Document QX5MJ6vGB74m6bDRgpkw8dk0E

(conoco) Interoffice Communication To M. L. Ashby From M. C. Manion Date February 28, 1984 Subject Clarifier Repairs Attached is a plan to allow repairs to be made to the clarifier with the secondary "on-line". This plan will require: 1) the LCCP wastewater stream from the DAF unit to be shut off three days prior to the clarifier outaqe in order to adjust basin levels and stabilize the ASU feed. 2) the LCVCM incinerator wastewater to continue to flow to the LCCP north lagoon and the sump pump to be in good working order. 3) the LCVCM cooling tower blowdown to continue to flow to LCCP. 4) no plant activities to be scheduled during the clarifier outage which result in additional water to the sewer (ie. washdown or washouts). 5) close monitoring of the LCVCM effluent pH during the outage. 6) favorable weather conditions. The clarifier outage is scheduled to begin on February 29 at Q700. Repairs are expected to require a total of 40 hours. These repairs include modifi cations to the clarifier rake and the clarifier weir. Sufficient capacity is available to contain the plant's wastewater during the clarifier outage see attached tables. M. C. Manion kf cc: RAC-JWW-MLA(4)-JRH-HOA-SRA-PLF-RB-DLD-PE WC OOOOOQX03 Date 2/24 Time 1600 2/28 0700 2/29 0700 2/29 0700 1100 1200 1200 CLARIFIER OUTAGE PLAN Action 1. Shut off LCCP DAF unit wastewater. 2. Use 3" gas driven pump to empty the sludge basin into ASU. 3. Shut off the aerator in the South Basin. 4. Lower the set point on the South Basin level controller to zero. Allow one ASU lift pump to pull level down. 5. Turn on second ASU lift pump to empty the south basin as low as possible. Use the 6" diesel driven pump as necessary - do not overload the clarifier (use diesel after the electrics lose suction). 6. Allow the ASU level to stabilize. 7. Remove the polymer agitator from the clarifier inlet box. Turn off the Reaeration Basin aerator and the polymer pump and flush water. 8. Install wooden slide gate in the clarifier inlet box. Position sand bags as necessary at the bottom of the si ide gate for seal. 9. Shut off the clarifier rake and set up the 6" diesel driven pump to take suction from the clarifier and discharge into the ASU. 10. Use the sludge recycle pumps and the 6" diesel driven pump to empty the clarifier. 11. After the clarifier is emptied, wash down the clarifier and pump out. 12. Shut down the ASU lift pumps when the ASU level becomes high. 13. Set up a 3" gas driven pump to take suction from the sump in the clarifier and discharge into the ASU to remove water if leakage occurs thru the slide gate. 14. Set up the 6" diesel driven pump to take suction from the clarifier inlet box and discharge into the ASU to maintain circulation in the ASU - leave ASU aerators on. VVC 000008104 Date 2/29 Time 1200 40 3/2 brs. 0400 0400 0400 0400 0430 0430 0500 0500 Action 15. Secure all ladders with ropes when entering clarifier for main tenance. Set up scaffolding and lighting as necessary. 16. Make repairs to clarifier rake, clarifier weir and south basin level control valve. 17. Remove the 6" diesel driven pump from the clarifier inlet box. 18. Remove the 3" gas driven pump from the clarifier. 19. Turn on the polymer pump and flush water. 20. Open the slide gate slowly and allow the clarifier to fill. 21. Start the sludge recycle pumps and clarifier rake. Start the reaeration basin aerator. 22. Install polymer agitator. 23. Start up ASU lift pumps. 24. It is important to bring levels down slowly as not to overload the clarifier (700 qpm max). 25. After basin levels have returned to normal, line the LCVCM CT-50 blender back to the LCVCM secondary. WC 000008105 000008106 Flow 300 350 400 450 500 T-701 W Basin 15.5 13.3 11.7 10.4 9.3 T-703 S Basin 47.6 40.8 35.7 31.7 28.5 TABLE I CURRENT AVAILABLE CONTAINMENT TIME (2-24-84) Containment Time (Hrs.) Subtotal T-702 T-701; T-703 ASU Total T-701, 2, 3 63.1 54.1 47.4 42.1 37.8 26.3 22.5 19.7 17.5 15.8 89.4 76.6 67.1 59.6 53.6 NOTES: 1) Based on a maximum basin level of 1.0 ft below the top of basin. 