Gulf Coast Waste Disposal Authority 910 Bay Are<? Boulevard Houston Te*ds 77058 713/488-4115 February 2, 1987 Hr. Joe Ledvina Vista Chemical Company P.0. Box 19029 Houston, Texas 77224 Dear Mr. Ledvina: The incinerator project proceeds about as the earlier schedules indicated. The Keystone Local Review Committee completed their report and that report was mailed to you. If you want more copies of the report, which is a part of the application, we have an ample supply. Local units of government have adopted resolutions in opposition to the project and the RASH group remains active in their opposition. Although disappointing, their efforts track fairly closely activities at other proposed facilities and should be expected from concerned citizens'. . A certain amount of misinformation has been noticed, such as "the world's largest incinerator," "undocumented data," comparison to the El Dorado, Arkansas unit, "burning of unknown types of wastes," etc. The Texas Water Commission's review of the permit will thoroughly evaluate air emission data, operating procedures, safeguards, controls, etc., and we have no exposure in any technical area since the processes and equipment exceed normal requirements. We will continue to work with the agencies to provide any additional information they require. The permit application was delivered to TWC on November 25, 1986. We received their first letter relative to administrative completeness on January 16, 1987, and our complete response is due in their office no later than February 15, 1967. That response will be completed within the 30 day time period. When TWC determines the application to be administratively complete, we will make copies available for public review. The following updated schedule is based on the most recent information to TWC and our best evaluation of those "loose" areas. Receipt of TWC Administrative Completeness letter GCA response complete TWC/TACB initiate review TWC/TACB complete review - submit notice of required changes to GCA GCA response complete TWC Initial Draft Permit TWC Final Draft permit Earliest date for Public Hearing January 16, 1987 February 15, 1987 February 26, 1987 April 2, 1987 May 2, 1987 June 2, 1987 July 16, 1987 September 10, 1987 CWH 000000634 Page 2 February 2, 1987 Projected date - Examiner's Recommendation Projected date of TWC action December 1987 February 1987 o Design period - 4 months o Construction period - 15 months o Trial burn period - 6 weeks o Anticipate trial burns November/December 1989 o Anticipate initial operations January 1990 We feel that the issue of bringing in wastes from outside the area is the most significant area of public concern. We are containing our efforts to secure more local industry commitments and will hold that reserve we had previously committed for later Texas City industries. If we can secure additional users from the local area, their usage would come out of the present 18 percent "open" category - not the 15 percent Texas City industry reserve. This is consistent with our commitments to the local concerns. Please contact me if you have any questions. Very truly yours. -JPT/tg Joe P. Teller Manager, Special Projects CUH 000000635