Document LR0Y07yvXoENEprrmzeD3jy7
R&S 140764
MINUTES OF VCL SAFETY ASSOCIATION MEETING AT CLEVELAND
OCTOBER 24-26, 1973
A. General
The agenda of the meeting is covered in Attachment 1.
Each item covered will be discussed in the text of these minutes.
A list of the attendees is covered in Attachment 2. An updated list of the member companies and their official representatives is covered in Attachment 3.
If further information is desired on any of the items covered in these minutes, please contact me as I may have further details.
B. Blend Tank Safety Guidelines - P. Bogart
Mr. Bogart compiled a list of safety guidelines on blend tanks based on data that he received from various sources within the PVC industry. He wrote these up and they appear as Attachment 4 of this report. He asked that we read these and then submit comments back to him. I will > perform this function.
C. Monomer Loading and Storage Safety Guidelines - D. Miller
Mr. Miller presented Shell's design criteria for VCM storage. These criteria are really the Shell International guidelines for LPG based on an LPG fire they had sometime ago. They include:
1, No liquid must be allowed to stand underneath the vessels. It must all drain away.
2. All spheres must be at least a diameter apart,
* 3. There mi^st be fire walls around all-pumps and safety valves. -
4. Only essential nozzles are allowed below the maximum liquid level in the vessel.
R&S 140765
2- -
5.! No valves are allowed beneath the drip line of the vessel. j Instead they place spring loaded ball valves outside of the dikes. I
6. All piping of VCM is above ground.
7. Varex style level gauges are used.
8. Fire coverage is provided by hydrant mounted fog nozzles and a ' deluge ring with buried headers.
He will have these guidelines typed and distributed to all members.
D. Reactor Entry - 0. Pal inski
Mr. Palinski presented the procedures currently in use at Universal PVC Resins Inc. This is a subsidary of Robin-Tech. They were formerly owned by Allied Chemical. I will note just the pertinent points or deviations from current Dow procedures that were discussed during the course of this presentation.
1. A vessel entry permit is required when entering any vessel, hole, etc. that is greater than 4 feet in depth.
2. The permit is valid for only one shift after which it must be renewed. The permit must be displayed at the site at all times, and is removed at the end of the shift and tbe job. The permits are then filed by the safety supervisor and retained for ninety
/ . days. They have found that they are very useful for insurance purposes.
3. The safety watch must always be. at the manhole and can cover . only one vessel. This point brought up some additional discussion with the following information being obtained:
a. Ten companies require a constant watch as was described here and as used by Dow.
b. Fourteen companies will allow a watch to cover more than one vessel or for the watch to go away from the manhole for short periods of time.
c. Three companies rely on a personnel protection alarm system. This system revolves around the utilization of an electrical device, which requires acknowledgement by the man in the vessel every three minutes or outside personnel are notified of a potential problem automatically.
-3-
4. The man in the vessel wears a safety belt or shoulder harness or wristlets but has no line attached to them. In the event of a problem the safety watch at the manhole sounds an alert and when help arrives he then goes down into the vessel and attaches a safety line to the man's harness. This brought out considerable discussion on the merits of this type of system and the dangers involved in sending a man into a vessel with an unknown problem possibly existing.
5. They use an explosion proof drop cord light at 110 volts, A show of hands revealed that 22 companies used portable cord lights with 12 of them being 110 volt and the remainder being lower voltage.
6. They blank or remove all lines. A show of hands revealed that 12 companies are now using block and bleed systems instead of blanking where repetitive reactor entry is required.
7. The foreman takes oxygen and L.E.L. reading at three different points in the reactor prior to entry. This is rechecked when ever a man reenters a vessel after a break or at shift change.
8. All electrical circuits are locked by as many as 3 or 4 different people with different locks at the breaker. These include locks by the foreman, the maintenance man involved (if there is one), the man in the vessel, and the safety watch at the vessel manhole.
Safety Valve Testing - R. Frantz
Mr, Frantz reviewed the general safety valve testing procedures utilized by Union Carbide at their Texas City Plant. Operating people decide on the type and frequency of testing based on the following criteria:
1. Testing is carried out at least once per year on Class 1 valves, which include those in corrosive service, those that might be subject to plugging, or those new valves in unknown services.
2. Testing is carried out between one and two years on Class 2 valves, which include those on fired pressure vessels, those under extreme pressure and temperature, and those with less severe corrosive service then-those in Class 1.....................
3. Testing is carried out between two and five years on Class' 3 ' valves, which include all other safety valves.
R&S 140766
R&S 140767
-4-
Their testing is scheduled by computer, but in addition they paint each valve a distinctive color for the particular year it was tested so'that anyone can tell at a glance the last year the valve was tested. ;
Union Carbide does not use safety valves on reactors. Rather they only use frangibles due to the fact that they have had previous problems with valves plugging up. They-currently use one 3" and one 4" disc on a 5700 gallon vessel. These discs are in separate parallel lines venting directly to the atmosphere.
Additional discussion at this point revealed that 6 companies use only a disc with'no safety valve (similar to that described by Union Carbide), while 12 use a frangible under a relief valve similar to what we at Dow use. This previous data applies to reactors only.
In the case of VCM storage, 19 companies use only valves while 12 use discs below safety valves. Union Carbide uses reverse buckling safety discs. Discussion revealed that nine companies had at one time used reverse buckling discs but only 3 are currently using them. Some companies have had trouble with reverse buckling discs in that sometimes the disc can flip up without being cut by the knife edge. It was pointed out that installation is extremely important. Other companies have backed away from reverse buckling discs because if you happen to hydrostatically fill a vessel, the disc won't break at the proper pressure. Also, the vendors do not recommend reverse buckling discs if a possibility exists of hydrostatically filling the vessel. I inquired as to whether the people using reverse buckling discs were utilizing this disc to /test the safety relief valves in place. Several people indicated they had seen a demonstration of testing valves in place but none were currently using that system. All people removed their valves for testing as indicated by a show of hands, and 19 checked their reactor valves at a frequency of 1 year or less.
F. Safety Valve Sizing' - F. Frey
Mr. Frey presented 3 considerations from a philosophical point of view.
1. The valves should not be larger than required.
2. Should assure that the vessel -wi 11 not rupture.........................*'
3. Should minimize the amount of material being vented.
5- -
He stated the main reason that he had agreed to be the discussion leader was his concern for the divergence of opinion on the size or method of sizing the safety relief valves for reactors. He then illustrated by example. If we assume that we have a 10,000 gallon reactor, the standard formula (which is based on .0012 square inches per gallon) would indicate we need 12 square inches of vent relief area. The Diamond Shamrock revised formula would indicate that we need a vent area of 16 to 21 square inches. The Goodrich technique would indicate we require 13 square inches of vent area. W. Boyle's (Monsanto) formula would indicate 56 square inches and the F.IA specification would indicate an area of from 67 to 140 square inches would be required.