2) Based on levels measured on 2-24-84: Basin T-701 T-703 T-702 T-706 "C" (Inches) 90 95 61 54 Available Volume (MGAL) 279.7 856.3 473.3 74.4 3) Normal flow is approximately 400 gpm. 4) "C" is the length of the exposed basin from the top of basin to water level. < o T-706 Sludqe Basin 4.1 3.5 3.1 2.8 2.5 Flow _9HL 300 350 400 450 500 T-701 W Basin 23.4 20.0 17.5 15.6 14.0 TABLE II CONTAINMENT TIME AVAILABLE AFTER LOWERING LEVELS T-703 S Basin Containment Time (Hrs.) Subtotal T-702 T-701; T-703 ASU 68.1 58.4 51.1 45.4 40.9 91.5 78.4 68.6 61.0 54.9 42.7 36.6 32.0 28.5 25.6 Total T-701, 2, 3 134.2 115.0 100.6 89.5 80.5 T-706 Sludqe Basin 7.9 6.8 5.9 5.3 4.7 NOTES: 1) Based on a maximumi basin level of 1.0 ft below the top of basin. 2) Based on 1owering basin levels as follows: Basin T-701 T-703 T-702 T- 706 Current Level (ft) 7.84 7.61 9.18 2.99 Amt Lowered (ft) 1.84 1.61 1.18 1.00 "C" (Inches) 130 130 87 81 Available Volume (MGAL) 420.4 1,226.2 768.3 142.2 3) Normal flow is approximately 400 gpm. 4) "C" is the length of the exposed basin from the top of basin to water level. VVC 0 0 0 0 0 8 1 0 7 OVO I--ir--. -oco>- LO 1 CO r-- C\l ro 4-j > O r-H t-- o r-. I-- oo un OO o o *Q- <M oo VO i--H CT) CO r~- VO TABLE IA CURRENT AVAILABLE CONTAINMENT TIME (2-28-84) CNJ c ro I--I GO co rt o vo OO CM oo CM tn ld o co CSJ t--< oo 1-- o m r^ 4-J 1 O 1-- +-> O " 3 -H VO O r". i t-- OO oo st CO uo cr> cn oo r-. r'- vo LO LO 3" e OO -- o to r-* ro 1 CO 1-- oo r-^ o uo a* 'cr o CNJ LO o vo VO LD st oo e O t/i r- ns 1 CO l-- 2 VO CT"i <Ti . r-H co LO OO CNJ i H i 1 r-t --H F 1 S= o _ LU n1=\0 o o CD CD CD o LO O UO o 00 oo st cr uo fiOn JD 4o ,--. __1 Cl < O CD -M s: . S"S QT--t 11 0) .E QJ r-- +- E QJ 3 r-. --* > 3 !-- OJ o o st 1-- *=Q- l r-- 1-- D> no oo uo i <u room E JD CD 7-- r-- (-H LO 4-> _D CD 4- 03 r" Q o r 03 t--t > 4-J 3 co <c 4- 1 O LO O CO CvJ 1 C QJ CNJ > QJ E Q CJ1 r-- O VO T3 o OJ OJ o E -D J= s- co r-- Q> VJ 3 to S- E LI3 IN CO Irt 11 <0 3 i--i OHlfl fl uo to r-H i-H QJ C- fO r E O) E QJ O 4-> 3 E2 4-> QJ E r- vo X 03 QJ E> OE 2 E o QJ n3 r-- s o 1-- c E E --l CO CNI VO 4-- o O F-- O O CD CD to r-- r^. i--. i-- i-- TO TJ fO 1 I 1 1 03 0> QJ CO 1-- 1-- 1-- 1-- 3 VO VO fO ftJ uo CO CQ LU 4*J VJ *sC of-- ---n z l-t CNJ CO VVC 000008108 (- f t I _r c <n <-- &ooooo o v cd oo p- VVC 000008110 v-li' IT (, -- A \y^ U1 t r* o r4 *^> oc u o 0Q o t-0 1 WnJ ' SaJ 5 r s i \ *A 1 1 ^-- --n s - *! *x o Q (* -- rj -J ry u --o c c, C; n e> r:i Stl 0 O C ~y CJ ---J o o rsi v4 -o vr o tl o t rvi $ 'i r^. 0 c tfCM p t/b U T / r/4 i t * snt?tr Sk S e~- >/ ^J A r* o V-4 sr . *$* r-j A r1 <3j--. ^3/ o f> t^_ ?Q J s i T> A --0 w\ VJ c* & i S? $ W o A t7" TT- Ss X> -c. -f* <S A r, C> **s -A *? ta rst j_Q rv A *wS r ^____ .-____ <v_ \1 *s n rs ta <*) % 03-- :Xp v rv Oi ^5" T5- *v \ im A Sw VvJ IT'- r* -J IT" 5k A a -Ji r> < * j | /j i i | i i 1 i i vvc 112000 008 .571-A a-ur .*sfV ! , . TSidHi/s amoV-vHHnj. tpoM 7733siw <WV 8 fro g SSV7-3 G-LASS BOMB AA/P Mt'scELLWOt/S TVR^AA 0 W S *-;: ac AT/OV AA/P PSCH! Pr/6tJ PATS r/Afir V'C.M FPC \/CfiA Sr~AyiS 3-<SJ3 2/30 /% V d~ $T/y>S 236 o C - PO 2. . o/f-t ^-S'3f3 -------------------------------------------------7------------------------------------------------ cy &/. 3'S-X3 00 3 o o/3o <2-/03 0/0 J -5 -*3 0 2 o o 0. 937% 'rzi-X // X* ?/? /ijL iTO C -2c ^ >// 3r'&5 0 2</S 3? 5^ 3^ <r*o (to!***. 3-S-J3 <D 330 3 <??<> /V7J0 ---------------------------d-------:--^--O----i---------o-f-/1/-9-------------------------------------------- 3-S-S3 C - ? 0 3 0 /// - -- - ---------------- / 3 -S- 23 <77 o s-^c_ bb Co /. 3-S-hh ooo to </so O S*& ( 7 9 3.$e*0 /V/30 __/_Sc'___7__0_ C -/ o 3 R-3o*> i- ici 3~-23 a S/S' 3'?-}?> OScrO S-/-A 5 r3~2 3 ^J Jt"f Oil 3293 r/t 7 <JlC to l oS oo nJ/ L .031 (l- jor -- a/ft- . / t "7'' / 3 - A - Z, b ;, (1 rV ? - ct-2-o-u (j+ei : -! > f; `4. 