Document M4RdLeDJBNpqpJkNKwEK3xqRV
Anniston
C. K. Eastman
A. J. Koenig J. C. Landwehr ~
Ar-ts-iaiayG. W. Miller
U, 0
U. E. Papageorge
W. F. Taffee
H. L. Williams
General Offices
U. C. Carder D. E. Cayard D. Danna (5) H. 0. Hehner F. Bt Hodges D. B. Hosraer (2) W. A, Kuhn C. F. Luecke T. M. Patrick H. L. Payton N. L. Sample J, E, Smith R. J. Stratmeyer H. S. Trail
COMPANY CONFIDENTIAL
11 e
Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Summary
October, 1968
Cost Improvement Results For First Ten Months
Estimated Actual
Target
% of Target
Month
$ 18,640
$ 40,500
46
YTD
$364,910
$415,935
88
Organic Division
!
South Second St.
Solid Aroclor yield increase project J015 and Santowax R column project 5OI6 sent to St. Louis for approval. Prior verbal approval was given on long term delivery items. These projects are needed to meet 1969 Solid Aroclor pro-* duction forecast.
Preliminary scope definition started with CED on the Solid Aroclor expansion.
Market testing to start on new blended Solid Aroclor 4465 Savings $12 M/yr. with zero NFC.
Other Locations D. W. Jackson - WGK
Work on upgrading No. 1 Biohenvl Tubular Unit started in field. Shutdown expected in November to tie-in piping and equipment.
Purification of biphenyl hydrogen for HB-40 via mixed bed adsorption continues to show good potential in pilot run. Now determining optimum conditions for maximum recovery efficiency.
Preliminary Project Scope Report on chlorine bulk handling including flow diagrams and plot plans received from CED on 10/4. Scope was reviewed and returned with plant comments on 10/18.
0346311
In toe 3' |
`
CONFIDENTIAL INFORMATION
;
"Tht* document COfdelni confidential Intormetion which li the property of Memento Compeny. Only there portions of' the document retevent to e
duly euthortied IndlvJducl't need to know may be excerpted for hlmi The report mutt not be eent outride the Compeny without written epprevel end
the evtfcorited recipient I* eeceuntebl* for It* refe keeping, excerpting or otherwlte diiclotlng of ite content* end for It* proper dlsporet. The decu-
merit remelnt the property of Montetfo Compeny end jhall be returned within tiro month* to ;lt*-eofhor, except upon epoclet euthorlieflon to hold for e longer period."
TOWOLDMONOQ44407
Company Confidential 2.
Organic Division (Continued) Evaluation for production of Staley Grade Acid complete. An AFE was forwarded in October for $6,000 capital to pretreat before carbon towers so that organic loading to towers is in 200 ppm range they are designed for.
Agricultural Division Farathion fume collection system successfully started up and is now operating at design conditions. Project has been accepted by production. Rental centrifuge for pilot sulfur recovery unit has been returned to Bird Machine Company. Progress report summarizing conditions for sulfur recovery as determined in pilot plant studies was issued. PR&P has scheduled report on recommended process for purification of recovered sulfur in December.
Design and Drafting Major effort was expended in October to expedite design and drafting for Santowax Still project.
Utilities Cost Improvement Savings of $10 to $20,000 per year appear possible in power factor improvement and central compressed air system.
CEP Liaison New warehouse occupied in raid-October. Flaking and bagging equipment targeted for mid-November.
Personnel Alan G. McCarty was transferred from the Agricultural Division and promoted to Engineering Supervisor responsible for Parathion, PNP, p>Sc, HC1 and Chlorine to succeed Don Malm. Alan has extensive experience in Parathion and Pgs5 through startups, production supervision, and production planning.
Jw
0346312
TOWOLDMONOQ44408
PN P NIRAN
AROCLOR BIPHENYL
HB-40 | HCL
:hlorine
TOWOLDMONOQ44409
TOWOLDMONOQ44410
AROCLOR
E. E. Bowles, C. R. Mcllwain, (V. R. Haupt)
Company Confidential 3.
