Document QJ8761EqBr63LQNrR0k4QmDOv
ESCAMBIA CHEMICAL CORPORATION INTEROFFICE MEMORANDUM
Tot Mr. T. L. Carey
Delet
From* Ret
J. J. Dorsey, Jr.
Copies*
Summary of Technical Department Monthly Reports February 1966
March 7, 1966
NEW PRODUCTS
DNT
During this month an extensive review of operations and design details was carried out with Chemico during the week of February 14. These dis cussions were very fruitful and will lead to a better plant design.
We still have several contract questions with Chemico which have not been resolved. Some of the areas were referred to Biazzi for comment and hopefully can be resolved during March.
A meeting was held with Wyandotte Chemicals on February 9, 1966 at which time agreement was reached on how to define specifications and methods o analyses. At the same meeting, Wyandotte indicated they will require material in July or August 1966. Later in the month they affirmed they would like to order in August to have material for their plant start during September. It is still planned to air ship the DNT plant equipment to Pensacola unless some thing develops which will allow further delays in completing the plant.
During this month plans were made for the new operating personnel for the plant. These people will be required approximately six weeks before the plant start.
In anticipation that Wyandotte may not take the full plant capacity in the fall of 1966 and 1967, it is planned to consider the preparation of other aromatic nitro compounds.
ADE
The pilot plant program at Pensacola continued this month with a further definition of the plant design and operating conditions. The work, which is summarized in Mr. Forester's report, indicates a satisfactory yield and
AP00045509
Mr. T. L, Carey
-2- March 7, 1966
reproducibility based on chromatic analyses of the reactor material. The plant laboratory work has successfully developed a chromatographic technique which gives excellent checks on knowns and plant samples.
The use of 316 stainless steel seems acceptable for the reactor material. A reactor life in excess of six months can be designed, based on present know ledge, which with two reactors in parallel will allow continuous operation with no problem. It was not possible to keep the 1/4" titanium coil from plugging with polymer.
At the moment effort in the plant laboratory and pilot plant Is being directed towards separating on as quantitative a basis as possible "in hand" crude amines. This will confirm the yield and product distributions obtained by chromatograph. Once this is verified, it should be possible to continue the planned program. During March, as soon as this verification of yield is obtained, the material for a projected salt separation study at Struthers 'Wells will be made. During the balance of March and April the separation of the crude amines into products for customer evaluation will be done.
Of the $30,000 appropriated for operation of the plant, approximately $15, 000 is left for March and April. As is true in most pilot plant operations, it is not possible at this time to determine for sure if this will be sufficient. However, it should be sufficient to assure us that we definitely have a process.
PROCESS IMPROVEMENT
As was discussed last month, very Little process improvement work in Process Development is proceeding. Mr, Scattoloni has been assigned to the NP group to work closely with Mr. Barfield on all problems in this area. Process Improvement in amines is handled by Messrs. Jones and Kersh,
LABORATORIES
The volume of laboratory work in February continued unchanged. However, in spite of the additional work, the anticipated variance is probably less than $1,000 for the month.
While the details of the laboratory work are covered in Mr. Fowlkes' report, of particular significance is the work done on the ADE pilot plant by Mr. Tolar in the development of an analytical method for the amine components and its use to define yield. This is covered in detail in his report.
A new Durabead catalyst for methylamines has given excellent per formance in the small test reactor. A charge for the plant reactor has been ordered and'will be tried some time later in the year. This catalyst has greater strength characteristics, equivalent or better activity, and costs approximately 80% lass than the previous catalyst.
AP00045510
Mr. T. L* Carey
3- March 7, 196b
ENGINEERING
A more detailed review of the major projects and many of the minor projects is presented in the Engineering monthly report developed by Messrs. Hill> Kippels, and Metcalf. This month the study includes more of the smaller projects which have been approved.
Attached to this section is a summary of the work Btatus of these projects. It is apparent that many of the projects estimated in the last quarter of 1965 and being completed now are exceeding the original estimates for many reasons. In some instances, the estimates did not take into account the tremen dous amount of construction which is proceeding In the Pensacola-Mobile area, thus making available less high quality craftsmen than have been available in times past. Further, we have experienced the need to install equipment in operating units in operation, and under inclement weather conditions. These have contributed to the cost. As we recognize this situation, in future estimates we will attempt to allow for this by adjusting our labor factors for the lower output as well as the fact that some overtime is essential to hire craftsmen. Presently at times we must almost guarantee 10 hours/day work to obtain welders and pipefitters.
We are currently completing and working on many major projects, such as methyl methacrylates, NP storage and loading, amines storage, IBN and DNT. While our design drafting group is working 50-55 hours/week per man, this has been necessary to keep up with the various projects.