0 <J TO-___ . 5*0 JJC_____ ?, C." K )if. V V A ) lc "7 - 1 3 4 s 7'- L ` s ' L /t /<.. JO <- v-""^ -- -rT /C : 40 1 * ! -*f. p^ / COMM EASTS J?OC A-t Gu/ 7} S A-^o/r ey S&A- SA-'VG-e'b <**> f/c 3 6,/<P1s Orr*** A A/e S x /^erwi A/ / / f C4iJ 4ot^, /, /i Q l/% f) / v J1 <m A ] rgs ._. j_ O ^ * > ^d^>re F.yuic* /** s*~y?/c i3ow 1 1 1 ft < \N \r\ K V _ 5 'V ^ V\ r t\ ^ 1X a t l/i A V rrt- - , Z **' ^i V ot Va J o V t a* k' \' 1 ( -v o ( u \ "(1 \ o >0 X \ '-M Vi Vi r N 0 r 9* - e)I IS oCl 'VoS * : V >s, ^* ! V Au, S. $ a* ^ 57s?* *0, ^ c^ I * * *<& Vc \ \ \ \ \ \ u <V-1/v4 ^'1 'X \- \ Uj \ \ \ b v. \ \ \ \ V \ \ \ 'X Cv 1" * > 5 %A & $A O o \* o \ V*i 9 Vm <b La <a) \ Ci h a U) Uj 0 o *o Vn * 00 Cj a 5s c \u \j c. \ C, \ 3. s. * n O U\ V\ b F^ h ?f p -J rX V* K . & -O . ?\ V\ SN >0 f\ % f. S V r ?T P5U ns Os. <5- i? * C> X> o V \ nj tD n "1----- nfrtf*>*. * t o> ^ - $ I *-> i is J sX* X-.^ {X u * > fiv. XX -o -T X>c. * A <* X r V i c, ft } A 0 i , *x> U^ vvc 00 000 EU17 .... L *y > o > l G-t-ASS Bo m B A-VB M/ScElL&JVOt/S t v r m M O vhd X am P ie s . --I . ; r p ^ &lr &LA5S 8oaa8 AW MtSctLL+Ayoi/s t JRMAfiOim> -f AMPISS . * acATfCA/ Aa/0 Pscp'tPrUtl OATS r/Afi? V'CM EPC 4^3 4si ?-n-*3 t~- u . zo .53 L.9 Roc.I<E 7 o5o AJ<C 17-5 pC'C la l >h) c' im' <T 130 /S7 N- L- "f 1 0 i y :> 'ftT //.' i- - s 3 Z> PCtt l_ ,\J 4 t-' / .s~fi ?. S' .7 i/,. c ToP________________________________ 3-/$ Ofto* V/ ^ *z (- 4 S3 87m -- . 8J /.y p<9 c /c L/a) <-* 4/ T-Io-l <-.. 0 Soo y.* A3 4*/ Ro^ke T T"9 <r% p,7~i~~ -- o5<>*> . *>/ /D.C VS~oo /0/L N,'C L. /3t'-<: //?L rmm n-p ft t- /ft A ,fcnr' 4~ 3 $ 7 in ft-r/ 4v 3-* -?-?/ ?-v 7 2/ 3-K {/c r- N`t 177 ytJ.. 02 Oo AftL 0 30o 03 Q& 0^ Oo </? WL OSJo Nr<- ? 7 ~l"Za*JL_ T$o(t ZaAaP P7L 3-o 3.1 11 1 % ' PACr C OtfMeMTS 7N7 .9 '--- U --- COoD oo u>> Sy & Iti Q T r zlG ------------------------ i Sp^7/ GLa$ fio/ni? t v / ii- 3c- ^ b ,( r~'" 4//P^ Sv/'l A>Air t s 7db/Vs cm oV + *iiru. t d o n w h s iw afcb ghfog ssvy-3 __________4 r f . 4 V _JZxX f \ o> ?i h v Bc rX1 A 0\ A 'n O J -X X\ X lv s -\\ NV lsJ\ {K A % v. \ > J 1 IA Tl A X \ X v\ X \ fx ro 0 c s X 0 r 3 \ r^ VA >A-s o < X >nrlh*i, J & \\ \ X\ ' J % V\ U J O.1O X X \s X i X. X%$ & XXx i *\ Ui > CLW^> D xowi 0 X \j 4, ?y X pU5j X x X j '\ < u, \ X X 4 :x $> ! 1 Xi ii vNO> A \ \s \ WNN> " > e? -oc'tv. $ o<x o o O I- \ && X \ X\ X V\ \ % ^ n r 4 </ *v X KX r^ A . \_ & K > V x X XN S ^'*V X VX, X r \X N W f* u "N ^3 ^1 A 5\ s< (a x iS\ i\ X? X? G\ x ' N $* N * Ul n \0 5X V 4 (* x. -ioi vvc ooc 008 L 20 3Wd ;, . 1 1 ! 1! i .. i1 1 : i-----------------------------------------------------------------i c t <l) o o o uu - fU i J i- , SJ/r3ynrf<?^ r 4y(.. . e . "7 7 ~jrr; ` U' Q<3*cS ny* c? toi i:-h r*n X*3 V --' - M Xy -2130 JJjf / o& ~^b^Q 8l-i^ r^TTrn '3 * jv -- S.S52 Lt'f fTr^cr'gj? 'o>rv/7 )/ o P(T' S b~Z\ Li-j? ^0/7^7 ->i 7^ y* "77^ <r;r //'/ ~ 0/--A rwfm ~ &'Z <S/' fj>^n Jr-fr Y~tzrr t r> qq\?0 ---X -7-C . S <L_S f* t-J- ' i iti-y 'f-'.-M n? '/ ~w 0/1 -7Zk?J OO -Jy C? l \> 0y v ' i ") ''e) OP-?--? sr -T^ 0 U' , */ ^ 7 . T^ f jf y-/v'(/ / T . . -St? ..* ^ , / ~^T ( l /' * 1' / i ,: .. V C /. v. , - w* ` v o 'OZ i.W s-; ii -- -<^Z i:c< rs/ (t'i2-L od 3 yr? a Jtty/J. 3J.V0 ---r:7-JJ WT^Tf 1 f!' ^ c c * -" - ./ y^r' 7' > -01- f-J ^r/ -/0 2 ftp/jj{ti^rza aftv /vouv?q7 :v. rs7dH\fs Mownsisw 4frV gftog ssvy-3 fc* o 01 7^ i rr 1 'J[ i , K V R_ fx & o n J*v N S V i c r,, ? <5 t^\ >s N rs, r n * 'h &* r r\j r* r s >\ Sk \ -V ^0 > 0 1 1 :> \J $ $ c "S -J KM <oX 'V "3 0 rj> \!3 -}4r^ <c~ tfl ? v> < oJ VM 'i r V kO i <v XX] n k -- r* 5 TVv 'N. O }> r- !v\ 4 N \ w <> Ul % n 0 X i *) 'i u> vvc G<3000 812 ? * l/C.M. CO C_ ! 7.3.5- ('t..?^j) ?7kzA.$&y ZJL 0, (. . ?v) ^.04 %*~f : 7t. a 1 /-?. ?/ 4! A/7 0'?*) c^JLj H 5~ C02) /2> 70 AUJ&, l. (& 1,0.1 C-5-a0 ^Crttjuut'y ^ 7 1.9 3 /7.C.3 CudJ>y e. rC ) /7.^2- 7fuJC-t /f. 7 C ^<v> //. 