Document LgEKYYjG8rqvL3davawZQEmYw
Ref: 8 Montana
SENT VIA EMAIL DIGITAL READ RECEIPT REQUESTED
City of Poplar
, Mayor
Re: Inspection Report for City of Poplar/Wastewater Treatment Plant, NPDES Permit No. MT0030597
Dear
:
On July 24, 2024, a representative of the U.S. Environmental Protection Agency inspected the City of Poplar's Wastewater Treatment Plant in Poplar, Montana, to evaluate compliance with the facility's National Pollutant Discharge Elimination System permit for wastewater discharge. The inspection was conducted under the authority of Section 308 of the Clean Water Act. Enclosed is a report of the inspection.
Inspection findings are summarized within the enclosed inspection report in a table titled "Findings, Corrective Actions and Recommendations." Within thirty (30) days of receipt of this report, please provide the EPA with a summary of corrective actions taken to address each of the findings identified in the report and any information that may change the findings or content of the report. This summary should be sent to:
U.S. EPA Region 8 - Montana Office
Fort Peck Acting Environmental Director
Please contact me at this letter or the enclosed report.
if you have any questions regarding
, several weeks in advance. Throughout the inspection, I noted observations in bound notebooks and checklists which reflected conditions of the Permit. Photographs taken during the inspection are included in the attached photo log and are maintained by EPA in accordance with the Quality Assurance Field Activities Procedure and Standard Operating Procedure.
The inspection commenced at approximately 0800, when the inspectors arrived at the facility and met
with facility representatives
, Poplar Public Works Director and
, project
manager, Interstate Engineering. The group convened in the control building where I presented my
credentials and outlined the intended format and scope of the inspection. We then began the discussion
portion of the inspection, where facility representatives provided an overview of the wastewater
operations, their Operation and Maintenance (O&M) Program, monitoring procedures, lift stations,
collection systems, and active and planned projects within the collection system and at the wastewater
treatment system.
The facility was originally constructed in 1978 with periodic upgrades, the latest being in 2020. The facility treats the residences and businesses of the city of Poplar with a population of approximately 758 people (2020 census), as well as the surrounding homes on the reservation for a total population of 2,350. Facility representatives stated the facility does not treat any industrial wastewater, only domestic.
According to facility personnel, the current facility consists of a headworks, oxidation ditch, clarifiers, and disinfection. Influent enters the facility through the headworks, which consists of a mechanical bar screen (waste collected is brought to the Wolf Point landfill for disposal approximately once per month) and a grit chamber (waste collected is disposed of in one of the on-site drying beds). Wastewater then flows through a Parshall flume and is either diverted into a lagoon system (overflow) or into an oxidation ditch. From the oxidation ditch, wastewater flows to a clarifier for settling prior to flowing through UV disinfection. Treated wastewater flows through an ultrasonic flow meter and out a pipe (Outfall 001) to an unnamed ditch connected to the Missouri River. The facility returns most of the activated sludge and scum from the clarifier back to the oxidation ditch. A small portion of the sludge wasted from the clarifier flows to the aerobic digester. The digester aerates sludge for approximately 30 days before pumping the sludge to one of four drying beds. The facility is a continuous discharger with a design flow of approximately 0.6 million gallons per day (MGD) and an average flow of approximately 0.35 MGD. The pipe for Outfall 001 discharges to a naturally occurring surface water channel that runs approximately 1,300 feet into the Missouri River.
The City operates one lift station in the collection system. Facility staff stated the lift station is checked daily. The City also has several siphon stations; however, they do not require pumps. explained that siphon stations are used to transport wastewater without suction, in place of the use of pumps. The collection system is comprised of approximately 50% PVC piping, with the rest a variety of asbestos/cement or clay/tile piping. Representatives indicated a phased upgrade of the collection system is underway, with phase 1 consisting of approximately 4,000 feet of sewer main and 25 manhole replacements in 2021; phase 2 consists of approximately 5,800 feet of sewer main and 35 manholes to be replaced in 2025. Representatives indicated the entirety of the collection system is cleaned each year.