MAIN TE NANCE
Considerable effort has been exercised during February in all of the Maintenance areas to analyze costs and provide information to the various process superintendents. This additional paper work will hopefully be of benefit in helping to control Maintenance costs from a Process viewpoint.
Maintenance costs during the current month have been about $158, 000 as compared to the budget of $172, 000. The actual cumulative Maintenance costs for the year are $306, 000 as compared to a budget of $345,000.
Areas appreciably over the budget for the year are shown in the table below:
Area
Solutions Shipping AN Prills Shipping
Actual
2,798 4, 342 11,842
Budget
1, 248 3, 166
8,000
AF00045511
Mr. T. L. Carey
-4- March 7, 1966
Area
Actual
Budget
NP NP Shipping PVC Amines
40,198 7,052
32,933 27, 843
20,000
3, 334 25, 998 22,166
In many cases improvements have been made in the above areas which could have been prorated over several months, or the total year. However, the total costs were taken this month and will hopefully reflect in reduced Maintenance costs in the same areas later on.
REVISED FIVE-YEAR EXPANSION PROGRAM
Considerable effort, in cooperation with Accounting, was spent on revising the five-year expansion program. While at month's end the program was not complete, it indicates that the problem areas are what to do in the Nitrogen Division and in methacrylates.
The production of methanol in a new 800 ton/day plant appears very profit able even when charging methanol $700, 000 for CC>2 purchased from the ammonia operations. This credit to the Nitrogen Division, plus revised economics for producing and metketing NP, indicates a greater profitability in the Nitrogen Division than had earlier been expected.
The plan for presenting the five-year expansion program is to refer to the previous program as far as marketing projections are concerned and to revise
the economics based on new conditions either in the sales or production area.
MISCELLANEOUS
During March three technical representatives of British Hydrocarbon Chemicals from Grangemouth, Scotland visited the plant to discuss problems with methanol production. British Hydrocarbon has a plant virtually identical to Escambia's plant. Their plant was designed by Chemical Construction and has operated approximately four years less than Escambia's. The free exchange of technical information was very helpful. While British Hydrocarbon could profit greatly from mechanical information which Escambia could supply based on its operating experience, Escambia could profit from several excellent studies made by British Hydrocarbon, particularly computer studies over the reform area and synthesis area. In general, we have established an area of mutual exchange of technical information which should be of benefit to both groups.
mdc Enel.
AP00045512
SUMMARY OF PROJECT WORK STATUS
oiect No.
Till*
6499
MMA Expansion
Appropriation Commlttsd Revised Completion MS MS MS Date
173 237 233 4-1-66
Remarks
Coats continue to rieo above estimate primarily because of unexpected problems, shortage of construction -- personnel, and volume of Important work in progress.
6924
Reactor Drop Valves
12
10
24
5-1-66
Awaiting valve*.
PVC
6532 6969
Now Railroad Track DNT Plant
26.5 1,,070
22.3 520
23 1, 070
3-11-66 -1-66
Virtually complata.
Work In progress, completion date pushed back to 5-1-66.
6572
Duat Collector for N-P
56
34
37
4-1-66
No change, awaiting Dustex
hoppers.
69 T3
Additional N-P Storage
223
243
260
4-1-66
Higher costs result from
labor shortage and push to
complete for fertiliser
season.
6577 6376 6565
Improvements and Modifications to N-P Plant
Proeaora to Storo IPP Catalyst PVC
Production of IBN - Amlnoa
34.5 9
224
44, a 9. 6
54
43
2-1-66
Work complete.
9.7
Complete Complete,
224
5-1-66
Project appears to be on schedule and budget.
6604 6605 6617 6616 6620 6621 6622
New 600# Boilor
320
Water Treating Modifications - Bailer
Additional Bulk Car Loading Pacilitiee - PVC
Alpine Mill Holding Bin PVC Plant
Spare Reactor Agitator Motor PVC Plant
20-Ton Refrigeration Unit PVC Plant
Spare Gae End on Monomer Recovery Compressor (PVC)
105 10.4 9.6 4. 1 12 14. 3
132 nont none
2. 6 3, nonm 13.0
320 105
10.4 3. 6
U-l-66 11-1-66 7-1-66
Project appear* to be on schedule and budget.
Project appears to be on schedule and budget.
Planning.
4-1-60
Nearly complete.
4.1 7-1-66 Spare - awaiting delivery.
12 Indefinite Planning,
14. 1
6-1-66
Awaiting delivery.
6626
6679 6631 6636 6632
6633
6634
6676
New Bag Packaging Equip ment - PVC Plant
IS
Cerftrel Itoom Chromatographs Additional Electrical Heat 1.