3-i io C ,//J> ^**du~*j c. // C .37^ /<> .13' A/. /<K C-dO /-? Co ^ nP.sr? G*. /f (&c/ A<5W J 3". A*" C.3i) /?- ?5~ /Zfd'erb'Zj /6 (.*) /S.l 3" o'qo,;* j a. n (.37) /3. 97 *S/*9?o??ey? j A. t* (*0 Vft-7 3/f e/fHsrf C./J it .Ho */ Cl5) IZ.iV C.i?) tO.HI *2 i ^ C/feess * Foxt ii, /?, 1.1? 00 / e w? > CwJ /o,i>s 25- i.n C ,i.Yj J8CJA; e. TAftfifif// uafifty * f'jZ*----- f W& 3-C-* 3 3 J-J--P-3 n i* 3* t/-P3> ?/S 0LX~t-/3i-JP /=AA/R 3-Y-P3 dUJ aJig F-jr-23 3 -3-F-3 3-3>~-F3 3 S~'?3 J-C-P3 3-C.-P3 J-C.-P3 J-L-P3 3~>r$} C <J/a. i. . s/^ &8.Z: 4 PxZ. T~ Y*S~3 ^<e> 7 ^co 7 7 10 v,- t r'-c&z-^ S-&Z.J C-3& 3 3-<'f5 l ? r> #V0 - 3 - C, 'P3 3-C ~r_3 3-fc^ 3 3 < 'P 3 3-S--P3. 00 jn ^M3 ? 4 ?* ?t sytO vvc OOOOO0123 -/r)pLoy BS V 4-3 2 V H3L, 13 3 <*UO' 3^ (, 4377 t/ V?3 '(p(.'0lO 1/ 3?-J7-3633 L/ H39- OS '/970 17 HS9-J7- 7o3<? 1/ S/9-78 -4.??? i/ <939-L% ~79Z V 43-C>2 - 74fO V 43 (, o> *???:>" L/ q*9-S4-q/C,f V 4rf 'J3 - 4*3? \/ 439-2/ - 3*93 \J 433' da.- 44/4, v v*?- 5-y^ 7//2 v 430,' ?0 -93.39 V 4$i~ 3t/'7*ZL 1/ 439-/s "929/ y 1/ 43?'7Z' \f </ss--^'9S^ \S 432 'O 2'770/ H-VDi Sof) J ftonn/J /)etscj , Tv-. S^q^t -Thilh': M. 4?voX,'f~rv\ f 4e-+\ r^-j B-e*tOl/ J / Sy-t'^ **1 3cc//*v- f ^.c*c. Burn e. 7T Cto-rro// C/e.s/*^ CAT-j Afr*/c. ty/t**4/K CRAPBui- USA- AyMA> C_Ro<-0 ; f S7~EpH--Aj Cfcowe- ^ &C/lS>irJ XT'. PaBRoeL. jl~oy H-. (y-vtdr^ , donn/e. A3 //oo^er ^ x 7" jAcATScW; G/rfl^ /er&.r<L ^Q-Tl/ve-fi-, STue- 3t/c-e kfi-u/son ^ -///>- JiiC/Ctr/jr MfrfJClHsrZi bA-A/A/y P&aJ /yifrflTiti ? Loof% /MuMiHCr , ?A?iLLiaio ?(&{(&*., SoAA/&nr l/joaj 4n4c4 *A-KU /l &/-n/AJ Or, bW/i3 r 0' Tbyi i9f/A/r7Tr i/}-rotL , mutKey vvc 000008124 I < <o o ooo o CD h: UN1 ANAL-REPORT turnaround KAY 82 Interoffice Communication to J. A. DeBernardi From j. VJ. Ware Date September 15, 1982 subject 1982 Turnaround Critique (conoco) Q/-J- Sumnary The 1982 turnaround was completed on-schedule, under budget and with the best safety record ever for a VCM Plant turnaround. The turnaround was budgeted for 23 days, stream-to-stream, and a total cost of $1,Q85.2M. The turnaround was actually completed in 26 calendar days following a cost-saving three day suspension of turnaround activities during the Memorial Day holiday weekend. Turnaround cost accounting indicates a total actual cost of $963.OM (to be confirmed by receipt of actual invoices at a later date). This represents a favorable cost variance of $122.2M. Three injuries requiring first aid treatment were reported during the 1982 turnaround. The best previous record was associated with the 1980 turnaround which recorded four first aid injuries and one medical treatment case. The improved overall performance achieved by the Plant during this turnaround must be considered to be a significant accomplishment, especially in light of the Plant Modernization Project workload. General elements which were factors in making the 1982 turnaround a success are as follows: 1) Favorable weather conditions during the turnaround period. 2) Relatively complete, experienced plant staff. 3) Close coordination of the work effort in daily meetings. 4) Decreased Plant Modernization activities. 5) Institution of an improved cost control program. 6) Availability of more qualified casual craftsman. Attached you will find a more detailed analysis of the various aspects of the turnaround with plans for further improvement where appropriate. J. W. Ware Plant Superintendent br cc: RB-MLA-JRH-JHB-SRA-PLF vvc 000008126 Safety and Security The 1982 turnaround was completed with three injuries requiring first aid treatment being reported. This statistic represents the best turnaround safety performance in the Plant's history. In addition fewer potentially hazardous "near miss" incidents were reported. All injuries recorded during the turnaround involved casual personnel. The fact that the number of injuries was substantially less than previous turn arounds is attributed to increased direct supervision and employment of a casual work force which, for a variety of reasons, was more committed to established plant work practices. Contractor safety performance improved considerably as compared to the 1981 turnaround. Factors contributing to this improvement include: 1) Fewer contract personnel in the plant. 