CMP REACTIVE CHEMICAL REVIEW
MEETING CALLED BY: Don Taylor DATE: Thursday, November 10,1994 PLACE: Building 4601 Conference Room START TIME: 8:30 END TIME: 10:00 PARTICIPANTS: CMP Staff, Reactive Chemicals Committee
PURPOSE: Review Reactive Chemicals concerns in the Chlorinated Methanes Products production unit
AGENDA: TOPIC Introduction and review of past action items Ml production unit review M2/M3 production unit review Sealants, reactive chem reports, miscellaneous Discussion and follow-up
PREWORK: none
FACILITATOR Bruce Miles Steve Ledoux Jim Haney Kevin Kelley Group
TIME 15 min 20 min 20 min 20 min 15 min
CONFIDENT! Al DO 006548
November 15, 1994
The Dow Chemical Company P 0 Box 400
Plaouemine Louisiana 70765-0400
Don Taylor 4601 Bldg.
REACTIVE CHEMICALS NEW SUPERINTENDENT REVIEW - CHLORINATED METHANES PLANT- NOVEMBER 10, 1994
AUDIT TEAM: Gerald Wagener, Don Jones, John Monroe, Joe Schell, Buck Bailey, Scott Hanrahan, Mark Mitchell, Seb Corbino
RECOMMENDATIONS:
1. Concerning the inadvertent use of titanium parts in dry chlorine: a. Add a statement to the block safety indoctrination package on the reactive chemical hazards of using titanium parts in dry chlorine service. b. Consider adding a checksheet that addresses this hazard to maintenance procedures for equipment used in chlorine service.
2. Concerning the reactive chemicals review slides for the Thermal Chlorinator: Add "Evacuation of personnel from reactor area during start-up" to the lines of defense for avoiding injuries due to a possible deflagration/detonation.
3. Consider the following scenario and make sure appropriate safeguards are in place to avoid a runaway decomposition: D-1 Tar pot is blocked in and 235# steam flow does not shut off. If the decomposition temperature is not known ARC data should be generated.
4. Review the materials of construction in the sulfuric acid demister and make sure that they are compatible over the range of temperature and % sulfuric acid that will be encountered in normal and upset conditions.
Please respond in writing to the committee chairman within one month as to action taken or planned in regard to these concerns.
f>IC;
Gerald Wagener, Chairman Reactive Chemicals Committee