9.6
a
New Converter for #1 Plant
15
Well Water to HP Scrubber No. 1 Amine* Plant
4
Install 2 DMA Check Tanks No. 1 Aminas Plant
12.4
Aqua Mix Tank - No. 1 Amines Plant
3.6
Nitrogen Sales Bagging Facilities
47.2
10 7.3 3 1.4 3 i.e
22
18
6-1-66
Awaiting delivery.
9.4
5-1-66
AuvaMng delivery.
35
5-10-66
Awaiting approval on
location for heater,
4
4-1-66
In progress.
12.4
4-1-66
In progress,
5. 6
4-1-66
In progress.
47.2
4-1-66
Work in progress, early April completion.
AP00045513
Summarr of Project Work Status
Paf 2
Preltct No.
Titla
Appropriation Committed Reviaed Completion MS MS MS Data
6675
Nitrogen Salas Warehouses Appropriation for 12 Appropriation for 4
33.3 11.1
10.8
16.8
3-15-66
W-5066
Additional Amino* storage
250
239 277 4-1-66
Remark*
Four of Engineering responsibility will over run beeauee of uit of iel.ee coet estimate.
In progree* - 13 tank* in service. 4 on ett*.
W-5082
ADS Pilot Plant
50
54
56
4-1-66
Completed. Overrun caused
by weather and overtime.
1580-18829 Independent Raw Water Supply FVG
1580-18841 New Condenser Column T-68102 - Amine*
1580-18842 New Condenser Column T-68103 - Amine*
1580-80001 Temporary Centrifuge for MMA
9.7 8.5 9.9 9.3
1.8
9. 7
9-1-66
Only overhead epent.
7. 6 8.3 C ornplete
7.9 9.9 Complete
1.2 9.3 4-1-66
AP00045514
ESCAMBIA CHEMICAL CORPORATION INTEROFFICE MEMORANDUM
Toi
Fiomi Ret
Mr. T* L* Carey
March 1, 1966
s. M. Spurlock
Capita*
Monthly Report - Personnel Department - February, 1966
PERSONNEL
Activity for the Month
Division
No* of
No* of
Employees February February Employees 1966
1/31/66 Additions Separations 2/28/66 Budget
Executive
56 2 1
Research
53 . 1
0
Agricultural Chemicals 156
13
5
Industrial Chemicals Production
15 386
0 _2
0
_2
57 64 94 59 164 160
M15 18
393
Totals
666 29 8 683 699
There were l6l walk-in applicants, 114 applications Issued end 6 received hy nail. Thirty-seven applicants were interviewed and 97 were tested
TRAINING
Schools were held for the operation of trackmobiles and forklifts. There were 8 trackmoblle operators licensed and 11 forklift operators
licensed.
SAFETY
The Corporation has worked 93 days or approximately 224,000 man-hours without a disabling injury. The various division records are as follows:
Division
Man-hours
Days
New York Office
Research Division Atlanta Division Pensacola Plant Corporation
331,000 786,500
56,500 1,779,000
224,000
1,669 3,149
53 770
53
AP00045515
Monthly Report
-2-
March 1, 1966
SAFETY (Cont'd,)
Medical Section
The Medical Section treated 12 injuries for Escambia and 20 for Carroll, performed 14 pre-employment and l6 annual physicals and gave a total of 0 immunization injections*
EMPLOYEE RELATIONS
One 5-year service sward and three 10-year service awards were presented*
All of the work has been completed on the first edition of the new house organ. The Sphere, end it should be mailed to the employees by terch 10, 1966,
work Is continuing on Job Descriptions and Job Performance Standards for the first four levels of supervision in the Production and Agricultural Sales groups.
LABOR RELATIONS
There has been and la continuing to be a great deal of union organizing activity in the Pensacola area and particularly in the case of our next door neighbor, American Cyanamld* The Textile Workers Union of America has handblUed American Cyanamld at their gates on two different occasions and have held at least two group meetings* This effort la continuing and we ere endeavoring to determine whether or not any of this unrest la filtering into our plant.
INSURANCE
During the month of February, ve paid 6l claims under our Group Hospitalization program which amounted to a total of $ 11,004*55.
VS have experienced considerable difficulty In placing our Fire Use and Occupancy Insurance In the London market* We were able to place 85# of this coverage without too much difficulty and have now placed 97i& with a great deal of difficulty* Whether or not ve will be able to place the remaining 2^ la doubtful.
We settled the following claims during the month;
Five claims amounting to $ 1,253*65 under our Automobile
Liability and Property Damage Insurance*
Five claims amounting to $ 2,474.55 under our Public -- ' Liability and property Damage Insurance.
AP00045516
Monthly Report 3- Marcb lj 1966
PfSURftMCB (Cont fd,) We settled the following claims during the month; (cont'd.) Che olein amounting to $ 569.85 under our Fire policy, explosion which occurred in the Amines Plant on February 3, 1965.