2) Increased communication of plant safety requirements to contract personnel prior to the turnaround. 3) Depressed economic conditions in the Lake Charles area which permitted the use of more experienced contract personnel. Plant security and employee/contractor control was adequate. Separate gates were designated for employees and contract personnel. Employees and plant contract personnel were provided identification badges and Plant Modernization contract personnel were required to wear specially designed identification tags along with their union identification buttons in full view for plant entry. This made possible improved gate control and coordination of personnel once they were in the plant. May 1, 1982, marked the expiration of contracts between various craft unions and the Association of General Contractors in Lake Charles. Crafts with contracts which expired on May 1 included the carpenters, iron workers, cement finishers, brick layers, teamsters, operating engineers, pipefitters and boilermakers. The VCM Plant experienced no problems as a result of the expiration of these contracts. Planning and Scheduling The work planning effort for the turnaround was begun in early March, approx imately two months prior to the start of the turnaround. The planning effort was directed toward identification of plant maintenance and Modernization Project work items and then organization of these work items into a schedule. This effort is well standardized for plant maintenance items and is based primarily upon past experience. A special effort was made during the 1982 turnaround to apply a risk/benefit analysis to standard work items. Selected items were then eliminated in support .of the cost control program. This effort yielded true cost savings during the turnaround. An Operations Shift Supervisor was assigned to work with Maintenance Department, Modernization Project and CED Planning personnel to update/improve 00008127 vvc o upon the computerized work schedule developed prior to'the 1981 turnaround. The Shift Supervisor was occupied full time with this assignment for approx imately three weeks. This Operations manpower commitment is critical to the success of the planning effort and the three week period was adequate. A similar commitment by Maintenance Department personnel was not possible while pre-planning the 1982 turnaround due to an understaffed condition. This deficiency manifested itself during the turnaround in deviations from the established work schedule and the resulting conflicts for available work space and manpower. An increased interaction between Maintenance and Moderni zation personnel is needed prior to the next turnaround. Due to the extent of the Modernization Project work and the projected duration of the 1983 turnaround, planning and scheduling work has already begun for this next turnaround. Mechanical In general the mechanical work went well. Unanticipated major work items which had an effect upon efficiency and scheduling included repairs to R-201A cracking furnace walls, replacement of five trays in the HC1 column, C-202, and replacement of two tantalum sleeves in the spare primary oxychlorination separator, $-309 (which was installed during the turnaround). A significant amount of extra time and money were spent cleaning the EDC Vaporizer (H-201A & B) bundles. This is believed to be due to the fact that these bundles were not cleaned when the furnaces were decoked during the previous run. As a result of this experience, the plant will return to the practice of cleaning the vaporizer bundles during routine decokings. Catalyst removal