Rev. 8/77 CAPITAL PROJECT SCHEDULE Project Name and Number: OC 3007 Lead Dust Ventilation and Material Handling Renovation EP 20 Approximate Cost: $275,137 Location: Chicago Date of Issue: 4/10/78 Supersedes: 10/1/77 Issued By: F. B. Dorf Description (in c l u d in g a p p r o x ima t e c a p a c it y ): Reduce airborne lead dust by improved material handling and ventilation in Chicago plant. Objective (in c l u d in g e c o n o mic s ): Redesign and upgrade facilities to meet OSHA require ments for airborne dust abatement. Distribution: M,, D. Cover W. A. Fead G. A. Forlenza H. C. Gaffney H. H. Hofmaier G. R. Koehler F. C. Schmelz H. G. Thompson R. L. von Glahn B. G. Witherspoon Special Considerations: EPA is setting a standard for lead in the atmosphere. Plans are made to measure lead emitted from the plant vents and stacks after completion to determine if any hygiene problems are posed to the surrounding neighborhood. Checkpoints Overrun Mechanical Completion Close Out Job Responsibility Strategy Board Gaffney Gaffney Dates: Start End 9/8/77 6/1/78 Remarks: Additional funds of $59,000 approved for more extensive renovation of old dust collectors and doubling the size of the stack sampling study - 0C 3007-R1. Compliance schedule with OSHA. 6/30/78 kmc/P 171 This schedule represents available information and judgment estimates at the time issuance. For changes or corrections, notify the issuer (or F. C. Schmelz BB X3777 or W. A. Fead BB X2775).