Document MMnxDZeBjQv15XzpQqDrMvo69

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION 5 77 WEST JACKSON BOULEVARD CHICAGO, ILLINOIS 60604 SUBJECT: FROM: THRU: TO: CLEAN AIR ACT INSPECTION REPORT Gallagher-Kaiser, Detroit, MI Daniel Schaufelberger, Environmental Scientist AECAB (MI/WI) Sarah Marshall, Section Supervisor AECAB (MI/WI) File BASIC INFORMATION Facility Name: Gallagher-Kaiser Facility Location: 13710 MT Elliott Avenue, Detroit, MI 48212 Date of Inspection: 8/8/2022 EPA Inspector(s): 1. Daniel Schaufelberger, Environmental Scientist 2. Valeria Apolinario, Environmental Engineer Other Attendees: 1. Brad Hite, Manufacturing Manager 2. Pat Shaw, Safety Supervisor 3. Katie Koster, EGLE Contact Email Address: jlorentzen@gkcorp.com Purpose of Inspection: Determine compliance with the Clean Air Act. Facility Type: Construct Industrial Paint Finishing Systems Regulations Central to Inspection: Michigan State Implementation Plan Arrival Time: 2:50 PM Eastern Departure Time: 4:00 PM Eastern Page 1 of 4 Inspection Type: Unannounced Inspection Announced Inspection OPENING CONFERENCE Presented Credentials Stated authority and purpose of inspection Small Business Resource Information Sheet not provided. Reason: Not a small business Provided CBI warning to facility The following information was obtained verbally from Brad Hite or Pat Shaw unless otherwise noted. Process Description: The Gallagher-Kaiser, Detroit, Michigan facility fabricates industrial paint finishing systems from various materials, including sheet metal. Two lasers, used for cutting sheet metal, and line welding operations, are used in the construction process. A paint booth, at the facility, is used to coat parts. The paint is applied primarily with sprayers; but also, to a more limited extent, by roller or brush. Air and particulate from the paint booth is drawn through a filter system before exiting to the atmosphere. Staff Interview: The Gallagher-Kaiser facility currently has approximately 168 employees and operates two shifts per day at two plants; Plant A and Plant B. All of the paint used at the facility's paint booth is water-based. Painting is only conducted at Plant A. The coating operation typically operates 10 hours per day; 5 days per week. The particulate filters at the booth are changed when the differential pressure at the fan reaches a specified value. This occurs, typically, once every one to two months. No coatings are mixed on site. Two 16.7 MMBtu/hr natural gas fired boilers operate at the facility. Only one boiler operates at a time. TOUR INFORMATION EPA Tour of the Facility: Yes Data Collected and Observations: The facility tour was led by Brad Hite and Pat Shaw. The tour began by viewing the operations at the pre-fab department. The inspectors viewed the two lasers. The first laser was viewed in the process of cutting sheet metal. The tour continued to view the two Cleaver-Brooks boilers and a partially fabricated oven section. The tour concluded at the paint booth area where buckets of paint and the filter system were viewed. EPA/EGLE reviewed safety data sheets for the coatings used at the paint booth. Photos and/or Videos: were taken during the inspection. Field Measurements: were not taken during this inspection. Page 2 of 4 CLOSING CONFERENCE Provided U.S. EPA point of contact to the facility DIGITAL SIGNATURES DANIEL Digitally signed by DANIEL SCHAUFELBERGE Date: 2022.09.21 10:30:51 SCHAUFELBERGER R -05'00' Report Author: _________________________________ Section Supervisor: SARAH Digitally signed by SARAH MARSHALL __M_A__R_S__H_A_L__L__1_6:_19_:1_7 _-0_5'0_0'_____________ Date: 2022.09.21 Page 3 of 4 Facility Name: Gallagher Kaiser Facility Location: 13710 MT Elliott Avenue, Detroit, MI 48212 Date of Inspection: August 8, 2022 APPENDICES AND ATTACHMENTS Appendix A: Digital Image Log Page 4 of 4 Facility Name: Gallagher Kaiser Facility Location: 13710 MT Elliott Avenue, Detroit, MI 48212 Date of Inspection: August 8, 2022 APPENDIX A: DIGITAL IMAGE LOG 1. Inspector Name: Valeria Apolinario 2. Archival Record Location: EPA Region 5 Electronic Records Center Image Number 1 2 File Name IMG_0167.JPG IMG_0168.JPG Date and Time (incl. Time zone and DST) 8/8/2022 3:38 PM EST 8/8/2022 3:38 PM EST Description of Image Boiler 1 Information Boiler 2 Information Page 1 of 1