Document MGew9Ry3oo6LYmbVkm8VQZZwy
Georgia-fecific
intracompany memo
to Mr. K. W. Brown from G. W. Green subject Asbestos Dust Survey
^
location location date
Acme Tigard April 22, 1976
Oa January 21, 1976 the Acme, Texas Joint Cement Plant was monitored for airborne asbestos dust by George Fowler.
The counting was done at Tigard by Dawn Steyaert under my supervision. All persons were well under the current limit of five fibers per milllleter, and also well below the limit of two fibers which is now to become effective in January, 1977. The overall plant average is 0.63 fibers, which compares to 1.04 on the June, 1975 count.
A summary of the data is attached.
GWG/gvp Att. cc: Mr. J. R. Hurd - Portland
Mr. T. W. Richards - Tigard Mr. G. F. Fowler - Marietta
G. W. G.
SGP 0019642
GP 09