R. C Herman - (6725) - General Officer.
April 10, 1969 Work Remaining on CEA 1430
TO * *- Anniston
H. E. WalCrep - Amiistcr
H. L. Vi i. Illarr.s -
"
R. M. KountE
R. R. Cook
K. A. Ilayckvl - Anniston
L. Dirchf ie-i d
Confirming our discussion of April 8, 1969, the f ollo'-'i ng problems remain to be resolved prior to closing CEA 1430.
1. Dust collection
2. Biphenyl temperature control.
3. Aroclor flaker operation.
ci. Plastic material over the drum. b. Flake breaker operation. c. Housekeeping problems resulting from aroclor
under the pan.
4. Level indication in the biphenyl hopper.
5. Pan for collecting drippage from hose station at the drumming scale.
6. Replace air operated vibrator on biphenyl hopper with an electric one.
7. Modify north truck dock to add adjustable steps.
8. Installation of drumming scale. 9. Install clay oven.
The following action is being taken to resolve these problems: 1. Dust Collection
Based upon an evaluation of the existing systafn
Bill
Scbuchat of CED, we feel that the problems ob .clogging in the rotoclone are caused by the condensation/' aroclor
and biphenyl fumes in the duct work. This oefurs when
the hot fumes come in contact with the cool air coming
from the hoppers and the bagging operation. As conden
sation occurs, a eutectic is formed which is plastic in
nature, and attracts the dust from the cool, air stream
resulting in a large amount of plastic material being fej^t to the rotoclone.
0357151
TOWOLDMONOQ44782
CEA 1430
-2-
April 10, 1969
We are going to modify the duct work such that less eutectic is formed in the duct. The eutectic which is formed will be collected in a sump rather than allowed to flow into the rotoclone or back down the ducts to the.1st floor. The ductwork drawing was mailed to H. E. Waldrep on 4/7, and a revised drawing was mailed on 4/10. Mr. Waldrep will expedite the fabrication of this new duct system. Based upon the time required for the fabrication, which I should know by 4/14, I will coordinate with you the installation date. During installation, the rotoclone must be disassembled and completely cleaned.
The sludge removed from the collection tank will be in the liquid state when both flakers are in operation, and in the solid state when only one flaker is in oper ation. Steps have already been taken to heat the re circulating water in the collection system to a tempera ture above the melting point of the eutectic (40C).
In the event that we still have problems with this system after the above steps are taken, we will have some alter nate plans available.
Investigations are underway by Bill Schuchat to find a
method of handling the fumes so that they might be col
lected separatly from the dust. The laboratory at Anniston
is evaluating H.B. 40 and 1242 or other liquids to see
V
if biphenyl and aroclor could be dissolved. If a high
boiling point solvent could be found, it could be used
as the scrubbing media in the rotoclone. Bill Schuchat
is working on the basis that this is an urgent problem.
The work by the Anniston laboratory should be expedited
as much as possible.
DUST COLLECTION SUMMARY
A,. Modify ductwork system - revised drawing sent to
CED Construction 4/10.
SjyfTUS,
B,. Clean out rotoclone during ductwork installation, this will be done by the plant.
c,. Continued investigation by CED and Anniston for
alternate plans.
LLF 7
1
'
0357152
TOWOLDMONOQ44783
CEA 1430
-3- April 10, 1969
2. Biphenyl Temperature Control
We will convert the steam heating system to a therminal heating/cooling system on the flaker pan, flaker feed tank, and the jacketed piping inside the warehouse. The plant will lower the temperature of the biphenyl storage tank to 80C (or as close to 80C as possible) the plant will shut off the steam to the jacketed transfer line during the transfer of biphenyl to the feed tank (day time transfers only).
A diagram of the new therminal system was sent to you on 4/8, for your comments. We are preceding to order the new pump and instrumentation. We will not proceed with the piping design until we have your comments.
3. Aroclor Flakers
A. Plastic material coming over drum. The ductwork
modifications discussed earlier will stop the
plastic drip back at the center of the drum. Goslin-
Birmingham feels that the plastic material at the
west end of the drum is caused by poor water distri
bution inside the drum. A new water distributor is
being made by Goslin. The availability of this new
distributor will be during the week of 4/14.
'
B. Flake breaker stalling
This should be corrected by (A) above. The plant is purchasing a new flake breaker from Goslin. This
Aj j fXl
new breaker will be insulated on the pan side to
prevent build-up of flake on the sides of the breaker.
C Housekeeping problems - melted flake under the flaker pan.
WeepThe new flake breaker being purchased by the plant
will have modified deflection plates which should
preclude flake from getting under the pan. The
Qfriec-n><
Ef-xt e >: 0-rotation of the flake breaker has been reversed,
and flake will be thrown away from the flaker pan.
4. Level Indication In Biphenyl Hopper
A "bindicator" will be purchased on 4/10. I will advise
you as to when we will be ready to install it. You are
aware that "bindicators" require regular maintenaniceey./
^---------------------
-v
-
?
0357153
TOWOLDMONOQ44784
CEA 1430
-4-
April 10, 1969
5. Pan for Collecting Drippage from Hose Station at Drumming Scale.
I will provide fabrication information to CED Construction^,
as soon as I receive your recommendations as to the
required size.
"" '
V/*
6. Replace Air Operated Vibrator on Biphenyl Hopper with an Electric One.
An electric vibrator will be ordered by 4/11.
7 Modify North Truck Dock to Add Adjustable Steps
The adjustable steps will be ordered by 4/11. The modifications to the dock will be made when the steps arrive.
fjo ftoPlf'
Installation of Drumming Scale
This should be complete by 4/11. Upon completion of the
installation, a Toledo representative will check-out the
operation. It will be available for your use after the
check-out. This should be 4/11 or 4/14.
f/A^Y
9. Installation of the Clay Oven
This oven is at Anniston now. We are holding the install
ation pending your agreement as to its location.
"Yf&i "V /Sr/.
Upon the completion of the work outlined in this memo, the project will be closed. We are giving this work the highest priority, and I will keep you advised as to our progress.
RCH/bl
c. R. C. Herman