Cost Improvement
Month
YTD
Target $4900
$47,400
Actual $4085
' $52,465
Evaluate QuaterphenylPolyphenyl Effects on Solid Aroclor Yields
1969 Savings - $63>200 NFC - $14,000
TSD Objective B-8 (a)
Instrumentation for Solid Aroclor yield increase, ordered on verbal approval, to be shipped 11/1/68. Project 3015 mailed to St. Louis 10/31/68 for approval. Application for Alabama Department of Public Health special license to be made in early November.
Expand Solid Aroclor Department1969
TSD Objective
CED preliminary scope reviewed by Anniston personnel and counter proposal sub mitted. Savings favor using one large line of equipment rather than two half size disimilar units.
Therminol System
Evaluation
TSD Job 863
Results from the first computer simulation of the existing Therminol system were useful in efforts to eliminate unnecessary flow to individual users. Three tem perature control loops were not functioning properly. An effort is being made to repair these control loops.
Further study is planned to determine the best route for system improvement.
Solid Aroclor 4465 by Blending
Savings $12,000 NFC zero
TSD Objective 1969
Laboratory samples made by G. L. Arnett sent to St. Louis for market testing. Blending of solid and liquid Aroclors to make 4465 has passed all property specs and tests. Savings comes from a 4.6% capacity gain in Solid Aroclor manufacture.
0346315
TOWOLDMONOQ44411
BIPHENYL-SANTOWAX
W. G. Niemeyer, (V. R. Haupt)
Cost Improvement
Month
YTD
Target
$3,335
$36,820
Actual
$6,630
$100,130
Company Confidential 4.
Debottleneck Bihenyl
Capacity
TSD Objective
Stills to 87.6 M lbs/vr.IncreaseB-7 (a)
CED is working on drawings for changes in the distillation area.
No. 1 Furnace Upgrade
Capacity
Liaison (CEA-1892)__________________ Increase
TSD Objective _____ B-7 (c)
Concrete foundation and dike wall for new benzene storage tank is nearly completed. Preheaters have been set. Structural steel set at preheaters. Coke traps have been set and installation of external alloy piping is in progress.
Biphenyl-Santowax MIPB-l (a)
TSD Objective
Rough drafts of all sections are complete. Completion of review and revisions will be delayed until December '68 due to full attention as CEA 1892 manufacturing representative, HB-40 hydrogen cleanup, and Santowax R still improvements.
Santowax R
Quality
TSD Objective
Distillation ColumnB-7 (d)
This project will be installed in two phases:
Phase I.
Install column and new Montar 9 pump with manual controls.
Phase II.
Add instrumentation to control the new column.
TSD is preparing a design package for Maintenance on Phase I. Package to be issued by 11/8/68.
Electrical and instrumentation drawings for Phase II are nearly complete. Phase II will be Installed when CED ties in their new Santowax C surge tank and pump. EDC of Phase II is February, 1969.
This project J016 was sent to St. Louis for approval. Verbal approval had been given to order long term items.
0346316
towoldmonoo444T2
HB-40
C. E. Woodward (V. R. Haupt)
J, L. Brown
(G. W. Miller)
Company Confidential 5.
Alternate Hydrogen
Evaluation
TSD Objective
Supply
1969__________________________________________________________________________________
Progress report issued detailing various routes to supply hydrogen to HB-40 when the Chlorine department is shutdown. Received bid from Chemical Design Company on their package unit for cleanup of hydrogen using silica gel and mole cular sieves. Details are being discussed with Chemical Design Company. CED will take over the project installation with the expected EDC of 1 May 1969. The Chlorine department will be kept running until this time.
CHLORINE
D. W. Dudley (D. C. Malm)
Cost Improvement
Month
YTD
Target
$2,600
$38,600
Actual
$ 475
$57,380
Reduce Mercury Usage to
Savings $1700
0.75 lbs, Hg/ton Cl?
___________________ ,B-6 (b)
TSD Objective
Installation of acid wash tank for recovering mercury from "butter" underway. Expected date of completion is end of November.
Brine Dechlorination
Savings $6,875
TSD Objective
B-6 (c.)
No change in status. Awaiting maintenance revisions to complete demonstration.
