Document MJvzd0gN1J4zBMR1eoeG7NaRM
Inter Office
Body end Electrical Product Engineering
May 8, 1980
To: cc:
From Subject:
J. V. Durstix
H. P. Freers W. C, Tyner
J. A. Fflug
Carcinogens Task Force Report to E St R apd M & S Subcommittees
We bare reviewed the subject report and are in general agreement with its
contents except for the recommended strategy timetable. BEFE cannot agree
to eliminate asbestos, selected chromium compounds and benzene by Job #1,
1935> Such a commitment has far reaching headcount end expenditure
,
ramifications. For example, ve have estimated that 7*5 man years and over
$200K would be required to Investigate, test and approve asbestos substitutes
in sealers and adhesives. There ere na known suitable substitutes for the
chromates used in primer paints end the timetable end expenditures required
to develop substitutes cannot be quantified at this time. In vaaw of the
current budget limitations we may be unable to comply with CEPL 0 which
puts forth a goal of eliminating asbestos in newly designed components while
avoiding the commitment to a strict timetahle. We do agree that where
elimination cannot be contained, design, process and exposure controls must
continue*
It should be noted that BEFE did not participate in the classification of asbestos materials into the A, B and C groups shown on page $. Most of our sealer end adhesive applications require considerable development and long term test programs before suitable substitutes can he identified.
Also, the words "was tedious and inexact" in the first sentence on page 8 should be deleted.