and charging of the oxychlorination reactors continues to be a manpower intensive task. Several contractors were approached prior to the 1982 turnaround in an attempt to identify any new technology in this area which might be practical and economical for the VCM reactors. One such contractor was allowed in the plant during the T/A to test newly developed equipment. The equipment appeared to be workable. Costs for catalyst removal and charging were carefully tracked during the 1982 turnaround and will be compared with a quote from Reactor Services, Inc., in a potential move to save costs and eliminate the hiring of some 55-60 casual employees during the 1983 turnaround. Halliburton Services were used as the chemical cleaning contractor during the 1982 turnaround. Halliburton personnel were found to be more reliable, competent and safety conscious than personnel associated with cleaning contractors used in the past. For the first time in the history of the VCM Plant no weld repairs were required in the direct chlorinator, R-101. In addition minimal repairs were required in S-206, T-1G1 and T-102. Operations Plant shutdown and start-up procedures are well established from many years of use. Minor modifications are implemented from turnaround to turnaround to accomodate revised mechanical work plans and improve efficiency. The VVC 000008128 shutdown and start-up activities proceeded well during'the 1982 turnaround. The following comments represent areas to be considered for the 1983 turnaround. 1) The use of breathing air for blinding operations will require additional emphasis prior to the next turnaround to ensure a greater commitment to this need by both Operations and Maintenance personnel. 2) The heavy ends column and light ends column were shutdown on Friday of the shutdown weekend. This is earlier than on past turnarounds, had no adverse effects and represented a considerable cost savings. 3) Samples were not taken during the EDC purge nor during equipment preparation for entry until, by past experience, it was reasonable to expect acceptable results. This saved lab time, limited the purging of lab equipment and resulted in more accurate sampling and analysis. 4) Incinerator operator double coverage was stopped on Saturday evening shift and the standby incinerator was shut down on Sunday morning. This was effective in reducing shutdown costs. 5) The HC1 storage tank, T-204, is routinely vented to control the pressure during the turnaround. Previous to the 1982 turnaround the HC1 was vented to T-500 which then required caustic addition to the plant effluent for neutralization. During the 1982 turnaround T-204 was vented to the acid concentration unit and used in muriatic acid production as a cost saving measure. 6) Reduced heat load on the cooling tower allowed reduction of treatment chemical injection to near zero. This was accomplished during the 1982 turnaround without adverse effects. 7) A delay was encountered during start-up due to a malfunction of the laboratory water analyzer; this occurring during azeo drying of the unit with EDC. A minimum of two workable water analyzers should be available prior to the turnaround.8 8) Prior to and during start-up operations all vinyl check tanks should be vented to the incinerator on a pre-established frequency. This is needed to avoid the development of high pressures which could lead to operational problems in the caustic decanter, S-206. Personnel Programs have been established at the VCM Plant related to hiring, control and termination of casual employees with the following objectives: 1) Employing capable, qualified personnel. 