EMSjkc
AP00045517
PRODUCTION MONTHLY REPORT March, 1966
i
AP00045518
.ary T L C
INTEROFFICE MEMORANDUM
To:
H. F. Roderick
Date:
April 7, 1966
From: Re:
T. L. Carey March Production
Dear Mr. Roderick:
Copies:
L, W. Gopp H. L. Harwell Dr. W. M. Smith Dr. T. H. Vaughn J. F. Walrath J. G. Gibert
The production units averaged almost exactly budget for March. This was after accruing $10, 000 for future ammonia plant repairs and $5,000 for methanol plant repairs. The following page tabulates the variance results for the past three months and year to date with a column showing April's estimated results.
I think you will find the tabulation an interesting presentation and one that presents a clear picture of our production operations to date.
HIGHLIGHTS
Steam > Steam usage is quite high and requires operation of all units at capacity. The inefficient small boilers accounted for most of the variance. There is no relief in sight until the new, larger boiler is in operation late in the year.
Water - Usage will gradually increase to wipe out the favorable variance to date.
Overhead - This item was badly under estimated for March. It is receiving immediate attention.
Ammonia - A reasonably good month is expected.
Nitric Acid - Major maintenance was performed the latter part of March and a major part of the repair costs will appear in April's results. Production rate will be up as a result of the repairs.
83% AN - Sales volume is expected to pick up in April.
Urea - Practically no production is required for April. Essentially idle plant.
AP00045519
Mr. H. F. Roderick
-2-
April 7, 1966
COST VARIANCES FROM STANDARD
Steam Water Overhead Alloc. toMMA Ammonia Nitric Acid 83% AN Urea U-34 Bay-Sol Frills NP (P2Os) PVC Methanol Methyl Amines Ethyl Amine s Isopropyl Amines
TOTAL
January
3, 821 (2,310)
(889) -
(39,312) (5,582) (6,126) 526 1, 731 (4,490)
(11,366) 44,549 (26,841) (30,200) (10.812) 24,333
-
(62,968)
February
March
Total To Date
April Estimate
3, 924 (4, 133) (6,686)
1, 226 (467)
2,642 1,308 4,371
381 (4,454) (17,112) 46, 543 (1,773) (6,608) 29,970
5,460 7, 734
8, 583 (3, 178) 17,907 (5,482) (31,660) 12,846 2,209 4,536
1,098 (10,874) (29,073)
24,035 (7.555) (9,818) 10,071
123 16,999
16,328 ~ (9.621)10,332
8,000 44 99 (2,500 )'??a 5, 000 ^7Y-2)
(4,256)
(4,000)
(71,439)-
(25, 000)'; i m
9,906
15, 000 i r.sr a
(2,609)-
Budget - r*.
9,433
10,000
3,210
2.000
(19,818)
(5,000)
(57,551)
(20,000).-
115, 127"--12, OOQ-^.^
(36,169) cnrooofc-*--
(46,626)-
Budget ftjt*
29,229 29,916
Budget
-
15, 000 lOo'S
24,733
5,000 ,
62,326
767
125
500
Methacrylates
HIBA MAA MMA
TOTAL
66,570 21,500 37,500
125,570
47,000 30,931 30,033
46,895 46,796 41,484
107,964 .135-, 175
159,465 97,227 107,027
363,719
50, 000 40,000 30,000
120, 000
AP00045520
Mr. H. F. Roderick
-3-
April 7, 1966
U-34 - Sales volume.
Bay-Sol - Relatively high rate of production geared to sales and favorable solution mix.
Prills' - High volume as a result of good sales.
NP - Set a new production record in March and expect to set another in April. High use and high cost of F2O5 plus a write off of prior over-use of sulfuric acid caused the major variance. Operation changeover to 1-1-0 grade indicates a high quality product and good production rates. May will be the first month that should eliminate the negative monthly variance.
PVC - April is off to a good start volume wise and a favorable product requirement should result in an excellent month.
Methanol - Expect production to be about on budget. May make a small favorable variance.
Amines - Detailed reviews and estimates have been made for these two plants. April will be better than February or March. The total
$ , .variance for the year is now estimated to be approximately 250 000
METHACRYLATES
A new production record was set in both HIBA and MAA in March. Losses of product, however, in both the MAA and MMA sections combined to produce the largest negative variance of the year. This was very disappointing and was primarily caused by large amount of polymer formation in both sections. A revised and improved inhibitor addition system has been installed which should materially reduce these losses in April. A 60,000# order for repurified MAA is presently being filled. Following this MAA will be purified prior to conversion to MMA. Prior experience indicates that if relatively pure MAA is the feedstock, yields of MMA will be at or close to design.
