
2 5/2001 PSM Ref 9 2 4 The IRD Data logger used for vibration analysis is not being calibrated on an established schedule - The Closure comments states - IRD data logger has been sent out for caibration PM set up for this The IRD logger was sent out for calibration but is now overdue A PM program could not be provided at the time of this audit
3 See 8 15 1
8.18 Other Areas of Interest 8 18 1 Consider repairing a major crack the runs from top to bottom of the Recovery building (4 floors, can see through the cinder block) XXX 8 18 2 Consider reviewing weep holes on relief valves two of ten Relief valves check had weep hole plugged (yellow RV top of recovery building and large RX West side of plant floor below the condensers) 29 CFR 1910 119 8 18 3 Consider replacing asbestos siding on the dryer building Friable asbestos tn visible in multiple places due to forklift damage 29 1910 1001 8 18 4 Consider installing overhead clearance markings for piping over plant road XXXXXXXXXX
ABDOOO19062
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT PAGE 10
2/28/03
8 18.5 Consider removing a Chicago coupling located in the recovery area It
is on a line from the seal water separator to the coupling
Environmental markings are located on other valves on this line but not
on the Chicago coupling which is open to the atmosphere LDAR
8 18 6 Consider removing friable asbestos from the bottom of an old
suspending agent tank 29 19101001
8 18 7 Consider removing friable asbestos from the "old chiller" building CFR
29 19101001
8 18 8 Consider the removal of the "old chiller" building Appears the floor is
sinking (informed that a sump is located under the floor) along with the
above issues this building appears to have multiple safety liabilities
8 18 9 Consider developing a ladder inspection program
8.19 Good Management Practices (GMP)
8 19 1 Consider installing a car seal program for your AMS kill system (main and nitrogen) Car seal valves in their correct position CMP
8 19 2 Consider fixing the latch on the Hydraulic instrument box under RX 700 It is wired shut GMP
8 19 3 Consider updating your Contractor Qualification form to indicate the OSHA 300 log is required GMP
8 3 9 Consider total decommission of the old electrical panel in the "old chiller" building This area has exposed wiring missing panels and poor out of service labeling There are also some live boxes within this system GMP
8 19 4 Consider securing the instrumentation on the top of RX 400 GMP 8 19 5 Consider enforcing the plastic side shield policy GMP 8 19 6 Consider updating the emergency response plan to indicate
manpower changes 8 19 7 Consider moving fire extinguisher#105 in maintenance shop - air hose
reel could limit access GMP 8 19 8 Consider moving break area in maintenance shop It is located in the
work area next to operating equipment GMP
ABDOOO19063
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
2/28/03
PAGE 11
8 19 9 Consider upgrading identification of breakers in 120v panels Though
out the plant GMP
8 19 10
Consider replacing signs that are faded CMP
8 19 11
Consider labeling activator pits with Confined Space Entry
required signs
ABDOOO19064
ABERDEEN INTERNAL HEALTH AND SAFETY AUDIT REPORT
PAGE 12
AUDIT FEEDBACK FORM
Aberdeen, MS
2/18/03 to 2/20/03
Strongly Disagree
1 The audit objectives were clearly communicated to me
J The audit took an acceptable amount ot time (Irom entrance to exit)
1 The disruption of dailv activ ities was minimized as much as possible during the audit
4 My concerns (such as interxiews, schedules, etc ) on the manner in which the audit was conducted were adequately considered
r) Communication ot the progress ol the audit and immediate concerns was timely and adequate
f> The audit team demonstrated technical proticiencv in the audit areas
7 The audit team demonstrated courtesy professionalism and a construe tive approach during the audit
8 I he audit team s conclusions were logical and substantiated
<) Audit results were accurately reported and appropriate perspective was provided
10 The audit report was clearly written and logicallv organized
11 Overall the audit will add value" to my safety management system
Disagree
Neither Agree
nor Disagree
Agree
2/28/03
Strongly Agree
No Basis
Comments on any of the areas listed above or other items noted during the audit