Central Chlorine Unloading
Project Scope Development
TSD Job 860 ______ _
Official notification of delay (until May 1969) in chlorine plant shutdown received from Director of Manufacturing on 10/22. Preliminary scope issued by CED on 10/4 was reviewed and returned on 10/18. Project now to include Niran Chlorine handling facilities as well as hydrogen clean-up.
034631?
TOWOLDMONOQ44413
HC1 J. H. Jones (D. C. Malm)
Cost Improvement
Month
Target
$1830
Actual
$ 400
YTD $6080 ' $2500
Company Confidential 6.
Production of Staley
Increased Sales
Grade Acid & Savings $6.000B-10 (c)
TSD Objective
Final evaluation complete. AFE to install coalescer to enable Staley Grade acid production will be submitted by 11-7, Progress report published by 11-15.
Muriatic Acid Storage______________ Savings $6750
TSD Job 497
Construction of tank foundation in progress. Bids have been received from rubber liners for construction of tank. Project awaiting letting of contract.
PNP 0. J. Norris, J. M. Jones (D. C. Malm)
Actual
Month $2500
0
YTD $114,000 $ 55,100
Comment
Unable to demonstrate mole ratio reduction because of letdown problems.
20 M #/yr.
Savings $99,000
TSD Objective B-9 (a)
Demonstration complete. Production rate since July has been at a 20 M #/yr. rate or better. Debottlenecking efforts will be continued to meet revised Niran requirements of 1.97 M #/mo.
Preliminary estimate for pre-heating and pressurizing charge tank complete. Project premise will be issued 11/6 with AFE by ll/lj. Expected rate gain is 0.8 M lbs/yr.
03^6318
TOWOLDMONOQ44414
PNP (Continued)
Company Confidential 7.
Increase Reactor Temperature
Capacity
TSD Objective
IncreaseB-9 (b)
Reaction time back down to 68 minutes as optimization work on reactor cycle time continues. A KTA analysis on reactor depressurization problem is continuing in an effort to define the variable which causes letdown to take more than 3O minutes.
Study of Molar
EVOP
TSD Objective
Ratio NAQH/PNCBB-9 (c)
Studies temporarily halted due to major work effort on increasing production rate. These studies are expected to be resumed by mid-November.
Revise MIP
TSD Objective
__________________________________________________________________________________ B-l (g)
Rough draft typing completed and being circulated for comments. Plant review target date is now 11/15, Final draft typing scheduled to be completed by 11/25 and review with TPM in early December.
NIRAN
K. J. Hale, D. W. Dudley (D. C. Malm)
Cost Improvement
Month
YTD
Target $19,365
$156,765
Actual $ 6,700
$108,850
Demonstrate Parathion Recovery
Savings $70,000 and 10-15% Reduced COD Loading
TSD Objective B-5 fa)
Demonstration has been delayed due to failure of original filters to effectively remove solids in feed to coalescer. Excess pressure drop has resulted. Life studies of alternate paper filters indicate they are uneconomical in this appli cation. The total project is being re-evaluated to determine the best course of action to achieve the claimed savings. A progress report summing work to date and recommended actions will be published in early December.
Solvent Addition
Savings $59,000
TSD Objective
______________________________________________________ B-5 (a)
Yield savings of $6700 were obtained in October. Savings are down compared with the four month period of May thru August reflecting a cut-back in Chlorine chargee in early September.
0346319
TOWOLDMONOQ44415
NIRAN (Continued
Company Confidential 8.
Sulfur Recovery from Residue
$400,000/yr. Savings, yi% Reduction in S0r in Air
TSD Objective B-5 (d)
Rental Centrifuge from pilot recovery tests has been decontaminated, cleaned and
returned to Bird Machine Company. A progress report detailing pilot test results
is in typing. Preliminary work necessary for project transmittal to CED is under
way.
PR&D work on final sulfur clean-up was continued. Results still indicate high probability of meeting desired specifications. Tentative process is expected out by mid-December,
Submerged Pump for
Savings $1,500
TSD Objective
RI Control of
B-5 (c)
Chlorination_____________________________________________________________________________
New light source arrived on schedule. Start-up delayed when monel circulating line was "pirated" to repair #1 chlorinator sample line. New target date to begin based on delivery of monel pipe is 11/15.