AP00045521
Mr. H. F. Roderick
-4-
April 7, 1966
Because the "Liquid Phase Dehydration" system looks so promising, we are moving rapidly to the detailed design stage for possible plant installation. The possibility of making a major process improvement may make it desirable to make the change as early as possible, probably April. A very rough estimate of cost is $20, 000 and a plant down-time of from four to five days. During this down-time other necessary repair work in the plant can be accomplished. These estimates are being firmed up and I will keep you informed.
TLC/djs
r/ T. L. C^rey
AP00045522
T e c h n ic a l S u m m a ry
ESCAMBIA CHEMICAL CORPORATION INTEROFFICE MEMORANDUM
Tm Fnm
Mr. T. L. Carey
DH
April 5, 1966
J. J. Dorsey, Jr.
Gopt
Summary of Technical Department Monthly Reports - March 1966
NEW PRODUCTS
DNT
All phases of this project continued to move forward satisfactorily. The location of the plant in Area B was resolved with the other operating departments of Escambia and the insurance company. It was agreed to locate the storage tanks approximately 15 feet&elow grade in a special revetment.
Minor revisions to process and engineering flow sheets continue to be developed with Chemico. Details of the control room and motor control center were resolved with Chemico* The control room will accommodate future expansions in production.
Some discrepancies are apparent between Bia2zi flow sheets for utilizing various concentrations of nitric and sulfuric acid. These will be resolved.
On Thursday, March 31, Wyandotte notified Sales that material would not be required prior to November 1, 1966. The program to complete the plant by August 1, 1966 will be modified to allow the plant to be completed by perhaps September 1 to 15, while minimizing construction costs.
With the probable late start on Wyandotte's part, it is desirable to produce some material to establish our ability to produce quality material for possible sale during 1967 to other customers, in addition to Wyandotte. It further"appears desirable to investigate the separation of various mononitra tion products and dinitration isomers for possible sale as pure products. This may be necessary to bring the plant operation to capacity in 1967.
ADE
During this period it was possible to demonstrate that a satisfactory yield is being obtained from EDC. The difficulty of separating crude amines
AP00045523
Mr, T. L. Carey
-2- April 5, 1966
from the reaction products in anything short of the basic plant is difficult for the uninitiated to comprehend. Mr. Tolar has done an outstanding job in separating this material in the laboratory and in developing a method of analysis by chromatography which gives reproducible, reliable results. Further, a distillation in the laboratory indicates that products equalling or exceeding that of competitive materials can be produced. His reports of March 18 and March 30, respectively, demonstrate that a 90+% yield is obtained and compare pilot plant produced materials with commercial materials.
To obtain, the type of verification which our management appears to desire for this project may require the expenditure of at least $500, 000 in a pilot plant, which will virtually duplicate the commercial plant in most respects. The fact that these products are made by all other producers from the same raw materials, in the same manner, in similar equipment seems to have little bearing. The anticipated pilot plant program will be completed at the end of May with the production of some quantity of each of the various products for possible future customer evaluation. An additional $15, 000 will be required to operate the pilot plant through May.
How to take the project on to a commercial phase remains to be resolved.
PROCESS IMPROVEMENT
Little process improvement is being carried out in any area except in NP by members of the Technical Department. Messrs. R. E. Jones and J. R. Kersh are totally involved in resolving production problems and supplying some new product information. The plant trial of the new methylamines catalyst looks excellent after several weeks of operation. Necessary process improve ment work should be done in PVC, ammonia, methanol, nitric acid, urea, and ammonium nitrate. The small cost of this improvement work has always been justifiable based on the improvements made,
LABORATORY
Laboratory costs are approximately $7,000 above budget for the first quarter of 1966, including the work in the ADE program. However, when this work is transferred to the work order taken out to accumulate operating costs in the ADE project, actual costs are estimated to be approximately $2, 000 below budget for the first quarter.
An analysis of laboratory costs indicates that four major areas share 82% of these costs; their individual percentages are as follows: MMA - 42%, amines - 17%, PVC - 13,3%, and ADE - 9.7%.
Four laboratory technicians were officially transferred to MMA pro duction this month. During April, when the new chromatographs-tfor amines
AP00045524
Mr. T. L Carey
3 April 5, 1966
are obtained, the transfer of some laboratory technicians to amines pro duction will be effected with an ultimate release of operators forfcther plant assignments. Virtually no work is being carried on in the laboratory to produce new amines.
A considerable amount of work, including a visit to the State Board of Health to discuss Escambia's effluent to the bay, was carried out by Mr. Fowlkes. The program he has developed would appear to maintain a satis factory effluent control program as far as the State Board of Health is concerned.
Considerable work was done on evaluating new analytical methods for methylamines and comparing the precision of these new methods as well as the quality of Escambia's amines with competitive products.
ENGINEERING
A summary of the status of various construction projects is attached. A more detailed analysis is contained in the engineering report of these projects. Mr. Metcalf's report on project work is included with the engineering report. His report on instrument and electrical maintenance is covered elsewhere.
