Document N2r5pqZrYz5KyLNn62y8abRjR
Monsanto
FROM
ANNISTON, ALABAMA
DATE SUBJECT
August 2, 1967 Aroclor Expansion - CEA 1430
REFERENCE
TO R;- P. Stevens
c:H. C. Carder W. B. Papageorge L. C. Fuhrmeister W. F. Taffee V. R. Haupt H. Williams R. Yates
As per your request production cost standards and some background for project justification have been assembled and are attached. The cost estimates have been given a cursory review by the manufacturing personnel and have produced no violent objections since they are truly estimates.
--J. MacPherson
/
IN* 10 REV. 6- 64
DSW 376798 STLCOPCB4099075
Project Justification
1. Customer service - new facilities will give Monsanto the ability to store minimum bulk inventory as defined by production planning.
2. Quality - new facilities will have the materials of construction and quality promotion system (i.e. nitrogen blanketing) necessary to maintain the high quality Aroclors produced in the refining units.
3. Solid Aroclor Debottlenecking - the solid Aroclor system will be
debottlenecked to 12.0 M lbs/yr by the installation of the new flaker. New earnings of $130,000 may be claimed by the project.
4. Tank car savings - 20 tank cars are required for the liquid Aroclor fleet as of now unless adequate storage facilities are provided, an additional 8 cars will be necessary to prevent bottlenecking of the liquid production. This would represent a capital expenditure of $153,000 ($19,l35/car).
5. Labor savings - YTD laborer effort required by the Aroclor/Biphenyl/ HB-40 complex is 14 men with 7% overtime, this represents a projected laborer hour expenditure of 31,000 hours. Based on the production estimates 'shown in Anniston TSD report 370-720 (1) the laborer hours through 1971 required for the existing installation are:
Laborers hours
Laborers (Aroclor/Bi0/HB-40)
1967
31,200
14
1968
37,200
17
1969
40,600
19
1970
42,200
19
1971
44,859
21
CED preliminary design estimates indicate the following labor re quirements:
Biphenyl - 1 man bagging / flaking
Solid Aroclor - 1 man bagging / flaking
BiO/Aroclor - 1 man to handle conveyor system for bags
Liquid Aroclor - 2 men drumming / palletizing
DSW 376799 STLCOPCB4099076
These activities represent 65% of the total effort for the Aroclor/ Biphenyl/HB-40 complex. Laborer breakdown may be presented as follows with the criteria that 92.5% of the laborer effort is in Aroclor/ Biphenyl:
Aroclor/Biphenyl Laborer
,
' .
(Aroclor/Biphenyl)
(existing system) CED Facilities + Other Activites = Total Laborers
1968
16
5 +6
= 11
1969
18
5 +7
= 12
1970
18
5 +7
= 12
1971
20
5 +7
= 12
therefore the labor not required for the Aroclor/Biphenyl areas will be:
Laborers (existing system)
Laborers (CED Complex)
Diff.
1968
16
11
5
1969
18
12
6
1970
18
12
6
1971
20
12
8
Using $10,000/man, the CED project could claim up to $80,000 labor savings.
The laborer split is assumed to be the following:
Liquid Aroclor
Solid Aroclor
Biphenyl
1968
4
4
3
1969
4
4
4
1970
4
4
4
1971
4
4
4
dS\N 376800
STLCOPCB4099077
Production Cost Estimates - the following data was estimated, assumed, or projected on developing the standards:
Liquid Aroclor
Solid Aroclor
Capital
$1,660,000
$490,000
FIE
6,050
3,375
Depreciation
1968
30,100
8,910
1969
27,200
8,020
1970
24,100
7,120
1971
21,100
6,240
Salaries
1968
1,528
800
1969
1,635
880
1970
1,749
970
1971
1,871
1,000
Medical Expense
$12,000
$10,000
Technical Service
1968
2,000
955
1969
2,140
1,045
1970
2,290
1,135
1971
2,450
1,230
Labor
Packing
Production
1968
3.2703
3.916
1969
3.3703
4.016
1970
3.4703
4.116
1971
3.5703
4.216
DSW 376801 STLCOPCB4099078