Thio Acid Reactor
Safety
TSD Objective
Temperature Controlled
A-10
Alcohol Addition________________________________________________________________________
No change.
Fume Collection System
Reduce Corrosive
in Parathion Department__________Atmosphere
TSD Objective F-10
Fume collection system now running at design condition. Old incinerator stack fan failed and will be replaced on project. This will allow the extra capacity required for future addition to the system. A wrap up report is scheduled for mid-November.
ENGINEERING DESIGN AND SERVICES
Mechanical/Electrical/Instrument Design and Drafting
J. C. Price. J. A. Veazev. R. L, Brewer, J. K. Rennie. (W. F. Taffee)
Highlights
Major effort in October was on Santowax distillation project with goal of meeting 12/15 deadline for installation of Phase I. November emphasis will be on Solid Aroclor instrumentation to allow improved cycles in chlorination and stills.
AFE approved covering diversion of acidic spring water to process sewer. Design complete, drafting schedule for late November.
0346320
TOWOLDMONOQ44416
ENGINEERING DESIGN AND SERVICES (Continued)
Company Confidential 9.
Design Responsibility in Disaster Control Plan
Safety
TSD Objective . A-7
Awaiting information from radio supplier on recommended frequency allocations be
fore writing specifications .
'
UTILITIES COST IMPROVEMENT
J. C. Price, L. 0. Chambers (W. F. Taffee)
Progress report on program plans was forwarded for typing and issue. Project premise to change cooling water on Trane compressor at Niran to Tower Water was approved and the AFE has been forwarded for typing and approval. Project premises for use of well water at Niran Jets (net savings $6000/yr. - NFC $15000) and Improved Treatment at Biphenyl Cooling Tower (net savings $6700/yr. NFC $2500) were forwarded for approval. Progress reports covering evaluation of a plant central compressed air system (estimated gross savings$8000-$l6,000/ yr.) and plant power factor improvement (estimated gross savings $2000-$6000/yr.) will be issued in late November or early December.
PLANT IMPROVEMENT
G. C. Goodwin (W. F. Taffee)
1968 road program AFE`s have been completed. Design package for Parkwin Street from 5th to 6th Street was forwarded to Maintenance.
Work on preparation of 1969 plant improvement program is proceeding on schedule.
ASSIST OPERATIONS ON START-UP
V. T. Langdon (W. F. Taffee)
CEA 1450 - Aroclor Expansion
Flaking and bagging equipment being installed with mid-November target for completion. Temporary drumming facilities to be installed early in November.
CEA 1452 - Warehouse
Warehouse occupied in mid-October. Only minor corrections have been required.
POLLUTION CONTROL
E. G. Wright (W. F. Taffee)
Reporting Spills and
Pollution Abatement
TSD Objective
other Non-Routine Operating
F-4
Conditions in the Plant^________________________________________________________________
14 air emission reports were filed by plant personnel. 6 were attributed to the unusually high amount of smoke from the P^S^ reactor and the other 8 were SO2 complaints.
03463^1
TOWOLDMONOQ44417
POLLUTION CONTROL (Continued)
Company Confidential 10.
Provide Catch Basin
Pollution Abatement
for Niran Spills_____________________ _________________
TSD Job 759
Project No. 2944 to provide a catch basin at the P^S^ track was transmitted to Maintenance on 10/2J/68.
Special Activities
1. Received and investigated one air pollution complaint noted odor of P in area where complainant lives.
2. On 4 trips to Coosa River everything was O.K.
3. Obsolete equipment at the Waste Treatment Plant has been dismantled. This has greatly enhanced the appearance of the area.
4. Contacted Drs. Gunning and Suttkus concerning another biological study of Choccolocco Creek. Study will be conducted in early 1969.
Waste Treatment
All wastes were effectively treated in October. The Niran turn-around began an October 27, and some necessary repairs are being made at Waste Treatment. The limestone neutralization pit is being relined. The valves with which the hold tanks can be segregated are also being replaced. Being able to segregate the tanks will make it possible to install vertical agitation in the north hold tank which will increase surge capacity.
