Document Oz65XbV7OkLdkN9QXEL09jwre
J. D. Olson
Interoffice Communication
From: Date:
Subject:
D. E. Knittig and R. C. Tebo May 30, 1990
5305 RESIDUAL VCM REDUCTION - PHASE I
Based on the comments from the RVCM Reduction meeting on
April 10, 1990, we want to implement Phase I of the RVCM
Reduction Project. Phase I will be the installation of:
.1 A silo air heater.
2. Additional spargers in T-407, 3. Flow indication on T-646 through T-652 and
T--407,
4 . Sparger team cleanout design on T-407, 5. Repairs to the old module hot water charge to
rinse control valve, CV-497, 6. Test spargers on T-647.
.Phase I 1 2. 3. 4. 5.
items will provide for: Heated silo air, Improved agitation, More reliable agitation. Hot rinse, and
Recipe optimization.
Phase II items will be: 1. Air reliability, and 2. Small blend tank sparger improvements.
Phase II will be implemented after Phase I results are
evaluated.
Phase I items are to be 4th quarter
projects. The installation goal is November 1990.
Doug Knittig Process Engineer
Rich Tebo
cc:
Aberdeen - RWS, DCS, JDO, JMV, REP
Houston - EJM, PCS, RDM, MCM Saddlebrook - MAE Austin - HGC
DFJ,
RBN,
SCH,
JME
VAB.0001167570