Document MMnxDZeBjQv15XzpQqDrMvo69
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION 5
77 WEST JACKSON BOULEVARD CHICAGO, ILLINOIS 60604
SUBJECT: FROM: THRU: TO:
CLEAN AIR ACT INSPECTION REPORT Gallagher-Kaiser, Detroit, MI
Daniel Schaufelberger, Environmental Scientist AECAB (MI/WI)
Sarah Marshall, Section Supervisor AECAB (MI/WI)
File
BASIC INFORMATION Facility Name: Gallagher-Kaiser
Facility Location: 13710 MT Elliott Avenue, Detroit, MI 48212
Date of Inspection: 8/8/2022
EPA Inspector(s): 1. Daniel Schaufelberger, Environmental Scientist 2. Valeria Apolinario, Environmental Engineer
Other Attendees: 1. Brad Hite, Manufacturing Manager 2. Pat Shaw, Safety Supervisor 3. Katie Koster, EGLE
Contact Email Address: jlorentzen@gkcorp.com
Purpose of Inspection: Determine compliance with the Clean Air Act.
Facility Type: Construct Industrial Paint Finishing Systems
Regulations Central to Inspection: Michigan State Implementation Plan
Arrival Time: 2:50 PM Eastern Departure Time: 4:00 PM Eastern
Page 1 of 4
Inspection Type: Unannounced Inspection Announced Inspection
OPENING CONFERENCE
Presented Credentials Stated authority and purpose of inspection Small Business Resource Information Sheet not provided. Reason: Not a small business Provided CBI warning to facility
The following information was obtained verbally from Brad Hite or Pat Shaw unless otherwise noted.
Process Description: The Gallagher-Kaiser, Detroit, Michigan facility fabricates industrial paint finishing systems from various materials, including sheet metal. Two lasers, used for cutting sheet metal, and line welding operations, are used in the construction process. A paint booth, at the facility, is used to coat parts. The paint is applied primarily with sprayers; but also, to a more limited extent, by roller or brush. Air and particulate from the paint booth is drawn through a filter system before exiting to the atmosphere.
Staff Interview: The Gallagher-Kaiser facility currently has approximately 168 employees and operates two shifts per day at two plants; Plant A and Plant B. All of the paint used at the facility's paint booth is water-based. Painting is only conducted at Plant A. The coating operation typically operates 10 hours per day; 5 days per week. The particulate filters at the booth are changed when the differential pressure at the fan reaches a specified value. This occurs, typically, once every one to two months. No coatings are mixed on site.
Two 16.7 MMBtu/hr natural gas fired boilers operate at the facility. Only one boiler operates at a time.
TOUR INFORMATION
EPA Tour of the Facility: Yes
Data Collected and Observations: The facility tour was led by Brad Hite and Pat Shaw. The tour began by viewing the operations at the pre-fab department. The inspectors viewed the two lasers. The first laser was viewed in the process of cutting sheet metal. The tour continued to view the two Cleaver-Brooks boilers and a partially fabricated oven section. The tour concluded at the paint booth area where buckets of paint and the filter system were viewed. EPA/EGLE reviewed safety data sheets for the coatings used at the paint booth.
Photos and/or Videos: were taken during the inspection.
Field Measurements: were not taken during this inspection.
Page 2 of 4
CLOSING CONFERENCE Provided U.S. EPA point of contact to the facility
DIGITAL SIGNATURES
DANIEL
Digitally signed by DANIEL
SCHAUFELBERGE Date: 2022.09.21 10:30:51 SCHAUFELBERGER
R
-05'00'
Report Author: _________________________________
Section Supervisor:
SARAH
Digitally signed by SARAH MARSHALL
__M_A__R_S__H_A_L__L__1_6:_19_:1_7 _-0_5'0_0'_____________ Date: 2022.09.21
Page 3 of 4
Facility Name: Gallagher Kaiser Facility Location: 13710 MT Elliott Avenue, Detroit, MI 48212 Date of Inspection: August 8, 2022 APPENDICES AND ATTACHMENTS Appendix A: Digital Image Log
Page 4 of 4
Facility Name: Gallagher Kaiser Facility Location: 13710 MT Elliott Avenue, Detroit, MI 48212 Date of Inspection: August 8, 2022
APPENDIX A: DIGITAL IMAGE LOG 1. Inspector Name: Valeria Apolinario
2. Archival Record Location: EPA Region 5 Electronic Records Center
Image Number
1
2
File Name
IMG_0167.JPG IMG_0168.JPG
Date and Time (incl. Time zone and DST) 8/8/2022 3:38 PM EST 8/8/2022 3:38 PM EST
Description of Image
Boiler 1 Information Boiler 2 Information
Page 1 of 1