Mr. Frey then proposed that the Vinyl Chloride Safety Association fund a research program to investigate the required techniques for sizing relief valves for PVC reactors. No conclusion was reached on this point despite the fact that Frey indicated Boyle thought it would be a rather simple matter and could be carried out for something less than $10,000.
Subsequent discussion referred to Huff's paper (Dow Chemical) at last years AICHE meeting and the question was asked as to whether it could be applied to PVC reactors. I indicated we were doing some work on safety relief sizing for Saran vessels and would check out if this data could be presented at a subsequent meeting. There was then a discussion on the sizes of vents currently being used in the PVC industry on various sized reactors. This data was tabulated as follows;
R&S 140768
Reactor Gallons
4.000 10,000 16,000 24.000 16.000 20,000
4.200 13,400 10,000
2.200 6.000
Relief Size
Vent Area
6x8 8 x 12 2 - 8 x 12 3 - 12 x 16
3- ? 2 - 12 x 16
16 in.? )
26 in/ ) 52 in. , ) 220 in. )
90 in.. 140 in/
3" Disc 2 - 4" Disc 2 - 10" Disc
160 in/.
3"'Inlet Valves 4" Inlet Valves
) )
Comments
at 190 psia at Diamond Shamrock
safely relieved a vessel
FIA approved this for Georgia
Pacific at 200 psia
bulk polymer
bulk polymer
ICI at 200 psia (never have had
" both flo* -w )
*T ' % *
have safely relieved
6- -
G. I Static Control - W. Bradford
l Mr. Bradford attempted to employ the technique of goading us into a ; discussion as to why we need to ground to control static. He speci-;,
fically asked why anyone bothers to ground VCM railcars when loading . or unloading because he contended that there is not an explosive
mixture there anyway. This of course resulted in quite a discussion with the following major points coming out.
1. Most people feel it is just a good standard operating procedure to ground systems handling hydrocarbons.
2. Tennaco had a 3,000 gallon VCM spill which was ignited by a resin conveying line static discharge so it can happen.'
3. ICI had a code that required jumper grounds on monomer lines. After extensive testing they proved it wasn't necessary as the bolts in the flanges provided satisfactory ground.
4. API has proven that spark proof tools are not warranted. In fact, you can get a spark from spark proof tools as well as standard tools.
5. Twenty-one companies have Division 1 reactor areas.
H. Catalyst Handling - R. Stack
Mr. Stack presented the PPG movie on catalyst decompositions. This movie has been presented to Dow personnel in the past. He suggested that since catalysts are looked upon by the FDA as being bad (whereas initiators are not nearly as bad because they are consumed) we should be talking of initiators and not catalysts in the PVC industry. He indicated that there is an Organic Producers Safety committee in effect now and PPG is a member. It includes manufacturers in the U.S. as well.as the rest of the world. This group has developed a manual on methods of classifying and testing various initiators. A summary of the data from that committee is covered in Attachment 5. Several comments came out during the discussion.
1. No one has ever seen an explosion unless the material has been confined.
2. Sometimes you get ignition-on decomposition but other 'times'you do not.
3. PPG prefers that catalyst solutions be added through open manholes, however, they do indicate that in the polyethylene business they are pumped in as solutions to hot reactors.
<>i
v I.
R&S 140769
-7-
4. Seven companies have had problems with decompositions or fires this past year.
5. In a separate discussion with W. Kcim of PPG, I learned that several people arc (and have been for sometime) using "neat" IPP in PVC reactions. When doing this they weigh out the IPP in ice cream cartons and charge it to a reactor with water in
it at a very closely controlled temperature being very careful that the time from addition to heat up is closely controlled. He further indicated that polyethylene producers are actually pumping 10 to 20% solutions of IPP in solvents to their reactors. He also said that several people take the solid IPP immediately upon receipt and make up a solution in up to 10,000 gallon quantities.
I, Pressure Vessel Obsolescence and Inspection - 0. Barr
General comments from this discussion were as follows:
1. Eight companies are required by company code to test vessels, but the remainder are not. Approximately 12 companies are utilizing thickness testing of some sort. General input indi cated that glass lined reactors from 17 to 23 years old were still in service and that it really depended on the care and treatment of the vessel as to whether they were obsolete or not. One company said their Engineering Department had predicted that after 30 years you should expect to see some fatigue failure in stainless steel vessels. However, Goodrich has vessels 30 years old with no failures thusfar.
2. All people but one have had chloride ion stress crack corrosion on their Bird centrifuges and this one has been in service for over 8 years now. No explanation was given for this seemingly unusual length of service.
i*
3. The general conclusion was that it appears that vessels don't really become obsolete.
J. OSHA Experience - W. Bradford
, Mr. Bradford revealed that within 01 in there have been many OSHA inspection^, but not at the PVC plant.". Of these, i6 were to 'check on compliance, 13 to check on complaints and 3 to check on fatalities. There were a total of 256 violations with fines of $4,000. They are currently contesting a noise complaint violation in a metal working plant. The violation sites that are in this new building they did not engineer the noise out. Guarding signs, walking surfaces, etc., are the most common violation areas. Three
R&S 140770
R&S 140771
-8-
PVC and one VCM plant have been inspected based on a show of hands. In general, most companies say the inspectors are very capable. However, they do seem to come in and look at specific areas and pass over other areas that might really be more important.
K. Monomer Leak Handling - R. Langer
Mr. Langer of Dow discussed the conductivity type halogen analyzers in use in the Midland Division, how they are checked, the printout available computer systems in use, etc. He stressed 1) the need for time weighted expose'e average data for people, 2) the fact that operating personnel' make notes on the charts whenever high levels become apparent thus having them intimately involved and 3) this is a good method for early detection of leaks. Goodrich personnel indicated they had a similar type system utilizing a Bendix analyzing unit. Several companies came up to me afterwards and asked for more specific data on this type of analyzer and I have referred them to the AED Company who are now manufacturing these units for Dow.
L. Safe Monomer Venting - M. Trowbridge
Mr. Trowbridge indicated there were 3 primary reasons for venting.
