Document LgQR4vDL4w8MeVR1gpx640XYQ
R E. Howard - General Offleas
August 4, 1967
Approval for Engineering and Equipment Purchase
CEA 1430 - Aroclor Expansion
H. C. Carder F. J. Holxapfel
J. Cresce
In our review of the Aroclor expansion on July 28 you requested that CED proceed with definitive engineering and with the pur chase of long delivery and high priority equipment in advance of submitting the appropriation request.
Specifically, we recommend that the solid Aroclor flaker ($30,000), 5 alunimaa tanks for Krunmrich ($50,000) and 11 aluminum tanks for Anniston ($100,000) be placed on order. By combining all the aluminum tankage we should be able to nego tiate a better price. Cancellation charges for the equipment 3 months after comltaent are estimated to be $80-90,000. Engineering charges which will accrue by that time will bring the total up to the General Manager*s level of approval author ity.
Ke, therefore, request that General Manager's approval for $100,000 be granted to authorize definitive engineering and equipment purchase. The General Manager's signature on this memo will be CED's approval to proceed. Please return one signed copy to me.
vo
Approved
General Manager
\
`
R. E. Howard
DSW 200719
STLCOPCB4058783
DSW 200720
STLCOPCB4058784