I^ p r l CORPORATION INTER-OFFICE
,-J- CORRESPONDENCE
CC E. 0. JOKES
TO Dr. R. A. Kehoe
FROM
Mr. H. K. Ball
SUBJECT
Tancred Steel Construction Company Florida Emergency Pipe Bine
a d d r es s Cincinnati
ADDRESS Tulsa
dat e
February 5 194B
We are attaching hereto copy of Mr. Phipps weekly letter of
Feb r u ar y 1 along with request for additional information re
garding an unobserved tank entry at Carrabelle, Florida. In view of the fact that the workmen involved apparently suffer ed no ill effect from the tank entries, probably no additional action is necessary. However, if you feel any steps should be taken in check-ups on these men we would appreciate your advice on this subject.
V.
HKBsJAT enc.
f
KE 0016974
mm/CCi DR. R. A.
HR* E. 0. JONES
W. H, Phipps
H. K. Bail /
Tancred Steel Construction Company Florida Baergency Pipe Line
Jacksonville
Tulsa
.
February 5* 1948
Dear Bont
We note your weekly letter of February 1 in which you advise that subject construction company dismantled an 80,000 barrel tank apparently without cleaning. You noted that the workmen had been in the tank for seven days with no illness due to the exposure encountered. No special precautions were taken for the cleaning work.
As a matter of record would you kindly send us an unobserved tank cleaning report listing names and addresses of all persons enter ing the tank and the number of hours spent in the tank. This information should be obtained very tactfully as we do not wish to alarm anyone. You should describe on the back the circumstances surrounding the work* We will then have a complete record in one place on this activity should it be- necessary to refer to it in the future
KKEtJAT
X K 0016975
tf. n. rhipps
Safety <vctivitiee '
Week ending Jan. yl, lpd-S
Jacksonville Fob * 1, 19^8
Dear Lou,
^
Thursday, I had.a lonj distance telephone call-from Mr. S. S. Staley, J V Supt. Tancred Steel Construction Company of 512 Lacy Building, Dallas, ^ Texas, regarding the lead hazard involved in the dismantling of leaded tanks at the Carrabelle* Florida water terminal of the defunct Florida Smer^nc,'/ ripe Line. X explained to him the hazards involved and immediately proceeded to Oarrabi.-lj.esf where Friday I contacted hr. I-. d Holley, Foreman for Tonered Steel, and made an inspection of the three tanks to be dismantled.
The roof, roof sup; or.tin-' structure and top rint' of plates bad already been removed from tank Lo. X9 which is an 0,000 bhl. tank, of' rivstel construction. X was told that thin tarsi: was used for leaded aviation geaolin* storage during the war, and that it had been empty for ov^r two years. The bottom war- covered with a thin layer of sludgs, rich was up to two inch?; deep in places. The sludge was wet at the time of my inspection because it was raining, however, I was tcld that it was dry before the roof wan removed. The shell was c l e m of scale, with the exc*ptioh of the area approximately twelve Inphes up from the bottom, which apparently was below the water line.
Kr. Holley stated that workmen had been working in .his tank for seven days and that to the best of his knowledge there had been no illness due to this exposure. This contractor was not aware of the lead hazard and therefore no special precautions were taken.
lank Ko. 8, which ic a 2y,000 bbl. welded tank was then inspected, she was found to have from one to two inches of dry caked sludge in it. Tank
Lo. 6, which is of the same size and construction, was found to be ir
eimilar donditlon. Both of these tanws have also been empty for over two . years. The manhole covers-and the hatch covers in the roof cf both of ' these tanks had been removed for severe! months and therefore both tanks were found to be gas free.
. The atmosphere in tank Ko. 8 was sampled with our lead analyzer and found to contain J micrograms pb./cu. ft. of air,
Kr . S .. 3 . Stn ley, Sr. Manager, Tancred Steel Const. Co. contracted' with Tank Cleaners, Inc. Jacksonville, *'H . for the cleaning of these tanks, and this work will start Monday, at which time X will be in Carrabel'le to observe the cleaning, "o t-or* dismantlin work will he done until after these tanks
X20917.02
Safety Activity Latter ek ending Jen. J.l, 19^S
have been thoroughly cleaned.
,I was advised that these three tanks ere purchased by Humble Oil
Company and thet the large on ill be erected atLaurel, Mississippi,
and the two small ones at Sunnyland, Florida.
-
Should the, Cuban Oil Ssfining Oon any'e fluid be shipped while I as
on the above job, I have arranged with Hr. Jordan to take over the
observation of these cleanings so that I may prodeed to Havana, Cuba
to observe the handling of this shipment while in transit, and to
make the first blend for Cuban Gil,
.
Curing the week six contacts were made regarding safety matters.
tours very truly,
W. K. Phipps
0016977