1. Frangible premature failure or fatigue failure.
2. A power failure (which could be offset partially by having , auxiliary power). .
3. Runaway batches (which in some cases could be offset by short stop addition.
He indicated that at Goodyear their safety piping consists of a frangible in the main line followed by a three-way valve. On one leg of the three-way valve they have a safety relief valve and on the other leg they have another frangible relief. In normal operation they have the three-way valve directed to the safety relief valve but if there is any indication of plugging they swing the three way valve to the second frangible and discharge directly to the atmosphere. In addition to this they usually have a small (2 to 4") manual vent on each reactor. They use a gauge rather than a bubbler to determine pressure between the frangible and the safety relief valve. Several comments came out in the-discussion after**--this talk.
1. Several companies have put bends in their vent lines to direct monomer vapors in a certain direction but when the frangible or safety relief ruptured the line was straightened out due to the
(i.
R&S 140772
-9-
!
I torque of the exiting gas. One company indicated that it was l important to cut the top end of the vent pipe off square rather I than at a beveled angle as this also could cause bending due to I the torque.
2. All but one or two of the. companies have separate manual vents in addition to the safety vents. Three companies have had recovery vent systems ignite due to lightening and as a result they have installed steam snuffers. One company has installed a steam ejector at the top of the vent stock to help disperse the monomers after a vent release.
3. In Germany there was a report that the government in one area required a recovery system on the emergency vent system. There was much concern about this subject and the question came up as to whether it would also be required in the U.S.A, in the future.
4. About half of the people use flame arrestors on their recovery system vents, while the other half do not.
5. It was reported that A. D. Little has a computer program that can predict dispersion of VCM vapor clouds. This work was originally done for the Coast Guard but A. 0. Little would be willing to discuss the information with others. It is scheduled to be released in January 1974. The primary concern here is with the detonation of these vapor clouds. The secretary will make a contact on this and report back at a later date.
M./ Noise Control - E. Schenke
The important item coming out of this discussion is that you must document all the action that is taken to avoid or eliminate noise problems and further we must keep the pressure on vendors for quieter equipment.
N. VCM Exposure Standard and Environmental Health Problems - P. Bogart
The following points came out in this discussion:
1. The MCA study on animals was initiated on September 1 and preliminary results are expected back by January 1. No one but Bogart knew of this. The-European Studies by Viola indfcate that at levels of 200 ppm or lower there are no problems on mice.
2. Four companies including Dow have the lower level set at 50 parts per million. Eleven other companies have carried out surveys to determine their actual exposure levels, but have set no level below the 200 part per million government regulation.
R&S 140773
-10-
3. The J&W analyzer that reads down to 50 parts per million is considered very inaccurate. However, the Century portable vapor analyzer is considered to be very good.
4. One company said that they were averaging 80 parts per million TWA and that it would be very difficult to get. this below 50 ppm.
5. Goodyear has been given a goal by their company that they get the VCM level in their resin down to 50 parts per million.
The group decided not to discuss the'subject. The discussion ended with Bogart making a pitch that everyone go back to their environmental control people and ORC representatives and tell them to start providing input to the various governmental agencies. It was felt that if we don't provide input now we may never have another chance.
0.. Accident Reviews
1. VCM tank car derailment in Fort Wayne by Goodrich. An excellent presentation was given including a film and still pictures. A detailed write up was also handed out and is included as Attachment 6. I inquired about the availability of the film for use by Dow and they said that it may be available in approximately
. 6 months. I gave them my name and address and they indicated that they would contact me. Several interesting points came out in this discussion.
a. The International Association of Fire Chiefs have now established a policy that if you can't get large volumes of water on the exposed steel of the vapor space of a vessel in 5 to 8 minutes you should back off 2,000 feet and wait as the car will explode due to the metal softening in the vapor space area.
b. They are exploring the railroad's sizing of relief valves and are having some difficulty finding their way through the details.
c. They feel that the car exploded due to the relief valve either being damaged or that it was not large enough to handle the liquid release.
2. Two catalyst storage problems by General Tire.' Both of the^e" incidents involved the storage of diluted material in bottles stored in the original freezer containers as received from the vendor which are kept cold utilizing dry ice. In one of the incidents they felt the problem was due to either poor gasketing or a man putting an overheated sample back in the freezer after he had used a portion of it. The second
R&S 140774
-11-
incident was a result of a man not placing the dry ice in the freezer properly. There was no fire in either case just a vapor release. During the course of the discussion it was pointed out that not removing the paper used to cover the dry ice is against the regu lations of the FIA, and also it is extremely important to have the grating in the bottom of the freezers in order to get good circulation.
3. Another catalyst problem. This * trident involv.--; ; - loss of 13 trays of neat IPP in an upright free., . -.-7 recur*, their material in plastic trays and store it in the same freezer as received. They feel the incident was a result of the freezer not being iced properly on their site. There was a decomposition but no fire.
4. A neat IPP problem by Monsanto. Again, in this case, the IPP is received in plastic trays stored in a freezer and they utilize this freezer for their inplant storage. In this case approximately 4 to 5 hours after the freezer had been delivered, it exploded and and burned. They do not know if anything had been taken out of the freezer or not. They suspect the material did not arrive properly iced or the shelves slipped down hindering circulation in the lower portion of the freezer.
5. VCM release while unloading a car by Dow Chemical. I reviewed the incident at our main monomer tank farm wherein a flexible line broke after it had been subjected to vibration as a result of the excess flow check in the car operating improperly. I described the safety system that we had valves that could be closed remotely in order to avoid inexcessive spills should such an incident like this occur. Many people were interested in the system we had installed. Further discussion revealed that there have been many problems with flexible lines utilizing steel braiding. Several companies pointed out that going from steel braiding to stainless steel braiding has resulted in no problems with up to 7 years of service.
6. VCM release while unloading a car by Goodrich. They had a problem very similar to ours where a flexible line parted and 5,000 gallons of material spilled out to the ground. Unfortunately they did not have automatic valves like we did and had to send a man in with a Scott air pack to close the valve on top of the car. Additional discussion at this., point revealed that therg... have been many problems with excess flow check valves. Several companies indicated they have had line breaks and the valves did not operate properly. The conclusion is "don't trust excess flow valves".
B8tS 140775
-12-
7. Flexible line break under a monomer receiver by I Cl. Another instance of flexible lines breaking while in service. In this case releasing 1,000 pounds of VCM to the ground. Discussion revealed that almost all people use flexible lines somewhere in their operation. Fourteen companies indicated they use swivel joints for tank car unloading and have only minor problems with leakage if they are greased every time they are used or on a once a week basis.