2) Identifying good/poor performers to ensure continued improvement of overall casual workforce. VVC 000008129 The established program used for many years is felt to be adequate. Several modifications/additions to this program were implemented with favorable results during the 1982 turnaround: 1) All potential casual employees were required to come to the plant prior to their employment to complete the "health11 and "work restriction" forms. This allowed for improved crew strength by bringing to the attention of appropriate plant personnel potential casual employees with significant health or work restrictions. 2) A deadline was established three weeks prior to the turnaround after which the plant could not offer permanent employee references con sideration. This again facilitated pre-planning for increased crew strength. This deadline will be moved to four weeks prior to the start of the 1983 turnaround. Cost Control During the recent May turnaround, a daily accounting procedure was implemented for the first time to aid in cost control and generate additional information on T/A expenditures. As a result of knowing these daily expenditures, measures could be taken to control T/A costs; and to correct any mischarged expenditures. In addition, this documentation will be useful in future T/A budgeting. Turnaround expenditures were classified under five categories: contractor work orders-rentals, contractor work orders-other, warehouse issues, direct purchase orders, and plant labor. Within each category, the expenditures were charged to 31 specified maintenance management system (MMS) equipment codes (see Table I). These areas were specified because they represent the major sources of T/A costs. Daily expenditures for each equipment code were recorded along with a cumulative total for the T/A. Also, daily grand total T/A expenditures, and a cumulative grand total were recorded. Expenditure information was received daily from warehouse and maintenance personnel, and in some cases, directly from contractors (i.e., insulators and chemical cleaners/hydroblasters). This information was filed in an "in" box, by equipment code, before being logged; and after logged, filed in an "out" box in the same manner and stored for future reference. The plant labor ex penditures were determined by equipment codes from a daily MMS computer printout supplied by the VCM Plant accounting dept. Turnaround accountants during the May 1982 T/A were S. Reynolds from the VCM Plant Process Engineering Dept, and Felix Braggs from Chemicals Accounting in Ponca City. Braggs worked full time for 18 days of the T/A, and Reynolds averaged 75% of each day during the T/A (20 days), 2 days full time prior to T/A, and 10 days full time post T/A, for a combined total of 45 man-days. This personnel arrangement is most ideal because an accountant must devote full time to the books and accounting procedures, while a plant employee assists in the accounting procedures and handles plant-oriented accounting problems, while still performing normal plant T/A functions. Also, the plant employee is able to manage the full accounting procedure during off-peak times (i.e., pre and post T/A). The overall accounting procedure was organized very well, and only minor changes were necessary: - VVC 000008130 1) The bookkeeping method was excellent, with expenditures broken down logically, and daily and cumulative information at hand quickly. (These books can be obtained through the plant superintendent, and are easily understood). Two changes to the original bookkeeping method were made: (a) a subtotal page was added to the general equipment categories (i.e., reactors, compressors, drums, exchangers, and columns) to allow a daily and cumulative total of these five equipment categories, and (b) a row must be designated in the books as pre T/A expenditures. These were kept at the top of each page during the May '82 T/A. Pre T/A expenditures should be accounted for in greater detail prior to future T/A's. 2) The flow of expenditure information was generally good. Warehouse issues and purchase orders were transferred consistently every day. Whereas, . contractor work orders (rentals and others) were, at times, inconsistent and difficult to track down. A definite line of transfer must be established from all sources of contractor work. A useful line that was implemented during the May '82 T/A was: all contract expenditures were transferred to the maintenance supervisor(s) by the contractors, who in turn transferred them to the plant superintendent, who in turn transferred them to the T/A accountants. 