Similarly, those projects which are still handled in Maintenance are listed in the project summary. There is a need to clarify the project res ponsibilities in these areas.
The large major projects continue to show overrun. The worst condition appears to be in the methyl methacrylate construction work, which particularly suffers from the need to install the equipment with the plant in operation. This has led to a major overrun in the labor area. A separate report will be issued analysing this.
Another area of substantial overrun is in the NP storage building, where it was necessary to fabricate some conveying equipment, which might normally have been purchased at a lower cost, in order to complete the plant for the fertilizer season.
REVISED FIVE-YEAR EXPANSION PROGRAM
A revision was issued on March 5, 1966. During the month various meetings were held to discuss further revisions to the program. At month's end it appears that agreement on the content of the program has been reached and it is mainly necessary to define the timetable for the various projects and to firm the economics on the methanol expansion program.
mdc
J. Dorsey, Jr.
AP00045525
`roiect No.
Tide
SUMMARY Of PROJECT WORK STATUS
Appropriation Cammittsd Rsvlssd Completion MS MS MS Date
6499
Increase Capacity MMA Plant
175.0
287.0
287.0
5- 1-66
Remark* Job complete.
650?
Air Conditionli Enclose Wet Bay Control Room
6.0 3. 3 6.0 4-30-66
6524
Purchaie Reactor Drop Valve* . PVC
12.0
10. T
12.0
5-1-66
Valves are hare,
6526
Amine* Catalyst Test Unit
2.2
1.7 2.4 4-30-66
6528 6532
Expand Shop io Area A Additional Rail Siding
11.| 26.5
4. 3 22.4
11.1
4- 30-66
23.5
5-1-66
Job complete.
6533
Ammonia Recovery Pus* sure Control System
3. 3 non*
3. 3 T-1-66
6565
DNT Plant
1070. 0
341.0
1070.0
8-1-66
No change.
657 3
New NP Warehouse
' 225.0
271.0
272.0
5-1-66
Job complete.
6583
Equipment to Produce tBN h SEA - Amines
223.4
106. 5
224.0
3-1-66
On schedule.
6604 6605 661?
6618 6620
New 600 pel 100, OOOffhr. Boiler
Upgrading Water Treatment System - Boiler
Additional Bulk Car Loading Facilities - PVC
320.0 105. 0
10,4
Holding Bin lor Alpine Mill PVC
5pare Reactor Agitator Motor PVC
3.6 4.2
132.0 83.0
2.0
320.0
11-1-66
105. 0
11- 1-66
10.4
7-1-66
Project still on schedule and budget.
Project still on schedule and budget.
On schedule,
2.7
3.6 4. 1.66
Complete.
3. 5
4.2 7- 1-66
On schedule.
6621
Refrigeration Unit for Cooling Solution Tank* - PVC
12.0
non*
12.0
Indefinite
Select equipment In April 1466.
6622
Spare Block for Roeovory Compressor* - PVC
14. 3
12. 0
1J. 3
6-1-66
On schedule.
6626
Packaging Equipment to Uss Valvs Bags tor PVC
18.0
12. 0
18.0
6-1-66
On schedule.
6624 6631 6636 66 32
6633
6634
Control Room Chromatograph*
Additional Electric Heat fa New Converter for 11 Plant
H. P. Water Pump, H. P. Scrubber #1 Plant
9.6 8.0 15.0
4.0
New Methylamino* Check Tanks
Aqua Mix Tank #1 Aminas Plant
12.4 5.6
7. 3 13. 7
1.4 7.4 3.4
9.6 35.0
5-1-66 6-1-66
4.0 5- 1-66
12.4
5-1-66
5.0 4-11-66
Availing delivery. Revised to Include gt* fired heater.
On schedule.
On schedule.
On schedule.
AP00045526
Stimm*ry of Project Work Statue March, 1964
Pago 3
Protect No,
Titla
66)5
Plant Steam Recorder
Appropriation MS
l.S
Committed Revleed Completion MS MS Date
non*
l.S 6.1-66
Remark* On order.
6641
1560-80001 1580-80002
MMA Till Centrifuge Cryttallieer Revltlen*
1.3 16, 3
3.9 9. 3 8-1.66
8.9
16.3
8-1-66
On echedute.
6647 6678
Ammo-Phot Production
Nitrogen Sale* Warehouaee Appropriation (or 12 Appropriation (or 4
200.0
13. 3 11. 1
6676
Nitrogen Salea Bagging
47.2
45.0 16.0 32.0
200.0
6-1-66
18.0
3-26-66
47.2
3-18-66
Some delay* reiulted in getting equipment approved.
4 of Engineering reeponellAlty will over run becauaeef ore ot Salta coat aetimat* Job complete 3-28-66.