8. Explosion in a blend tank by BPCI. In this case there were two 30,000 gallon slurry tanks that were interconnected with an air ventilation duct with dampers in each branch of the line as well as in the common line from the fan. It was a push type system. Indications were that the initial explosion occurred in the fan and the second explosion occurred in the tank which had the damper open. The other tank had its damper closed and had no problems. Damage was limited to curving or bulging out the top of the tank and blowing the duct off of the top of the tank. The tank was equipped with a 12" diameter vent and a 24" x 15" rectangular manhole. This vent area was apparently sufficient to relieve the vessel to limit the damage. The tank was
. three-quarters full at the time of the incident. Discussion revealed that one company uses an inert atmosphere and holds at 2% oxygen maximum while another one use inert atmosphere but does not check the atmospheric composition. Eleven companies use a forced air purge and only check on a spot basis. Eight other companies don't do anything at all with respect to purging or checking..
9. Vent line fire by Tennaco. In this particular case the plant was in the midst of an electrical storm which caused a voltage drop and as a result all the agitators stopped. A continuous vent from the recovered monomer system ignited possibly due to lightening. Upon noticing the problem they set off the deluge system and left the building. Several problems existed at this point.
a. Once they left the building they didn't have any way of knowing what was going on and therefore what action should be taken to correct the problem. They are installing critical instruments in an outside bunker so they can observe the reactor conditions on a continuous basis even after an evacuation.
b. They had no way of snuffing out the fire from the recovery system vent line.
c. The situation was really complicated when after approximately 8 minutes they were able to.restart the reactors and then the pressure began to rise and 2 of the reactors ultimately released their contents to the atmosphere and discharged one-half of the vessels contents. Fortunately, the wind was
i 'i
R&S 140776
-13-
blowing these vented gases away from the fire on the recovery vent line and there were no serious problems as a result of the entire incident.
10. Overpressuring of a reactor by Olin. This incident involved a 2,2'QO" gaVlon kettle that had just been loaded. Since they don't have a continuous pressure recorder they don't know exactly how high the pressure got or exactly what happened. The first indication of a problem was monomer coming from the seal and shortly thereafter they heard the rupture disc (which was set at 160 psig) blow. When the operator got to the 4" manual vent valve the manhole gasket began to leak and the operator immediately set off the deluge system. The foreman then put on a Scott air pack and went back in the building and vented the reactor to the atmosphere. They think the reactor was charged and in the process of being heated up with the agitator off and then the operator started the agitator. Although he claims that he did not. They found 95* of the glass was spalled off of the inside of the vessel due to the over-pressurization. The vessel was saf^jtied with a 4" x 6" pop valve and a 4" frangible disc, but that was apparently not enough to completely relieve the pressure. Corrective action includes placing an automatic valve in the hot water line which will not open unless the agitator is on. They also have established a policy that an agitator cannot be started if it has been over looked in the original startup procedure. Discussion about this incident revealed that many different types of manhole gaskets are currently in use including lead, teflonrsolid lead, and neoprene. In addition 7 companies pressure test the reactors after opening the manway while 9 companies vacuum test after opening the manway. Six to 9 companies have had the "0" ring In the Lenopo quick opening manway blow out. One company has switched from the Lenope to a Tube Turn type with much better results.
11. - Opening the wrong reactor dump valve by Panasote. An operator . went down to the bottom floor and opened the dump valve on the wrong reactor. Half way through the dump he recognized the problem and closed the valve. The 0&W monomer detection system set off the deluge water system. They did not have any other warning devices to alert a man of this type of problem. Since that time they have installed a pressure device that prevents the bottom valve from being opened if the reactor is under any positive pressure. Discussion-revealed that 9 companies haVe*J some type of lock or fool-proof system to prevent this type of incident. Another 5 companies rely on lights and another TO companies rely on double valves beneath their reactors. No one gave any indication of problems with opening the wrong reactor manhole.
-14-
12. Explosion in a mass PVC plant in Europe. This incident involved a thermocouple well" coming out of the bottom of a reactor dumping"'.12 tons of VCM to the building. The deluge system came on but the vapor cloud exploded resulting in 4 or 5 fatalities. Although no one is certain exactly what caused the incident, it revolves
around some maintenance that was to have been done on the thermo couple wells before this run had been initiated. They think that the maintenance man removed the bolts and attempted to remove the thermocouple but it was stuck due to a resin formation. Then,
rather than reinsert the bolts it was forgotten, Two different pressure checks of the system before loading the reactor failed
to reveal the problem. The ignition is thought to have been provided by the control room or the monomer recovery system, both of which were not far away. The fatalities all occurred as the men were leaving the immediate area. Apparently they were caught in the advancing flame front. The feeling is that the men could have been saved if they had gone behind the blast walls for protection. Instead they just seemed to run away with no apparent plan as to where they were going. The major lessons to be gained from this incident include:
a. Maintenance procedures are extremely important and must be followed to the utmost detail.
b. Evacuation routes should be very well defined and should be . ' carried out on all drills on a frequent enough basis to
assure that people will follow them.
R&S 140777
c. Since the incident may have been caused by stud bolts holding the thermocouple well in place this type of bolting should be avoided if at all possible.
Further discussion with regard to Item c revealed that there are many problems with the conventional stud bolt in that resin can get into the threads preventing proper installation. It is recommended that in its place we use a bolt that is threaded on, both ends and rely on a nut and washer on the outside, which would be removed when removing the thermo well.
13. Explosion in a PVC silo in Europe. This explosion occurred in a large compartmented silo in a PVC compound plant. The silo capacity was several hundred tons. At the time one of the compartments was undergoing maintenance in the form of welding in a nqzzle in the top of the vessel while-the other compartments were in operation. During the course of the welding operation a flash fire or explosion occurred and flames came out of the top fatally burning a man who was working there. They believe
the first flash disturbed some dust (a fine dusty modifier that was being used) in the bag filter and this dust then resulted in a dust explosion and fire. They ruled out a VCM explosion because in the cold temperatures they would think there is not enough VCM present. Discussion at this point revealed that some companies are spot checking with L.E.L.'s in their PVC silos. While they do find VCM present it is not in the
----------- -
-15-
explosivc range. It was pointed out by several companies that stearates can cause dust explosions and they are very sensitive.
14. Explosion in a pipe by ICI. This was a very unusual incident where a man opened a water valve allowing water to rush into a section of contained slurry line. Since there was a sight glass in this line he was able to see an explosion or flash of fire and later inspection found the presence of carbon. The only thing that they can determine is that it was some sort of compression ignition. They have also had two other instances of this type. While they are just local reactions they are of considerable concern. It was suggested that it may have been the result of a water hammer affect or static in a teflon lined ball valve.