Average values for Monsanto to city treatment plant effluent in October are as follows:
Average Daily
Specifications
PNP 1.0 <T5 ppm
COD 66 <^200 ppm
Parathion
.09
*^1 ppm
BOD 6.0 <dj?0 ppm
03463^2
TOWOLDMONOQ44418
PROCESS AND QUALITY ANALYSIS
W. B. Dunlap
Company Confidential 11.
PS Parathion Correlation Study$50,000 Savings
Potential
TSD Job 827
A study of PpSc batch sheets, control charts and cost sheet6 revealed that long term correlation of viscosity and X P is uncertain. Viscosity serves well as a relative day-to-day control of the reactor. Product composition shows considerable variability which must be stabilized before optimization studies are started.
Identification of Parathion Variables$17,000 Savings
Potential
TSD Job 828
The assay of crude chlorinated thio acid was reviewed to determine total vari ability, and to define the components of variability. Total random error was excessive. A study was outlined to measure the effects of the various components to make possible better control.
03Ab323
TOWOLDMONOQ44419
PLANT LABORATORIES
Company Confidential 12.
PROCESS RESEARCH AND DEVELOPMENT
Solid Aroclor
G. L. Arnett, (G. W. Miller)
1. All data requested by the marketing department as a prerequisite for producing Aroclor 4465 by the new process has been developed. No test differences were observed in the material produced by blending when compared with regular production material.
2. Several possible alternate catalysts for the production of Aroclor 5460 are under investigation. The purpose of the investigation is to reduce the color of the finished product. Initial tests show aluminum produces Aroclor 5460 with color slightly better than that produced with iron. Success in this project will solve the major solid Aroclor marketing problem with minor additional manufacturing cost.
Blnhenvl Hydrogen Clean-Up - HB-40
J. L. Brown, (G. W. Miller)
1. The heatless solid bed adsorption pilot unit continues to satisfactorily purify Biphenyl hydrogen giving a product stream containing less than 50 ppm CO and no detectable amount of organics. Hydrogen recoveries are averaging in excess of 70%. All PR&D test work will be completed
11/8/68.
2. Biphenyl hydrogen purified with CD test unit produces HB-40 in a reaction time 8-10 minutes shorter than required when using DeNora hydrogen. These lab autoclave studies also consistently show that superior HB-40 color is associated with the use of purified hydrogen.
3. To finalize design considerations, a series of tests were performed to evaluate the threshold effect level of CO on the hydrogenation. At or below 50 ppm CO, no effect on cycle time can be observed; however, at 100 ppm CO definite catalyst deactivation caused by CO is observed.
Sulfur Recovery
W. H. Howard, I. Ransaw, (G. W. Miller)
1. Process step optimization studies are progressing on schedule to be completed 12/20/68. Major delays were caused by design and fabrication of equipment suitable for the laboratory investigations.
2. The initial sulfur wash has been Improved by using a slightly alkaline wash. Optimum conditions are defined pending analytical results.
3. The process under development will consist of four steps: (1) Wash; (2) Hydrolysis possibly under pressure at 130-140C; (3) Steam sparge; (4) Filtration and drying.
TOWOLDMONOQ44420
Company Confidential 13-
ANALYTICAL AND QUALITY CONTROL
Aroclor
1. Plant personnel along with R. H. Munch, Organic Research Department, met with Messrs. R. H. Dewart and R. L. Bougreau in St. Louis October 17 to discuss analytical procedures for testing electrical Aroclors. The new analytical procedures developed by Dr. Munch were discussed along with our presently used techniques. As a result of this meeting a blind round robin test of Aroclor quality was begun to investigate method and laboratory precision. The results of this test will be published in , November.
2. Only minor quality problems have been associated with the Aroclor tank farm start-up. An initial build-up of white particles in the Aroclor was identified as a silicone glue leaching from the cartridge filters. This problem has been resolved and the material was purified by a simple cloth filtration. Initial quality from the system is excellent.
Solid Aroclor
1. Inclusion of large pieces of extremely dark Aroclor 5460 due to the poor condition of the flaker continues to be a problem. A customer reaction report has been received from Precision Cast Parts Corporation complaining about the problem. A formal quality complaint is expected.
Parathion
Analytical work load was low during October due to the fall change over to ethyl parathion production.
