Document QXqq8RwOx9zVqq7a76ZjryMQR
DEPARTMENTAL CORRESPONDENCE
DATE: 26 October 1992
SUBJECT: EB Tower Insulation Emergency Repairs
TO: G Richard
CC: RGC, GW
FROM: _MH DeBeriy
DEPT:
Planning
After reoent high winds blew corrugated metal Jacketing and asbestos offlhe Idle EB Tower? we have collected loose asbestos off the ground and set up a 150 Ton Crane at the Towers for Ire Following is a visual report and recommendations;
1. instal Mastic over all exposed insulation so that repairs can be made safely
2. Install insulation supports as needed to prevent insulation from felling from under metal jack 3. Instati corrugated metal patches over approximately 65 exposed asbestos locations on thethr 4. Instatinew oonugated metal over 5 large area exposed insulationareas
5. Instafl 20 circumferential bands where bands have broken or as needed for 5 large area patch
6. Completely replace chicken wire and mastic on top head of A-2 7. Send out bulk samples for analysis a UTlarge exposed bands of she8 on Tower A-1 and check tmin no other work, leave shell exp9. Removeloose Insulation ring flange on A-1 which is near falling.
10. Replace (1) 6" band atA-3 top head and (1) 5' band above lower exposed band on A--1
These repairs should last for about 2 years to prevent insulation and metal from taHina on person
This work can be done as a scope change to either AFE 42129 Safety Audit oi02131 Asbestos FH
Please advise if work soopeis acceptable. An Inspection report is being writtenoh UT readings
Also a bulk sample has beep tekpn andMRJs being prepared to purchase materials for this soap*
fdT}
jeZcd--icr
--< p"-)
Attached is a Summary Estimate
I ESTIMATE DETAILS EB TWR ASBESTQ&
RAM 0002261
J;> ' .iJ`S--
/
RAM 0002262
INTER-C-RPORATE CORRESPONDENCE
Date: January 16, 1992 Subject: Asbestos Removal Procedure Tof Larry Huwe From: Sharon SirgoSS
Listed below is a suggested Asbestos removal procedure with attached form.
1. Party requesting asbestos removal notifies Safety by submitting removal form to Safety with a copy to Environmental.
2. Safety verifies job and contractor procedures. 3. Removed asbestos is bagged, labelled and placed in
Coastal roll-off box located at Southside. 4. Party requesting asbestos removal notifies Safety that
job is complete.
SS92-017
cc: stennett DeLeon Dickman Benys Perkins Maldonado Pena
RAM 0002263
ASBESTOS REMOVAL FORM 1. Unit and piece of equipment asbestos removed from:
2. Quantity removed:
3. Contractor Removing Asbestos:
Name: __________________________________________________ Address: City: State&ZIP: Contact: Phone: TDH License No.:____________________________________
4. start date: Completion date:
5. Disposal charged to:__________________________________
6. Comments:
____________________________________________
original to Safety copy to Environmental
RAM 0002259