15. High pressure water lance fatality. Without revealing the source company I discussed the high pressure lance fatality that had
. occurred at Wyandotte as the result of a man being struck by a water spray from a high pressure lance. This has been covered
. in a separate letter.
16. General discussion on vessel entry. Due to the high safety incidence rate involved with vessel entry, the possible exposure of personnel to monomers, and the generally poor economics resulting from vessel entry, it was the general feeling that the industry needs to find some way to avoid having to enter vessels that have contained any type of monomers. There were some people present that felt this may be something that would be legislated while there were others that did not. The general feeling was that until we could come up with some system that would prevent the need to enter vessels we would have to continue to do it but would have to exercise extreme caution whenever this operation was undertaken.
R. L. Dostal 12/12/73
R&S 140778
i
Vinyl Chloride Safety Association Cleveland Ohio Meeting
October 24, 25 and 26, 1973
R&S 140779
Agenda
October 24
8:00 A.M. 9: 00 A.M. 9: 30 A.M.
Registration Business Meeting - Ray A'd. Ch.-iinn.-i'** Review of Industrywide Safety Guidelines P. Boget - Blend Tanks
IV, C. L, Rogers - Monomer Loading and Storage
R, Asti - Future Assignments
10: 00 A.M. 10; 15 A.M.
Coffee Reacton Entry (J. C. Palinsky - Universal PVC Resins,
11:00 A.M.
discussion leader) < Safety Valve Testing - (R. L. Frantz - Union Carbide,
discussion leader)
12:00 Noon Lunch
1: 00 P.M. Safety Valve Sizing - (W. J, Boyle - Monsanto and R. Fry -
* Diamond Shamrock, discussion leader)
* 2:00 P.M. Static Control
2: 30 P.M. Catalyst Handling - (R. Stack - PPG, discussion leader)
3: 15 P.M. 4: 00 P.M.
Pressure Vessel Obsolesence and Inspection O.S.H.A. Experience - (W, J7 Bradford - Olin, discussion lead
October 25
8:30 A.M. 9:15 A.M. 10:00 A.M. 10: 15 A.M. 11: 15 A.M. 12: 00 Noon 1: 00 P.M-.
Handling Monomer Leaks - (R, Dostal-Dofc*/, discussion leader) Safe Monomer Venting Coffee Noise Control (E. Schenke - Tennaco, discussion .leader) Monomer Exposure Standard - (P. liogart-Tcnnaco, discussion R Lunch Accidents and Near Misses - All
October 26
8: 30 A.M. 12: 00 Noon
Accidents and Near Misses, continued Adjourn
Attendees at October
iy73 Meeting
Cleveland, Ohio
_ Mr. J. T. Barr Mr. Earl Primeau Mr. Norm Brock Mr, M. M. Garrctson Mr. Harold Kling Mr. A. Godfried
Mr. Don Young Mr. J. A. Gray Mr. C. Arthur Gellner Mr. Suchochleb Mr. Earl Gremillion Mr. A. F. Gallagher Mr. R. E. Frey Mr. J. Robert Mehall - Mr. Eli Zinn Mr. Rob Dor.tal Mr. Larry Adcock Mr. Henry G. Smith Mr. Francis Koy Mr. Harlan Jewett Mr. Joe Mudd Mr. Claude Acree Mr. Harry Lloyd
Glen D. Schaef
Herman Waltemate Mr. Amos Dixon Mr. Mai Trowbridge Mr. Jphn C. Floros Mr, Brian D. Cole Mr, Maryin LeCornu Mr. D. B. Hopkinson Mr. J. R. Sanchez Mr. S. D. Law Mr. David L. Gendron Mr. H. L. Donaldson Mr. W. J. Bradford ' Mr. E. J. Goettman Mr. R. H. Carte Mr. Roy W. McCune Mr. K. K. Sheth Mr. Henry Rzcmpoluch Mr. William A. Keim Mr. Roy Stack Mr. Ray Asti Mr. I. W. Hager Mr. Don Miller Mr. P. Bogart
John T. Sweeney David A. Ellwood Jay E. Giffin
R. L. Frantz Mr. Walt M. Iliff Mr. Norman C. Walter Mr. Jack Palinsky Mr. Cal Rehfuss
Air Products and Chemicals, Inc.
Air Products and Chemicals, Inc.
Air Products and Chemicals, Inc.
Allied Chemical Corporation
American Chemical
Borden Chemical
Borden Chemical
B.P.C.I.
Certain-Teed Products Company
Conoco Chemicals.
Continental Oil Company
Continental Oil Company
Diamond Shamrock Chemical Company
Diamond Shamrock Chemical Company Diamond Shamrock Chemical Company
Dow Chemical Company Dow Chemical Ccsnpany
Ethyl Corporation
Firestone Plastics Company
General Tire General Tire
Georgia-Pacific
Georgia-Pacific
B. F. Goodrich
B. F. Goodrich
Goodyear
Goodyear Great American Chemical Corporation
Hooker Chemical Company
ICI, Ltd - England
ICI, Ltd - England
Industrias Resistol, S. A.
Keysor-Centuxy Corporation
Monsanto Chemical Company
Olin Corporation
Olin Corporation
Olin Corporation (Assonet, Mass.)
Olin Corporation (Assonet, Mass.)
Pantasote Company
Pantasote Company
Pantasote Company
Pittsburgh Plate-Glass
-
Pittsburgh Plate Glass
Stauffer Chemical Company
Stauffer Chemical Company
Shell Chemical Company
Tenneco Chemicals
Tenneco Chemicals Union Carbide (So. Charles, W. Va.)
Union Carbide (So. Charles, W. Va.)
Union Carbide
Uniroyal, Inc.
Uniroyal, Inc.