Complaint Report
Quality No.
Material
Customer
Reason
Justified
7-A-68
Aroclor 1262 10% Toluene
Amsco
High Sp. Gr.
Yes
YTD quality complaints/100 Shipments 0,10 : Target 0.20
Service
YTD service complaints/100 Shipments 0,16 ; Target 0.20
Cost and Operational Indices
Seotember 1968 YTD Average
forget
(1) Analytical Samples (2) Analytical Manhours (3) Manhour/Sample (4) $1 Manhour (5) i Total Plant Cost
(6) Overtime %
4433 1856 0.42 7.80 0.88 5.70
4736 2022 0.40 8.66 1.07 4.60
0.40 8.50 1.50 5.00
0346323
TOWOLDMONOQ44421
Company Confidential 14.
COMMUNITY RELATIONS. PERSONNEL. RECRUITING. AND DEVELOPMENT
Personnel 1. D. C. Malm promoted to Superintendent of Engineering Services and Plant Hide
Engineering at the J. F. Queeny Plant. 2. J. T. Bell accepted an offer as Senior Process Chemist starting December 1. 3. C. E. Woodward transferred to Chocolate Bayou to work in TSD in the Pthalic
Anhydride area. 4. Process Engineer Ken Buturla transferred to Kenilworth, New Jersey Plant of
Plastic Products and Resins Division. Development 1. College level, non-credit, "Process Dynamics and Control" being taught from
Auburn University campus by Dr. Z. L. Taylor via Victor Electrowriter and Telelecture system. Course with enrollment of nineteen technical personnel started October 1 and will meet twice a week until mid December. 2. The first department meeting in preparation for the 1969 objective setting and review of 1968 objectives was on October 11. Visitors 1. R. C. Herman, CED Project Manager, Warehouse (CEA 1452) visited the plant October 17. 2. Dr. J. R. Fair spoke to a group of fifteen technical personnel on the subject of "Continuing Education Trends", on October 16. 3. Dan Woods and Bill Corlew from W.G.K. visited for PNP review Tuesday, October 29. 4. D. J. Schulz and J. Mazzocchlo, CED, visited October 30 to November 1 to discuss details on Biphenyl distillation on CEA 1892. 5. W. E. Chandler from General Offices visited concerning utilities Improvement projects and plant improvement topics.
03A6326
TOWOLDMONOQ44422
' DISTRIBUTION OF TIME BY TECHNICAL SERVICE Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec.
PROCESS IMPROVEMENT
NEW PRODUCTS
PUNT IMPROVEMENT
ASSIST OPERATIONS
SPECIAL ENGINEERING SERVICES
TECHNICAL MANPOWER
MISCELUNEOUS ACTIVITIES
AMD ABSENCES
tt--r--r ixztzxzt
Jan. Feb. March-Apr. Kay June July Aug. Sept. Oct. Nov. Dec. S . 03A6321
TOWOLDMONOQ44423
IN MAINTENANCE
FOR CONSTRUCTION
600 J____ 500 .... .....
A.
k400 /i
500" '1 200 ..... 1
x|V
i
TSD PROJECT SUMMARY
jmi
i i
``uumb.k
r1....
'|
1
j| *
1
11 X1
"~4 i
..... i
IN MAINTENANCE COMPLETED
NOT CLOSED
PROJECTS SUBMITTED
FOR APPROVAL
APPROVED PROJECTS ' IN TSD
i i... i ii |
i1 i1 i
i\r 111
1 r~ 1i .1 i 1
j 1 1 ___ J____ --]-- .J
"i-- 1
|i
ii || ii 1____ if
1I
11
JZZL X
_ji:
0340328
.-J
Dec. Jan. Feb, Mar. Apr. May June July Aug. Sept.Oct. Nov. Dec. Jnn.
i i
TOWOLDMONOQ44424
60
ANALYTICAL SAMPLES
56 52 A8 AA AO
2A00
2300
2200
analytical
MANPOWER
2100 2000
1900 1800 1700
0.6
Manpower/sample 0.A
0.2
11.00 10.00
$/Manhours
9.00 8.00
y.ool
% Total Plant Operating Cost
Overtime "A
1