Document N20Gxb86dbwE7xBMk3a3J1Kp8
DATE: SUBJECT: FROM: THRU: TO:
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGIONS
77 WEST JACKSON BOULEVARD CHICAGO, ILLINOIS 60604
JUL 2 4 2019
CLEAN AIR ACT INSPECTION REPORT Reliable Asphalt, Chicago, Illinois
Jason Schenandoah, Environmental Engineer AECAB (IL/IN)
Nathan Frank, Section Chief AECAB (IL/IN)
File
BASIC INFORMATION
Facility Name: Reliable Asphalt
Facility Location: 3741 South Pulaski Road, Chicago, Illinois
Date of Inspection: June 20, 2019
EPA Inspector(s): 1. Jason Schenandoah, Environmental Engineer 2. David Sutlin, Environmental Engineer
Other Attendees 1. Paul Etter, VP General Manager, Reliable Asphalt 2. Bob Madden, Equipment Manager, Bigane Paving Company 3. Paul Alfi.ch, Oiler, Bigane Paving Company
Contact Email Address: rmadden@biganepaving.com
Purpose of Inspection: To determine compliance with the Clean Air Act.
Facility Type: Asphalt paving mixture manufacturer
Arrival Time: 8: 11 am Departure Time: 9:50 am
Inspection Type: ISl Unannounced Inspection
D Announced Inspection
ISi Credentials Presented ISl CBI warning to facility provided
The following information was obtained verbally from Bigane Paving Company (Bigane) unless otherwise noted.
Company Ownership: Reliable asphalt owns the asphalt plant, but Bigane operates the plant.
Process Description: Reliable Asphalt uses virgin aggregate in every batch that is manufactured. Depending on customer needs, the asphalt specifications can also require certain percentages of fine recycled asphalt pavement (RAP), course RAP, and Recycled asphalt shingles (RAS). Virgin aggregate is sent through a natural gas fired dryer to remove moisture and add heat before being sent into the mixer. Liquid asphalt, RAP/RAS and other additives are added at the mixer. The dryer and mixer are in series. The asphalt materials flow from dryer to mixer, but the air flow is countercurrent to the material flow. Emissions from the mixer and dryer are routed to a baghouse. From the mixer, asphalt is dropped onto a conveyor and sent to a series of storage silos. Asphalt is released from the silos through a trap at the bottom and loaded into trucks to leave the facility.
Staff Interview: The amount of recycled material that can be used at the mixer is limited by heat transfer from the raw aggregate to the RAP, RAS, and liquid asphalt and the maximum operational temperature of the dryer. Approximately 6-7 years before this inspection, the asphalt plant was retrofitted with new technology. Two additives were discussed during the inspection: rejuvenator and Evotherrn. Rejuvenator is used to soften the recycled material to make the mixing process more efficient. Evotherrn is used in the colder months of operation to hold heat in the asphalt and make spreading the asphalt easier.
TOUR INFORMATION
EPA toured the facility: Yes
Photos and/or Videos: were taken during the inspection.
Field Measurements: were not taken during this inspection.
CLOSING CONFERENCE
Requested documents: Safety data sheets for the following:
Page 2 of 4
o Evotherrn o Rejuvenator o Liquid asphalt o Liquid cold patch 2016-2018 Air Emission Reports Reports for all stack tests that occurred after plant retrofit occurred.
SIGNATURES
Report Author:
Page 3 of 4
Facility Name: Reliable Asphalt Facility Location: 3741 South Pulaski Road, Chicago, Illinois Date of Inspection: June 20, 2019
APPENDICES AND ATTACHMENTS
Appendix A: Digital Image Log
Page 4 of 4
Facility Name: Reliable Asphalt Facility Location: 3741 South Pulaski Road, Chicago, Illinois Date of Inspection: June 20, 2019
APPENDIX A: DIGITAL IMAGE LOG
1. Inspector Name: Jason Schenandoah
3. Company/Facility Name:
Reliable Asphalt
5. Number of Images:
11
2. Date(s) of Inspection: June 20, 2019
4. Street Address, City, State: 3741 South Pulaski Road, Chicago, Illinois
6. Archival Record Location:
Photos/videos are saved to a CD-R labeled "Reliable
Asphalt, Chicaf<O. IL 6-20-2019 Inspection: !mazes
Image Number
1 2 3 4
5 6 7 8 9
10
11
File Name IR 0071.jpg MOV 0072.mp4 IR 0073.jpg MOV 0074.mp4
IR 0075.jpg DC 0076.jpg MOV 0077 .mp4 MOV 0078.mp4 DC 0079.jpg DC 0080.jpg DC 0081.jpg
Date and Time (incl. time zone and DST)
6/20/2019 8:29 6/20/2019 8:30 6/20/2019 8:44 6/20/2019 8:48
6/20/2019 8:51 6/20/2019 8:56 6/20/2019 8:57 6/20/2019 8:59 6/20/2019 8:59 6/20/2019 9:00 6/20/2019 9:00
Description of Image FUR image of baghouse stack FUR video at baghouse stack
FUR image of mixer/conveyor junction FUR video at top of drag conveyor leading to silos FUR image at front end of mixer with pipe feeding liquid asphalt
into mixer Rejuvenator product label FUR video of silo load-out FUR video of silo load-out Cyclone with input duct from dryer and output duct to baghouse Exhaust duct from back end of mixer to dryer/mixer junction Dryer, exhaust duct, and baghouse in background
Appendices Page 1 of 1