Complete 3-16-66.
1580-18629 Independent Raw Water Supply Pvc
1580-16836 Hot gee bypati valve on refrigeration machine
1580-18835 Aft*rce1r for Att Com* prooior
1580-16839 New Blowdown Tank (or
1560-16851 Chunk Cruaher (or Slurry Sy item
1580-16854
30-Ton Air Conditioning Syetem for Field Admlnlatration Building
1580-18857 Concentrator Vent Linee 1770-5066 Additional Amine* Storage
1770-5082 1770-6003
ADE Pilot Plant PVC Reactor Reglaaalng
9.7 1.2 t, 9 2.7
.1
7.4
2.0 250. 0
50.0 38,0
.1
9.7 9-1-66
On echedule
1.0 1.2
1. 3 1.9 1.5 2.1 5.18-66
.1 .9
7.0
7.4 4- 30-66
On tchtdule.
,2 260.8
89.0 15.0
2.0 27.0
4-6-66
60. 0 38. 0
9-1-66
Complete April 1966.
Job Complete. On tchtdule.
/fie 4/5/66
AP00045527
P ersonnel
ESCAMBIA CHEMICAL CORPORATION Interoffice Memorandum
To: to. T. L. Carey
Date: April 4, 1966
From: E. M. Spurlock Re: Monthly Report - Fersonnel Department - torch* 1966
PERSONNEL
Activity for the 1Month
Division
No. of
No. of
Einployees
March
torch
ESroloyeea 1966
2/28/66 Additions Separations 3/31/66 Budget
Executive
57
Research
5^
Agricultural Chemicals 164
Industrial Chemicals 15
Production
m
4
3 15
0
11
1 60 64 1 56 59 7 172 199 * 0 15 18 _4 ho6 399
Totals
683 39
13 709 738
* This includes l6o as Hated on the budget sheet plus 39 temporary employees who were not shown in number on the budget sheets*
There were 193 walk-in applicants, 134 applications were issued and 11 received by mail. Sixty-one applicants were interviewed and 57 were tested.
TRAINING
Schools were held for the operation of trackmobiles and forklifts. There were 6 trackmobile operators and 6 forklift operators licensed.
SAFETY
The Corporation has worked 19 days or approximately 73,549 man-hours without a disabling injury. The various division records are as follows:
Division
Man-hours
Days
New York Office Research Division Atlanta Division Pensacola Plant Corporation
334,400 794,000
20,000 1,829,000
73,549
1,700 3,180
19 801
19
AP00045528
Monthly Report
-2- April 4, 1966
SAFETY (Coat'd.)
The Atlanta Division experienced a lost tine Injury during the month.
Personnel of the Anrconla-MBthanol plant in Pensacola completed six years without a lost time injury.
Medical Section
The Medical Section treated 15 injuries for Escambia and 42 for Carroll, performed 15 pre-employment and 17 annual physicals and gave a total of 12 immunization injections.
EMPLOYEE RELATIONS
Three 5-year service awards and two 10-year service awards were presented.
The first issue of the house organ, "The Sphere", was mailed in March and was well received by the employees.
LABOR REIATIONS
The Textile Workers Union of America has petitioned the National labor Relations Board for an election In the American Cyanamid plant. After the petition was filed, the International Chemical Workers Union moved in two organizers for the purpose of intervening in the Cyanamid election. They are presently making house calls and handbilllng the company. They have informed ua that once the election at Cyanamid is completed, the Chemical Workers expect to work on Escambia's employees. We have held three meetings with all first-line supervisors for the purpose of acquainting them with their rights and the way In which they can be most effective in combating this coming organizational drive.
INSURANCE
During the month of March, we paid 85 claims under our Group Hospitalization program which amount to a total of $ 12,850*54.
The London tferket on Use and Occupancy Insurance for chemical plants has become almost nonexistent due to tremendous losses in 1965 resulting from hurricanes, we did manage to secure a quotation from the London market on our renewal which was due April 1st but the Underwriters could not guarantee ua that they could place the entire coverage. We then tested the Domestic fferket and obtained a firm quotation for 100$ of our coverage from the Oil Insurance Association, however, we were required to accept a 5-day deductible. The London Market had quoted a flat $ 100,000 deductible, we have accepted the O.X.A. proposal and will work out the details next month. Prior to this, we had no. deductible. This coverage was worked out with the assistance of the EBS Insurance Department.
AP00045529
Monthly Report
-3 April k, 1966
INSURANCE (Cont'd.)
We Bettled the following claims during the month of March:
Six claims amounting to $ 1,391*31 under our Automobile Liability and Property Damage Insurance*
One claim amounting to $ 211*63 under our Public Liability and Property Damage Insurance*
TAXES
We filed Ad Valorem Taxes for the Pensacola plant with the Santa Rosa County Tax Assessor on March 30, 1966, however, ve were advised by the Tax Assessor that they were endeavoring to go on a 100# Evaluation during 1966* If this study is completed in time for the 1966 tax rolls, the rendition made by us to the Tax Assessor will be void and we will have to negotiate another tax evaluation.
