Document O1VJKkvgaBvDX5LdMqZVMY4De
Anniston, Alabama
April 10, 1968 CEA 14JO AKOCLOK EXPANSION ANNISTON DESIGN QUESTIONS
H. V. Peterson CBD General Offices
A. A. Haydel I. E. Smith
la ansver to your following questions, we can put 4465 through tha 5460 line and Flakar Feed Tank and then to a drumming station, and all other solids also. Steel pipe is ok for the above.
I talked with E. E. Smith and k. A. Haydel and they agreed that separate Hl-Level Alarms ere necessary for the eight tanks or a remote pump cut off be supplied for each tank.
JCB:kd
J, C. Bradley
0285252
M
TOWOLDMONOQ44199