3) The filing system proved adequate with no changes required. 4) Finally, determining the plant labor expenditures from the MMS computer printout was tedious and time consuming. This task usually took approximately two hours each day. A new program was written by H. E. Bible, of computer ORD in Ponca City, at the end of the May '82 T/A to condense most of the manual work. The program totals all plant labor costs per equipment code per day. This program was developed per the T/A accountants' suggestions and will be very useful during future turnarounds. Specific cost control measures instituted during the turnaround which actually reduced costs included the following: 1) Only a few trays in selected, readily accessible sections of the light ends column, C-102, were manually cleaned. This is the first time in the history of the VCM plant that this risk was taken. To date, this has not presented any operating problems. 2) Some heat exchanger surfaces which were routinely cleaned during past turnarounds were removed from the cleaning work list following a visual inspection. Such exchanger surfaces included the tube side of the ethylene preheater, H-308; the tube side of the quench column condensers, H-202A & B; the shell side of the light ends condenser, H-106; the shell and tube side of the quench column interchanger, H-213; and the shell and tube side of the quench column reflux cooler, H-203. 3) Turnaround activities were suspended for the Memorial Day holiday weekend. This reduced total labor charges for the turnaround. 4) The top section of the vinyl column was not cleaned. Both the section above and the section below the feed tray are normally manually cleaned each turnaround. As with the light ends column, this has not presented any operating problems to date*- VVC 000008131 As the effect of eliminating the above work items which are normally standard for every plant turnaround is witnessed during the present run, the risk/benefit analysis will be extended to other "standard" turnaround work items, such as, BL-501 propylene compressor turbine overhaul and BL-301 air compressor overhaul. Some other valuable lessons were learned from the institution of the abovedescribed cost control program which warrant follow-up for future turnarounds: 1) It was found that pre-fabrication labor normally incurred in the three to four weeks prior to the turnaround were not previously budgeted in turnaround costs. 2) A significant amount of costs have been charged to previous turn arounds which should have been charged to such areas as extraordinary maintenance, capital expenditure projects or routine maintenance. Significantly improved control of charges was exercised during the 1982 turnaround. This, however, does not diminish the effect of the cost control program since these other areas where costs were charged were also controlled within budget. VVC 000008132 TABLE I MMS EQUIPMENT CODES CATEGORY 05 Truck Driver 18 Warehouseman 27 Toolroom Mechanic 30 Rigging 31 Safety & Health 32 Hoses & Fittings 33 Reactors 34 Compressors 35 Turbines (BL-501) 36 Shop Tools, Portable 37 Painting 42 Insulation 45 Drums 49 Fans & Blowers 55 Exchangers 57 Control & Metering 58 Process Analyzers 62 Electrical & Telephones 64 Filters & Presses 69 Miscellaneous Structures 74 Rupture Discs 75 Wastewater Treatment Facilities 77 Piping & Valving 78 Relief Valves 79 Yards, Paving, Roads 84 Shop Equipment, Stationary 88 Towers 89, Tanks 59 Miscellaneous Equipment 92 Yard Machinery Ot; All others VVC 000008133