EM3:kc
AP00045530
PRODUCTION MONTHLY REPORT April, 1966
AP00045531
L .C .
INTEROFFICE MEMORANDUM
To:
H. F. Roderick
Date: May 9, 1966
Fr om: Re:
T. L. Carey April Production
Dear Mr. Roderick:
C opy:
J. G. Gibert L. W. Gopp H. L. Harwell Dr. W. M. Smith Dr. T. H. Vaughn J. F. Walrath
Two of the production units had outstanding results for April. Both PVC and NP set new monthly production records. PVC produced 4, 604 M pounds and NP, 6,710 tons. NP production costs were $1.81 per ton lower than the previous best costs.
Nitric acid was as predicted - a $15, 000 negative variance due almost entirely to a carryover of costs from the maintenance shutdown in March. Volume is now up to standard.
Methanol was negative $12,000 due to a broken tube in one of the reformers. This necessitated operating the plant at less than half rate for three days. Five thousand dollars was again accrued for future maintenance.
Ammonia had a reasonably good month with a positive variance of $23, 000. Again $10, 000 was accrued to help defray the costs of a major maintenance turnaround that is being planned for late June or early July.
The nitrates and solution plants were negative by $3, 700. The problems here were no urea production due to sales and not sufficient nitric acid and ammonia to run 83% and prills at a good rate.
The amines plants experienced considerable process difficulties which resulted in a production substantially below budget. Yields were good however, which partially offset the volume variance. The plants are now operating at a much better rate and with the additions being made, it is expected that by July these plants will be operating at above budgeted rates. April variance was a negative $54,000.
The overall results from all of the production units was negative $37, 100.
ti
AP00045532
Hi F. Roderick
-2 -
May 9, 1966
May will be an unusual month from the agricultural chemicals portion of our production. This was brought about by a sales situation:
1. NP inventory is sufficient to provide for all projected sales.
2. A shortage of ammonium nitrate and solutions. (Sales needs all we can possibly make and sales prices are good at this time.)
Because of this situation, a study was made to compare May profitability of making NP vs. diverting the NP use of ammonia and nitric acid to production of ammonium nitrate and solutions.
The results were as follows:
1. NP, no production - variance 2. Ammonium nitrate and solutions
increase - variance 3. Profit from additional sales of
prills and solutions 4. Value of granulating 3000 tons
NP fines during this period vs. selling at $3 off list
-$55,000 + 26,000 + 40,000'
+ 10.000
Net in favor of diverting NP raw materials
+$26, 000
Due to this special situation that exists at the height of the fertilizer season, the decision was made to shut the NP plant down and convert the ammonia and nitric acid to AN, prills and U-34 solutions because of the better profitability.
This was a reluctant decision because NP would have produced a positive variance in May as has been predicted. For example, with the same production as April and using only the difference in price of phosphoric acid if purchased under our agreement with W. R. Grace, April's results would have been $6, 000 positive. (This acid is available from Grace in May.)
AP00045533
H. F. Roderick
-3-
May 9. 1966
There is one other advantage and that is this shutdown will allow for the few days necessary to complete installation of the ammonium phosphate equipment. This project is on schedule and should be in operation on June 1.
Methacrylates
The operation of this plant featured a number of major changes that were being completed at the end of the month. The plant was shut down for eight days and this coupled with the changes contributed to the negative variance of $161, 000.
The changes:
1. Installation of liquid phase dehydration in place of the vapor phase. This will be much simpler equipment and operation and it is expected will improve yield and quality.
2. Repacking of the methanol stripper.
3. Installation of an additional tray in the HIBA column to improve quality o HIBA by removal of more of the low boilers and better operation of the past flash unit.
4. Installation and testing of the Western States continuous centrifuge.
5. Change to use of xylene in the MAA decanter.
6. Set up for plant scale test of 95% isobutylene to improve absorption and determine operation of reactors under these conditions as well as operation with no mother liquor return. Hopefully will point the way to increase HIBA production.
It is hoped that most of these items will have been evaluated by the end of May.
i i
AP00045534
H. F. Roderick
-4 -
May 9, 1966
Bonus
The production incentive plan was announced to all operating and maintenance groups early in April. Meetings were held with each group individually to announce and explain the plan. It was well received and,I think, is beginning to show results. I am well pleased so far.
Superintendent Reports
You will note that this month the area superintendents have each estimated the variance for May in their units. This is the logical outgrowth of the cost awareness program started in February. This program coupled with the bonus plan will be most beneficial to improved results.
AP00045535