MT0030597 Poplar Wastewater Treatment Plant
Page 3 of 10
Records Review The following records were requested for review in an email dated July 3, 2024, prior to the inspection. Records were made available to review on-site, as well as copies made with a review of the records off-site on August 6, 2024.
x Copy of NPDES permit #MT0030597. x Effluent flow values for monitoring periods ending January 31, 2024, February 29, 2024, and
March 31, 2024. o Evaluated records for required reporting values, and percent removal calculations for
biochemical oxygen demand and total suspended solids. x In-house results for pH for monitoring periods ending January 31, 2024, February 29, 2024, and
March 31, 2024. o Evaluated records for reported minimum and maximum concentration values. x Laboratory analytical results for biochemical oxygen demand, total suspended solids, nitrate + nitrite, total ammonia, total kjeldahl nitrogen, total phosphorus, and Escherichia coli (E. coli) bacteria for monitoring periods ending January 31, 2024, February 29, 2024, and March 31, 2024. o Evaluated records for reported concentration values. Chain of Custody and Laboratory Analytical Reports for monitoring periods ending January 31,
2024, February 29, 2024, and March 31, 2024. o Evaluated records for proper sample relinquish methods, analytical methods, and required
reporting limits. x Records of Laboratory Equipment and Controls, including records of equipment calibration. x O&M program records, to include Operations & Maintenance Manuals, Standard Operating
Procedures, and maintenance logs. x Permit required documents to include an Industrial Waste Survey and weekly treatment system
inspections.
Facility Evaluation
After the facility records review, we walked through the wastewater treatment process. We started with
the on-site laboratory located in the control house. We proceeded to the headworks building to see the
on-site siphon station and manual bar screen outside the building (photos 38 & 39). Inside the
headworks building we observed the influent flow meter (photo 42), automatic bar screen (photo 40),
and cyclone grit removal system (photo 41). We followed the flowpath of the wastewater and went to
the oxidation ditch next, observing the aerators (photos 43 & 44), flow into and out of the oxidation
ditch (photo 48), and locations where clarifier scum (photos 45 & 48) and return activated sludge (RAS)
(photo 46) enters the oxidation ditch. We then walked to the aerobic digester (photo 47) before
following the wastewater flow to the clarifier (photo 50). We observed the inflow from the oxidation
ditch (photo 51) and the scum pit (photo 52). We then observed the effluent from the clarifier (photo
49), which heads back to the control house. In the control house we observed the UV disinfection system
(photo 53) and the effluent flow measuring device. At the time of the inspection, facility representatives
stated only an ultrasonic meter (photo 54) was present to measure effluent flow; however, in an email
from
dated August 5, 2024,
stated the facility does have a sharp-crested weir as a
primary effluent flow measuring device and provided schematics of its location. The weir is located in
the same location as the ultrasonic meter, but was not observed at the time of the inspection. In
email, stated there currently is no measuring gauge installed, but one was on order and would
MT0030597 Poplar Wastewater Treatment Plant
Page 4 of 10
Finding #2: Failure to properly preserve samples. The facility is not properly preserving biochemical oxygen demand, total suspended solids, nitrate + nitrite, total ammonia, total kjeldahl nitrogen, and total phosphorus samples. Specifically, the samples collected on January 25, 2024, were received by the laboratory at a temperature of 8.6C and a comment of `melted ice' on the chain of custody form.
Permit requirement: Part 4 of NPDES permit #MT0030597 states "...sampling and test procedures for pollutants listed in this part shall be in accordance with guidelines promulgated by the Administrator in 40 CFR Part 136, as required in 40 CFR Part 122.41(j)."
40 C.F.R. 122.41(J)(4) and Part 6.2 of the NPDES permit #MT0030597 states, "Monitoring must be conducted according to test procedures approved under 40 C.F.R. Part 136, unless other test procedures have been specified in this Permit." 40 C.F.R. Part 136 describes approved analytical methods which in turn describes additional requirements to include preservation. The preservation method for the above indicated parameters includes cooling the sample to 6C."
40 C.F.R. 122.41(a) and Part 7.1 of NPDES permit # MT0030597 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
Corrective Action: Ensure samples collected are appropriately preserved until laboratory delivery. Records of the temperature of samples received are included on the chain of custody. The facility should retain a copy to verify preservation temperatures are being achieved. In the response to this report, provide EPA and the Tribes, with a description of the corrective actions taken to address this finding.
Finding #3: Buffer solutions for pH calibration were expired. Specifically, the City of Poplar's Wastewater Treatment Plant's buffer solutions for calibrating the pH meter are expired. The facility uses buffer solutions 7 (expired August 2023) and 10 (expired August 2022).
Permit requirement: Parts 3 and 4 and Tables 2 and 3 of NPDES permit #MT0030597 indicate the sample type and monitoring frequency.