Universal FVC Resins, Inc,
Universal PVG Refllna, Inc,
8/.0fr
S3o3
03
VINYL CHLORIDE SAFETY ASSOCIATION
Atr Products Mr. John T, Barr Technical Manager 5 Executive Mall Swedesford Rd. Wayne, Pa. 19087 215-687-6150
Allied Chemical Corp. Mr. D. L. Magee Gulf States Rd., Box 271 Baton Rough, La. 70821 504-356-3341
American Chemical Corp. Mr. Harold E. Kling Plant Manager P. 0. Box 9347 Long Beach, Calif. 90810 '213-834-8571
Atlantic Tubing and Rubber Co. Mr. E. T. Biehl Mill Street Cranston 5, R.X. 401-941-9200
Borden Chemical Mr. Sherwood J. Moll Supervising Engineer 511 Lancaster Street Leominster, Mass. 01453 617-537-1711
BP Chemicals International Ltd. Iain Steel, Production Manager Devonshire House Mayfair Place Piccadilly, London W1X6AY
Certain-Teed Products Mr. C. A. Gcllner Valley Forge, Pa. 19481 215-687-5000
/jdiucL
Conoco Mr. R. J. Freele Park 80 Plaza East Saddle Brook, New Jersey 201-845-3800
07662
R&S 140781
Diamond Shamrock Mr. Harold E. Birr PVC Plant Manager c/o River Road Delaware City, Delaware 19706 302-834-4561
Dow Chemical Co. Mr. Larry Adcock Oryster Creek Division P. O. Box BB Freeport, Texas 77541 713-233-6381
Ethyl Corporation Mr. H. G. Smith Operations Supt. PVC P. 0. Box 341 Baton Rough, La. 70821 j 504-357-4361
Firestone Plastics Co. Mr. Fran Hoy. Coordinator, Special Projects P. 0. Box 690 Potts town. Pa.
215-326-2000
General Tire & Rubber Corp. Mr. J. Mudd . P. O. Box 68 Middle Road Ashtabula, Ohio 44004 216-998-1120
B. F. Goodrich Co. Mr. Herman Waltemate Process Engineer, Manufacturing 6100 Oak Tree Blvd. Cleveland, Ohio 44115*' * 216-524-0200
Georgia Pacific
Mr. Harry Lloyd, Industrial Relations
P. 0. Box 629
1V
Plaquemine, La. 70764
-
504-687-6321
I
Goodyear Tire & Rubber Co. Mr. M. Trowbridge 5408 Baker Avenue Niagara Falls, New York 14302 716-283-7682
Great American Chemical Corp, Mr. J. C. Flores V.P. of Manufacturing 650 Water Street Fitchburg, Mass. 01420 617-343-6973
Gulf Oil of Canada Mr. R. S. McLaren Mgr. Operations Resin & Compounding P. 0. Box 330 Shawinigan, Quebec, Canada
Hooker Chemical Mr. H. Raster Plant Manager P. 0. Box 456 Burlington, New Jersey 08016 609-499-2300
1
Imperial Chemical Industries, Ltd, ^lr. J. S. Seeker, Works Manager Ilillhouse Works P.0. Box 3 Cleveleys Blackpool Lancs FY5 4QB England
Industrias Resistol, S.A. Mr. J. R. Sanchez Chief Production Engineer Presidente Masaryk N 61 Mexico 5, F.. F.
Keysor-Century Corporation , Mr. H. R. Jepsen, Jr.
26000 Springfirook Road Saugus, California 91350
*
Monsanto Mr. David L. Gendron Production Supervisor 730 Worehester St. Indian Orchard, Mass. 01051 412-788-6911
Montedison Mr. Mario Ghezzi Halogens Improvement Manager Casella Postale Milano 3596 Via Principe Eugenio, 5-20100 Milan, Italy
R&S 140782
Norsk Hydro, A.S. Mr. Per Rangnes Asst. Prod. Mgr. Plastics Div. Porsgrunn'Fabrikker 3901 Porsgrunn, Norway
Olin Corporation Mr. E. Goettman P. 0. Box 317 Assonet, Mass. 02702 617-678-4591
Pantasote Company Mr. II. Rzcmpoluch Plant Manager P. 0. Box 356 Point Pleasant, West V. 25550 304-675-1020
PPG Industries Mr. R. Stack 1 Gateway Center Pittsburgh, Pa. 15222 412-434-3131
Promociones Indus triales Mexicanas,S.S Mr..Pablo Enriquez .Apartado Postal Num. 604 Puebla, Pue.., Mexico 2920 ------- *-----
Robin Tech. Inc. Mr. John Erfel P. 0. Box 2342 Fort Worth, Texas 76101
. '.
*
#
Shell Chemical Company Mr. D. G. Miller Houston Plant P. 0. Box 2633 Dccrpark, Texas 77536 713-479-2331
Stauffer Chemical Company
Mr. R. A. Asti
P. 0. Box 320
Delaware City, DE 19706
302-834-7846
,
Tenneco Chemicals Mr. P. L. Bogart P. 0. Box 129 River Road Flemington, New Jersey 08822 201-782-4011
Union Carbide Company Mr. R. Frantz P. 0. Box 471 Texas City, Texas 77590 713-479-2300
Uniroyal, Inc. Walter Iliff P. 0. Box 460 Painesville, Ohio 216-357-7574
44077
Universal PVC Resins, Inc. J. C. Palin ky Safety Supervisor 786 Hardy Road Painesville, Ohio 44077 216-352-6241
, \
.. \
/
,4
'
'. .
. * ~
.' *
` . .
R&S 140783
Please add any additions/changes or new members.
Name of Co.: Name:- . Title: "Address:
_ *"
....
~ '
. Phone:
Mail to:
Mr. P, L. Bogart, Tenneco Chemicals P. 0. Box 129, River Rd. Fleraington, N.J-. 08822
BLEND TANKS
/lirUc^ ir V
R&S 140784
Definition:
A "Blond Tank" is defined as a vessel utilized to contain resin slurry prior to drying. Such tanks may also be referred to as "Slurry Tank" or "Holding Tank".
Type:
Blend tanks are normally non-pressure vessels equipped with power-driven agitators. (Slurry is retained under agitation.)
Hazard:
The primary hazard connected with blend tanks is associated with the unreacted monomer carried within the slurry after stripping.' This in turn comprises two areas of concern:
I. Explosibility
,
II. Toxicity
.' .
i
Suggested methods of control for each catgory include:
.
I. 1EX-P- LOS'-I-B- 1ILITY
< 1; !
A. Insure that vapors within the blend tank do not enter the explosive
range,
.*
*
B. Prevent any source of ignition within the'Ttank.
(Note: While either of these steps taken alone should theoretically suffici experience has shown that a combination of both objectives is required.)
-A-l. v
Maintain vapors constantly above the U.E.L. (upper explosive limit). Filling and emptying of the tank, varying monomer contents of the slurry, and varying rates of monomer release under agitation makes thisapproach impractical.
NOT RECOMMENDED.
A-2. Maintain vapors constantly below the L.E.L. (lower explosive limit). This may be accomplished by controlling the amount of
unreacted monomer carryover, or dilution of vapor within the tank.
Preliminary indications are that the percentage of unreacted monoraep carried over is greater than has heretofor been recognized, tln'til more efficient methods of stripping are ,* developed and implemented, control of monomer quantity cannot be depended upon to achieve vapor-air mixtures below-L.E.L.
