The Anniston Plant plans for poly-chlorinated biphenyl (PCB) determinations In liquid vasts streams including sources,quantities and recoanded actions ara included. Wa do not plan to look for atmospheric losses based on our present mutual feeling that losses to the atmosphere are negligible.
The target dates are based on 1) one mao full time (E.G.Wright) sampling,
correlating and reporting these and other studies; 2) one chemist for one to
two months and sufficient analyst time thereafter; 3) that adaquate methods
are developed and reduced to plant practice in time; 4) that adequate Instru ments and Instrument time are available. Items tvo through four require re shuffling of the Anniston Laboratory plans and will be discussed with W. A. Kuhn and J. E. Smith (since lov color Aroclor 5460 sample preparation is affected). Also,although electron capture equipment exists at Anniston It Is not presently
set up and operating. This will make meeting your proposed schedule of being ready to run PCB analyses by the Tucker method by June 2 unlikely.
Proposed Plan
1. Obtain gross samples of Snow Creek for visual checks to determine presence of discrete, non-aqueous liquid phase in pools or other stream bottom areas.
Completion determined vhen dovnstream limit of discrete, non-aqueous liquid phase has been established.
Start
5/1/69
Complete By 7/1/69
2. Obtain and analyse for PCB, samples of mud and water from Snow Creek at tvo points down stream of limit established In (1).
One of the sampling points will be at the mouth of Snow Creek. Tvo sets of samples taken tvo weeks apart will be used. (Total of 8 samples)
Target Completion 8/1/69
MOWS 097294
-2-
Proposod Plan (Coat'd)
3. Obtain two samples of mud and water from Choccolocco
Craak - ona naar Snow Creak confluence and second 8*10
miles down stream naar Jaekson Shoals. Same frequency
(2) above (Total of 8 samples).
Target Completion 8/1/69
Further action on mud and water samples will be decided after results of 1 thru 3 ere in.
Decision Target 8/13/69
Complete the in-plant survey now underway to Identify and quantify sources of PCB to the sewer.
) Identify all departments utilising or processing Aroclors.
b) Audit Aroclor and HC1 departments (pre viously identified as major sources) to determine source and amount of PCB loss to sewer.
c) R.coM.nd aaana of racovarlng, ellainating, or raduclng loasaa froa aourcii ldantIliad la (b).
<l> Define requirements and rough coat to assure ourselves that lose of Aroclor to Snow Creek (Solid and Liquid Aroclors) la limited to solubility losses.
Establish continuing monitoring systems:
Collated 4/15/69 Target Completion 7/1/69 Targat Coaplatlon 8/1/69 Targat Coaplatlon 10/1/69
) For loss of Liquid (or Solid)Aroclor to Snow Creek (hopefully sero).
Targat 6/1/70
b) For weekly or monthly PCB on our effluent
to Snow Creek (aolubilitv losses).
Define Meeds 9/1/69
e) Establish water sampling station on Choccolocco Creek to monitor PCB and
parathlon.
In Operstloo 6/1/70
7. Investigate means of disposal of Aroclor scrap.
This would need to be a cooperative venture bet* ween Beeearch, Marketing, WGK, Anniston end CED since the problem is not unique to a single Monsanto location and is facing our customers too.
Schedule for 1970/71
MGNS 097295
-3-
That completes the proposed plan. Thar* are a few oChar point* I'd Ilk* to mention though.
1. Tha Anniston Plant is procaading with projacta to raduca tha Aroclor in racovared HG1 - soma of which la sawarad.
a) Tha "catch-tank" In tha HC1 off-gas llna has boon auccaaafully atartad up and la collecting some material.
b) A membrane type coalescer la to be Installed in May to remove organics from tha absorbed HC1.
Aroclor from these two sources will be buried in tha toxic dump.
2. Gross sampling of Snow Creak started the weak of 4/28/69. Snow Creak outfall has been monitored for pH and X HC1 for several years. (Potassium and mercury analyses are no longer run)
3. Preparations are well underway to start tha Aroclor/HCl departmental audits. Actual sampling should start within a week, if tha analyses can be run.
4. Tha only departments using or processing Aroclor* at Anniston are:
a) PaS. - a Therminol system. This is drained to drums whan replacement of Therminol is required. This has been done in this manner since startup.
b) Aroclor
Processing Two Therminol systems Floor cleanings Spills HCl off-gae
No significant amount is lost from tank car cleaning since any material (including heels) is drained into drums, cleaning cloths are put in trash containers. Both drums of liquid and rags are sent to the dump.
5. Present estimate of PCB analysis time indicates 2 to 3 man-hours are required per sample. This may wall limit us to two to thrsa samples par day.
6. Present guess on future monitoring Is that wa would need to add one man to tha laboratory staff and buy an Instrument (at about $10,000) to support an adequate program.
7. An audit of the Parathlon and PNP Departments will be carried out thi* summer in addition to the proposed program. This work 1* urgently needed to establish how close we ere now approaching the ultimate capacity of the biological treatment plant and whether or not reduction through an in-plant control program is feasible. Answers ere required
HONS 097296
-4Polnta (Coat'd)
urgently because they determine the course of action of the sulfur recovery system proposed for Parsthlon as wall as tha ultimata production capacity of tha Parathlon Plant. While Parsthlon belongs to tha Ag Division tha biological treatment plant belongs to tha Organic Division. I hope this suary will serve your present needs. Many thanks for tha suggestions in your 4/28 nemo. As you can sea many found their way into our program proposal.