40 C.F.R. 122.41(J)(4) and Part 6.2 of NPDES permit #MT0030759 requires monitoring to be conducted according to test procedures approved under 40 C.F.R. Part 136.
40 C.F.R. Part 136 lists test procedures and sample collection requirements. Standard method procedures for pH include calibrating the pH probe with buffer solutions.
40 C.F.R. 122.41(a) and Part 7.1 of NPDES permit # MT0030597 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water
MT0030597 Poplar Wastewater Treatment Plant
Page 6 of 10
Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
Corrective Action: Laboratory equipment is required to be calibrated by Standard Methods or Part 136, Title 40 of the Code of Federal Regulations. Ensure buffer solutions used in the calibration of all monitoring equipment (pH meter) are within the expiration date. In the response to this report, provide the EPA and the Tribes with a description of the corrective actions taken to address this finding.
Finding #4: Failure to have an effluent primary flow meter.
Specifically, the facility currently only has an ultrasonic meter to record effluent flow. Ultrasonic meters
are considered secondary recording devices as they can frequently require calibration. A primary device
such as a weir or a flume is required as a primary device to ensure the secondary recording device is
calibrated and accurately recording effluent flow. In an email from
dated August 5, 2024,
stated the facility does have a sharp-crested weir as a primary effluent flow measuring device and
provided schematics of its location. In
stated there currently is no measuring gauge
installed, but one was on order and would be installed within the month.
Permit Requirements: Part 4, Table 3, footnote b/ of NPDES permit #MT0030597 states, "Flow measurements of effluent volume shall be made in such a manner that the Permittee can affirmatively demonstrate that representative values are being obtained."
40 C.F.R. 122.41(a) and Part 7.1 of NPDES permit # MT0030597 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
Corrective Action:
According to
email a sharp-crested weir exists on-site, and a measuring gauge was being
ordered and installed. In response to this report, provide the EPA and the Tribes with photographic
evidence of the weir with gauge installed.
Finding #5: Samples were not analyzed within the required timeframes. Specifically, BOD samples collected on January 25, 2024, at 14:51, were not analyzed until January 31, 2024, at 08:45 (5 days, 18 hours), which is past the required holding time of 48 hours.
Permit Requirement: Parts 3 and 4 and Tables 2 and 3 of NPDES permit #MT0030597 indicate the sample type and monitoring frequency.
40 C.F.R. 122.41(J)(4) and Part 6.2 of NPDES permit #MT0030759 requires monitoring to be conducted according to test procedures approved under 40 C.F.R. Part 136.
MT0030597 Poplar Wastewater Treatment Plant
Page 7 of 10
40 C.F.R. Part 136 lists test procedures and sample collection requirements. Standard method procedures for pH include calibrating the pH probe with buffer solutions.
40 C.F.R. Part 136.3(e), Table II (9) states the maximum holding time4 for Biochemical Oxygen Demand is 48 hours. Footnote 4 states, "Samples should be analyzed as soon as possible after collection. The times listed are the maximum times that samples may be held before the start of analysis and still be considered valid... For a grab sample, the holding time begins at the time of collection...."
40 C.F.R. 122.41(a) and Part 7.1 of NPDES permit # MT0030597 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
Corrective Action: Samples are required to be collected and analyzed as described in 40 C.F.R. Part 136. Ensure laboratories are analyzing all analytes within the required timeframes. In the response to this report, provide the EPA and the Tribes with a description of the corrective actions taken to address this finding.
Finding #6: Failure to report laboratory results correctly. Specifically, the facility is reporting a `0' where a non-detect (ND) value was reported on the analytical report. The facility reported a `0' for Total Suspended Solids (TSS) 30-day and 7-day averages when the laboratory analytical report reported a ND for the following sample collection dates: January 25, 2024, February 20, 2024, and March 20, 2024. The facility reported a `0' for Total Ammonia daily maximum when the laboratory analytical report reported a ND for the following sample collection dates: January 25, 2024, and February 20, 2024. When entering a single sample value for the monitoring period with a ND or less-than (<) value from the laboratory analytical report, verify the detection limit, and report in one of two ways: 1) report the detection limit value with a `<' symbol prior to the number; or 2) report a no data indicator (NODI) code `B' (Below Detection Limit/No Detection).
Permit Requirement: Part 3, Table 2, footnote b/ of NPDES permit #MT0030597 indicates the sample type and monitoring frequency.