I
Dilution with air, introduced at atmospheric and exhausted
mechanically; introduced mechanically or by pressure and
exhausted at atmospheric; or introduced and exhausted at
atmospheric ("open-hatch" method), is the most common current
practice and has been thought for many years to be a
satisfactory precaution. There is, however, serious question
as to Whether introducing air into the vapor space may not
actually increase the hazard by diluting the vapor below the
U.E.L. There is also the problem of insuring that all the
vapor space is sufficiently diluted.
*
RECOMMENDED WITH RESERVATIONS
Should the air-dilution method be chosen, the following precautions are suggested:
- Introduce a sufficient supply of air,-at a constant rate, to fully dilute the entire vapor space, regardless of slurry level, to below L.E.L.
Insure the reliability of air supply, including power supply to blowers .or exhausters.
- Design air introduction or exhaust so that sufficient velocity is maintained to insure dilution. Do not rely upon natural draft.
- Monitor the vapor space for monomer content.
- Connect the monitor to an alarm and develop procedures to be followed if monomer content exceeds L.E.L.
A-3. Inert the atmosphere of the vapor space
. Maintaining an inert atmosphere in the entire tank vapor
space effectively precludes ignition of vapors. This can
be accomplished by introduction into the tank of an inert
gas in sufficient quantity, at a controlled continuous rate,
to preclude the presence of sufficient O2 to sustain
ignition. It should be understood that introduction of
inert gas does no t preclude the presence of monomer in the
~vapor space.
-
*
-
'
*
RECOMMENDED.
3] fio
C/7
00-0n10bI
Where inerting is used, the following suggestions are made:
- Nitrogen is the preferred inerting agent. Use of 00 usually involves an incrt-gas-gencrator, which can caused
. safety problems of its own.
- Insure a sufficient supply of inert gas, introduced at * a rate which will suffice to inert the entire vapor space
at all times regardless of slurry level.
- Monitor the nitrogen flow by the use of flowmeters or similar devices.
- Check O2 level in the tanks by. means of continuous-reading or frequent intermittent reading monitors. Such monitors should be programmed to give an alarm should the 02 content approach unacceptable levels, and should prcfcrrably be designed to automatically increase N2 flow when such a condition occurs.
- It is recommended that the O2 level in the tank not be
' permitted to exceed 8%.
.'
*
B-l. Ignition prevention
#
In order to prevent ignition of monpmer vapors in, and associated with, blend tank operations, the following precautions are suggested;
* The blend tank area should be treated as part of the monomer train and all precautions taken in the reactor area should be applied here as well. These include, but are not limited to:
Class I, Group D, Div. I electrical equipment; No smoking, flames or open lights; Hazardous work (hot wo^k) permit required.
- Where tank vents are provided, they should be equipped with flame arrestors, and in the case of inerted tanks, conservation vents.
... -
-
--
m, _
- Vent discharge, even on inerted .tanks-should be reraoted
from ignition sources.
R&S 140786
t
- Potential friction points, such as agitator shaft bearings, should be evaluated and precautions against static generation and friction heating, under both normal and abnormal conditions, taken.
Examples:
Use of soft metal collars at point of entry of agitator shaft through tank top. Use of mis-alignraent sensing switches on shafts, etc.
II. TOXICITY
The second area of hazard which must bo considered with blend tanks is exposure to the anesthetic effects of monomar. This conn idem tion is of course not exclusive to blend tanks, but assumes particular significance because of the tendency to regard blend tanks as beyond the monomer area.
Operations:
The primary area of exposure is the roof hatches, or manways.. These hatches are opened to check levels in the tank, to check the condition of the tank interior, and to wash out the tank.
Elimination of the necessity to perform these*'tasks through the hatch in turn eliminates most of the monomer exposure.
It is recommended that:
.
- Operating procedures be so developed as to obviate the '' necessity for personnel to go on or across the tops of
blend tanks.
- Hatches and manways be closed and sealed with a frangible seal, such as a railcar seal.
. - Tank levels be determined by the use of remote-reading level gauges.
- Washout be accomplished by the use of remote-operated fixed or
rotating nozzles within the tank.
*
- Agitator motor switches and any other operating devices be located at ground *level.
J
R&S 140787
t
Maintenance;
*A -'
\
Whence is necessary to go on top of a blend tank, to inspect, or perform maintenance, the buddy system should be strictly enforced.
When entering a blend tank, all confined space entry procedures shall be followed.
r &S 140788
R&S 140789
V
THE SOCIETY OF THE PLASTICS INDUSTRY. INC.
250 PARK AVENUE NEW YORK. NEW YORK 10017 212/667-2675
The Society of the Plastics Industry, Inc. SUGGESTED RELATIVE HAZARD CLASSIFICATION OF ORGANIC PEROXIDES BY
ORGANIC PEROXIDE PRODUCERS SAFETY- DIVISION FOR
USERS AND VENDORS OF ORGANIC PEROXIDES
11/72
THE SOCIETY OF THE PLASTICS INDUSTRY, INC. SUGGESTED RELATIVE HAZARD CLASSIFICATION
OF ORGANIC PEROXIDES
The Organic Peroxide Producers Safety Division of SPI . classification system is designed to evaluate the effects of a number of factors likely to be encountered in shipping or storing organic peroxides: heating at various rates under partial confinement, long term storage at various ambient temperatures, mechanical shock, explosive shock and direct application of flame.
The following tests have been used to classify organic peroxides by the OPPSD system. Details of each test method are described in separate write-ups.
*
Pressure Vessel Test (PVT)
The rate and energy of thermal decomposition of peroxygen compositions are measured under conditions of rapid heating and partial confinement.
Rapid Heat Test
The type of decomposition that occurs to peroxygen com positions is determined under condltioiTs of moderately rapid heating.in a test tube.
Self-Accelerating Decomposition Temperature Test'(SADT Test)
Susceptibility to Decomposition
The lowest ambient oven temperature at which a peroxygen composition in its largest commercial package will undergo self-accelerating decomposition is established.
Damage Potential
The severity of such decomposition is also determined by damage to the container, oven, etc.
Impact Sensitivity
'`
The susceptibility of a peroxygen composition to under go decomposition upon being struck by a falling weight is measured.
Modified Trauzl Block Test
' This test measures the energy released by a peroxygen composition when initiated by an explosive force (blasting
cap).
R&S 140790
V
/-
-2-
...
Burnt nr. Test
1i This test determines the flame height that results.by burning a specified quantity of a peroxygen composition.
/
Results for each test are divided Into three hazard ratings:
3 - Maximum Hazard 2 - Intermediate Hazard 1 - Low Hazard
The numerical results from the seven test categories are totaled to arrive at the final classification.
