INTERNAL CORRESPONDENCE
UC 149- Z
CHEMICALS AND PLASTICS
TO (NAME) Mr. R. L. Frantz COMPANY Mr. J. L. Jones LOCATION Mr. R. H. May
Mr. R. Q. Payne Mr. A. A. Petersc Mr. G. T. Pyle Mr. O. A. Shelton
P. O. BOX 471, TEXAS CITY, TEXAS 77590
date
December 3, 1974
subject VC1 Exposure Projects
Gentlemen:
A meeting was held on Monday, December 2, 1974 by the Suspension/NonSolvent Department and Maintenance personnel in order to establish priorities and expected completion dates for several of the vinyl chloride exposure projects now underway in the area. The following is a result of this meeting.
Project
Priority
Completion Date
Dikes around Tank Area 4 (contract)
MEK liquid level instruments
Compressor Room exhaust fans (wrong fans, no motors yet) In-bin blenders, bldg. 174
Steam addition modification to No. 5 BD tank
Vacuum pump orifice (meter to NashHytor)
#2 &: #3 V.S. level control N/5 flash tank instrumentation and piping
C Autoclave seals
Water addition to C Autoclaves (waiting for valves to be delivered) (contract) Repair cold brine motor valves
2 lj 1
1 1
February 1, 1975 December 13, 1974
December 13, 1974 Add piping as valves are delivered
UCC 090982
YC1 Exposure Projects
2.
Project
Priority
Instrumentation for decanting water from VC1 tanks (contract)
Samplers on blowdown tanks
1 1^
MEK vent system - vacuum to east line steam-jet
Completion Date
January 15, 1975 Awaiting VC1 exposure analysis
A follow-up meeting will be held again to further discuss these projects on December 16, 1974.
Sincerely,
RPK/sld
R, P. Keefe
UCC 090983