March 3, 1978 Richard J. Palmieri 0. S. Department of Labor Occupational Safety and Health Ada. Dover Area Office 2 last Blackveil St. Dover, N. J. 0?801 Mr. Palmieri, The following report la in response to your 2/10/78 list of citations noted during Mr. Debt's January Inspectiont 1. Abatenant Date - Immediately. This ltan is completed. 2* AbatementDate - 3/13/78 This Item la completed. 3. AbatementDate - 3/13/78 Signs have been ordered and will be Installed by 3/13/78. * Abatement Date - 3/13/78 This Item Is in progress and will be completed by 3/13/78. 3. AbatementDate - Immediately. This item Is completed. 6. Abatement Date - Immediately. This item is completed. 7. Abatement Date - 2/27/78 The welder in question was taken out of service. Materials have been ordered and upon Installation the equipment will be put back in servioe. Sincerely, JRHlcn J. R. Hsarlsnder, Works Manager bcc: Chicago 170-6, J. D. Cornell Clark Plant, M. P. Kane R. H. Taylor T. Phelan o l/>