Within NetDMR, a tip sheet for `Submitting Timely, Accurate, and Complete NPDES Discharge Monitoring Reports' is available under the `help' tab. In this tip sheet, under frequently asked questions, it states, "NetDMR allows you to use a the less-than (<) symbol if your regulatory authority or permit requires a value to be reported. You may also use NODI code "B - Below Detection Level/No Detection" to report a parameter or value below the detection level or had no detection."
40 C.F.R. 122.41(a) and Part 8.1 of NPDES permit # MT0030759 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
MT0030597 Poplar Wastewater Treatment Plant
Page 8 of 10
Corrective Action: Data is required to be reported in the NetDMR system as it is reported on the laboratory analytical data reports or with the use of approved NODI codes. The facility must re-enter and submit corrected values in NetDMR for all 2024 reporting periods. In the response to this report, provide the EPA and the Tribes with a description of the corrective actions taken to address this finding.
Finding #7: Calculation records do not use the correct data to complete calculations. Specifically, the facility is using a `0' in calculations where a non-detect (ND) or less-than (<) value was reported on the analytical report. The facility used a `0' in Total Suspended Solids (TSS) percent removal calculations for the following sample collection dates: January 25, 2024, February 20, 2024, and March 20, 2024. When using a reported non-detect or less-than value in a calculation of any kind (including averages), verify the detection limit is correct, and complete the calculation by using the detection limit value in place of the non-detect or less-than value. Report the calculated result with a `<' symbol prior to the number in the appropriate location on the discharge monitoring report (DMR). Due to the use of a `0' in the calculations on the above dates, the percent removal calculations reported are inaccurate; the calculations should be reported as follows:
Monitoring Influent Effluent Calculation
Reported Corrected
Period end TSS result TSS result
value
value
date
(mg/L)
(mg/L)
01/31/2024 173
ND(RL=10) (173-10) / 173 x 100 = 94.2
100%
<94.2%
02/29/2024 88
ND(RL=10) (88-10) / 88 x 100 = 88.6
100%
<88.6%
03/31/2024 102
ND(RL=10) (102-10) / 102 x 100 = 90.2
100%
<90.2%
No effluent exceedances would have occurred as a result of the corrected value, if reported.
Permit Requirement: Part 3, Table 2, footnote b/ of NPDES permit #MT0030597 indicates the sample type and monitoring frequency, as well as the requirements set for percent removal.
40 C.F.R. 122.41(a) and Part 8.1 of NPDES permit # MT0030759 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
Corrective Action: The facility must calculate reportable results by using the verified detection limit in place of a non-detect or less-than value. The facility must recalculate and submit corrected TSS percent removal values in NetDMR for all 2024 reporting periods. In the response to this report, provide the EPA and the Tribes with a description of the corrective actions taken to address this finding.
Finding #8: Samples were not collected and reported correctly. Specifically, the facility did not collect samples for total ammonia or total phosphorus for monitoring period ending March 31, 2024. The facility correctly reported a NODI code E-Analysis Not Conducted/ No Sample for the total phosphorus daily maximum; however, reported a `0' for the total ammonia daily maximum result instead of NODI code E.
MT0030597 Poplar Wastewater Treatment Plant
Page 9 of 10
Permit Requirement: Part 4 of NPDES permit #MT0030597 states, "...At a minimum, the following constituents shall be monitored at the frequency and with the type of measurement indicated; samples or measurements shall be representative of the volume and nature of the monitored discharge."
Part 4, Table 3 of NPDES permit #MT0030597 indicates the sample type and self-monitoring frequency to include total ammonia and total phosphorus.
40 C.F.R. 122.41(a) and Part 8.1 of NPDES permit # MT0030759 states, "The permittee must comply with all conditions of this permit. Any permit noncompliance constitutes a violation of the Clean Water Act and is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or denial of a permit renewal application."
Corrective Action: Data is required to be reported in the NetDMR system as it is reported on the laboratory analytical data reports or with the use of approved NODI codes. If no sample is collected for analysis, the facility must report that no sample was collected with the use of NODI codes. The facility must re-enter and submit corrected representation of parameters where samples were not collected, in NetDMR for all 2024 reporting periods. In the response to this report, provide the EPA and the Tribes with a description of the corrective actions taken to address this finding.
Recommendation: Blower motor needs repair/replacement. Specifically, both aerators within the oxidation ditch are running off one blower motor. Repair/replace the second motor to create redundancy and to avoid the potential shut down of aerators in the oxidation ditch if the existing motor were to fail.
MT0030597 Poplar Wastewater Treatment Plant
Page 10 of 10