PHASE II - PLANNING SCOPE & COST ESTIMATES
Completion: Earliest completion 7/1/71 Latest completion 10/1/71
Status on 10/14/71
Phase II
1. Water Reduction 800 gpm to 200 gpm Reduction to 550 gpm has been accomplished.
a. New fume scrubbers-packed bed instead of drowning jet
b. Recycle vacuum jet water with surface condensers rather than direct contact condensers
c. Re-use water for direct contact require ments
d. Carbon disposal improvements and repair acid sewer
e. Re-route sewer
2. Cleanup Potential Waste Streams
a. Improved off-gas knockout tank
b. Improved liquid-liquid coalescer separator
3. Spill Containment a. Process drips collection
_
b. Curbs and pads for containing potential spills
4. Complete Upgrading of Limestone Pits
Capital Expense.
$280,000
Completed Aug. 1971
Indefinitely deferred. This water is a negli gible source of PCB.
Indefinitely deferred. Direct contact require ments have been elimin ated.
Project under design; target completion Dec. 1971.
Project in premise and evaluation stage -- potentially cost not consistent with benefit.
$21,000
Completed January 1971
Indefinitely deferred Not needed with improved knockout tank above.
$53,900
Completed, but training and emphasis continues.
Completed September 1970
$80,000
Completed August 1971