Document LgQ2Egz7N1zmq9mpLjR5BMpzd
1052
CHAPTER 49
. 1953. Guide
/
Table 3. Performance Requirements of Water Meters*
''
SlZB In.
a H' I
U4----------------------------------
9 a A.
8_________ _______
Normal Test-Flow Limits GPM
lto 2 to 3 to
5 to
20 34 53
100
5 to 160 16 to 315
28 to 500 48 to 1.000
Minimum Test-Flow . GPM
K u
i| 11?
\-
2 4.
7 12
8 American Water Works Association Standards: Registration. The registration on the meter dial shall indicate the quantity recorded to be not less than 98 percent nor more than 102 percent of the water actually passed through the meter while it is being tested at rates of flow within the specified limits herein under normal test flow limits: There shall be not less than 90 percent of the actual flow recorded when a test is made at the rate of flow set forth under minimum test
The water demand for hose bibbs or other large demand fixtures taken off
the building main is frequently the cause of inadequate water supply to the
upper floor of a building. This condition may be prevented by sizing the
distribution system so that the pressure drops from the street main to all
fixtures are the same. It is good practice to maintain the building main
of ample size (not less than 1 in. where possible) until all branches to hose
bibbs have been connected. Where the street main pressure is excessive
and a pressure reducing valve is used to prevent water hammer or excesT
sive, pressure at the fixtures, it is frequently desirable to connect hose
bibbs ahead of the reducing valve.
-
The principles involved in sizing either up-feed or down-feed systems are the same. The principal difference in procedure is that in the downfeed, system, the difference in elevation between the house tank and the fixtures provides the pressure required to overcome pipe friction.
Procedure for Sizing Cold Water Systems
' The recommended procedure for sizing piping systems is outlined in fol lowing paragraphs 1 to 6, inclusive.
1. Draw a sketch of the main lines, risers, and branches, and indicate the fixtures to be served. Indicate the rate of flow of each fixture.
Table 4. Allowance in Equivalent Length of Pipe for Friction Loss in
Valves and Threaded Fittings
Diameter op Fitting
In.
00 Deg Standard
Ell Ft
n-- 3A
1 1M
m---
2____
VA----------------
3 3L$
A"
6-----------------
i 2
2.5 3 4
5 7
8 10 12
14
17
20
Equivalent Length of Pipe for Various Fittings
45 Deg Standard .
Ell Ft
90 Deg Side Tee
Ft
Coupling or Straight Run of Tee
Ft .
0.6 1.5 1.2 3 1.5 4 1.8 5 2.4 6 37 4 10 5 12 6 15
7 18 8 21
10 25 12 30
0.3 0.6 0.8 0.9 1.2
1.5 2
2.5 3 3.6 4.0 5 6
Gate Valve
Ft
0.2 0.4 0.5 0.6 0.8 1.0 1.3 1;6 2 2.4 2.7 3.3 4
Globe Valve
Ft
8 15 20 25 35 45 55 65 80 100 125 140 165
Angle Valve
Ft
4 8' 12 15 18 22 . 28 34 40 50 55 70 80
Water Services
.1053
2. Using Table.2, compute the demand weights of the fixtures in fixture units. 3.. Determine the total.demand in fixture units and, using Fig. 1 or Fig. 2, find the expected demand in gallons per minute.
4. Determine the equivalent length of pipe in the main lines, risers, and branches.
Since the sizes of the pipes are not known, the exact equivalent length for various
fittings, etc., cannot be made. Add the equivalent lengths, starting at the street main and proceeding along the service line, the main line in the building, and up the riser to the top fixture of the group Berved.
5. Determine the average minimum pressure in the street main and the minimum -
pressure required for the operation of the topmost fixture. This latter pressure should be 8 to 15 psi.
6. Calculate, by means of Equation 1, the approximate design value of the average pressure drop per 100 ft of pipe in the equivalent length determined in paragraph 4.
p = [P - 0.43U - 10] ^
where
p = average pressure loss per 10Q ft of equivalent length of pipe, psi.
P = pressure in street main, psig.
,
(1)
Table 5. Equivalent Lengths of Iron Pipe to Give Same Loss as Special
Fittings, and Apparatus
Fitting Apparatus
30-gal Vertical hot-water tank, f in. pipe... 30-gal Horizontal hot-water tank, f in. pipe Water,meters (No valves included)
| in. with J in. connections........................ | in. with 1 in. connections........................ $ in. with f in. connections........................ 1 in. with 1 in. connections........................ li in, with 1 in. connections'..................... Water softener.................................................
Nominal Diameter or Pipe--Inches
i1
4 17 1.2 5
1
56 16
'll
_
--
6.7 28
90
4.8 20
64
3.4 14
45
9 30
-- 4.4 14
-- 50-200 --
--
_--
115 54 --
B = height of highest fixture above street main, feet..
L = equivalent length determined in paragraph 4, feet.
If the system is of the down-feed supply from a gravity tank, the height of water in the tank, converted to pounds per square im;h by multiplying by 0.43, replaces the street main pressure, ana the term 0.43 B in Equation 1 is added instead of sub tracted in calculating the term p. In this case, H will be the vertical distance of the fixture below the bottom of the tank.
7. From the expected rate of flow, determined as in paragraph 3, and the value of p, calculated as in paragraph 6, choose the sizes of pipe from Figs. 3, 4 or 5.
Example 2: Assume a minimum street main pressure of 55 psig; a height of topmost fixture above street main of 50 ft; a developed pipe length from water main to highest fixture of 100 ft; a total load on the system.of 50 fixture units; and that the water closets are flush-valve operated. Find the required size of supply main.
Solution: From Fig. 2 the estimated peak demand is found to be 51 gpm. From Table 3 it is evident that several sizes of meters would adequately measure this flow. For a trial computation choose the 1$ in. meter. From Fig. 6 the pressure drop through a 1J in. disc-type meter for a flow of 51 gpm iB found to be 6.5 psi.
Then the pressure drop available for overcoming friction in pipes and fittings is 65 - (15 + 50 X 0.43 + 6.5) = 12 psi.
At this point it is necessary to make some estimate of the equivalent pipe length of the fittings on the direct line from the street main to the highest fixture. The exact equivalent length of the various fittings cannot now be determined since the pipe sizes of the building main, riser, and branch leading to the'highest fixture are not known as yet, but a first approximation is necessary in order to make a tentative selection of pipe sizes. If the computed pipe sizes differ from those used in deter mining the equivalent length of pipe fittings, a recalculation will be necessary, using