The classes are: Code Word
Numerical Range Total of 7 Tests
Suggested Maximum Gross
Wt. Limit
Class I
Danger
15-21
Subject to
Class II Class III
Warning Caution
11-14 8-10
Test by Competent
Class IV
No Code Word Unregulated
7
Authority
Other chemical, physical and physiological characteristics such as flammability, toxicity, corrosivity, and special conditions for refrigerated storage and shipment are not included in this main classification system, but form the basis for additional labeling requirements.
R&S 140791
1/72
PROPOSED LIMITS
Test _____
Numerical Rating . ______________________
Results . Vent Diameter (mm)
Pressure Vessel Test (PVT)
3 2 1
20-14 <14-1.0 <1.0
Force of Decomposition
Rapid Heat Test
3.
Rapid - equal or great er than t-butyl peracetate in benzene
2 Moderate
1 Mild
Force of Decomposition
Self Accelerating 'Decomposition Tem perature (SADT)
3
Rapid Decomposition (Considerable Damage to test oven)
2 Moderate Decomposition * (Considerable damage to
container and possible - r slight damage to test
oven)
1 Mild Decomposition (No damage to oven and some or no damage to container
R&S 140792
SADT
Temperature
oo
(/)
3
<10C
^
2
10-49C
troo
1 >49c
- Impact Sensitivity1
3
Height - *'-*' <10 cm.
* ---------
2 10-25 cm. 1 >25 cm.
11/72
R&S 140793
Proposed Limits Cont'd
Test
Numerical Rating
Modified Trauzl Burning Test2
3 2 1
3 2. 1
Results Expansion (ml.)
60-35 <35-15 <15 Flame Height >152 cm. . 152-91 cm. <91 cm.
Applies to solids and pastes. Liquid peroxides with x shock sensitivity of less than 25 cm. are not classi
fied under this system.
2 If a product burns very vigorously. It Is given maximum hazard rating even If the flame height is less than' 152 cm.
EXAMPLES OP CLASSIFIilfOKS FOR ORQAKIC PEr.OXILES
Test Result \
Product*
Rapid PVT Heat
Lauroyl Peroxide
Decanoyl Peroxide
Benzovl Peroxide (Dry)
70^ Benzoyl Peroxide (Wet)
Di-t-butyl Peroxide
trButyl Hydroperoxide 7
(with approx. 20*6 MB)
t-Butyl Hydroperoxide 7
(with approx. 30j water)
75^ t-Butyl Peracetate in OMS
75^ t-Butyl Peracetate in
Benzene
t-Butyl Perbenzoate
t-Butyl Peroctoate
An 85^ Cyclohexanone Peroxide
A 60* KEEP
IPP
A nan-regulated 60}C MEKP
50^ BPO in TCP
50^ BPO Pire Retardant Paste;
25^ Acetyl Peroxide in DMP
50^ 2,4-Dichlorobenzoyl Per
oxide in Silicone Fluid
50^ Benzoyl Peroxide in
Silicone Fluid
50^ Benzoyl Peroxide in
Plasticizer (Paste)
55Jf Benzoyl Peroxide in
t
Plasticizer (Paste)
1
2 2 3 2 1 2
1
2 2
2 2 2 2 2 1 2 1 2 1
1
1
1
2 2 3 2 1 1
1
2 3
2 2 2 1 2 1 2 1 3 2
2
2
-2
SADT (Decomp.)
1 1 3 2 1 2
1
3 -3
2 2 2 2 2 1 1 1 (. 3 1
1
1
1
SADT (Temp.)
Impact
Trauzl
1 11
2 11
1
__________ 2__________
2
1 1 1
1 12
1 12
1 11
11 1 '1
11 2 1
1. 2
1 .1 32 11 11 11 21 1 ; 1.
2 3
2 2 2 2 3 1 1 1 1 1
1 11
1 11
1 11
Peroxides by various manufacturers may have different test results and different classifications.
|
S9U
Burning Test --- (Plane
Hcigr.t)
Total Points
19 1 10 3 18 1 10
29 1 10
17
2 13 2 15
2 12
2 13 2 13 2 11 3 17 17 19 17 2 14 1 8'
18
18
18
i*. .
SUMMARY
VINYL CHLORIDE TANK CAR DERAILMENT l'ort Wayne, Indiana - July 20, 1973
For your perusal; we have prepared the following compilation on the vinyl chloride tank car derailment. Data was obtained from newspaper articles appearing in the "The New-Sentinel", July 21, 1973, Fort Wayne, Indiana; "The Journal-Gazette", July 21, 1973, Fort Wayne, Indiana; and from a report issued by 0. C, Johnston, July 25, 1973.
At 3:40 p.m. on Friday, July 20, 1973, 13 railroad cars of a 123-car Penn Central train derailed one-half mile from the west city limits of Fort Wayne, Indiana. Four of the derailed cars contained vinyl chloride being shipped from the Calvert City, Kentucky plant to Hooker Chemical Company in Stevens, New Jersey.
According to authorities at the scene, one of the vinyl chloride tank cars was punctured and caught fire in the initial impact. A box car of wood shingles also derailed and ignited in the initial derailment. A second tank car derailed and imbedded Itself in the burning box car. The other two tank cars were on their sides, off the track, but did not vent or burn.
Authorities stated that some 3,000 to 5,000 residents in a two-square mile
area surrounding the scene were evacuated at 6:00 p.m. when it became evident the
second tank car might explode. The pressure relief device on this tank car was
releasing and the time between releases was diminishing. The car exploded at
7:20 p.m.
^
One home, one-quarter mile from the scene, burned to the ground following the explosion, when the end of the tank car shot into the residence;.and the porch of another home was sheared off. Fortunately, there were no injuries reported.
Penn Central officials notified CHEMTREC of the derailment at 5:35 p.m. The contents of the chemical cars was unknown for at least one-hour. The bills of lading were in the caboose but could not be reached at first, due to the proximity of the fire. The Calvert City plant was then contacted and confirmation made that the material was BFG's vinyl chloride.
Gene Phillips and Oran Johnston (Calvert City's CHEMTREC Team) were dispatched from the plant to the scene. Upon their arrival they were escorted directly to the derailment site and found the following: two tank cars coupled together and lying on their sides, both were cool with no leaks; another tank car on its side at a sloping angle, punctured in the initial derailment and burning; and two-hopper-eo-rsy two box cars, anil a piggy back flat that had also derailed. The team was advised that a fourth tank car had exploded and burned itself out.
After surveying the situation, the Goodrich team advised the fire chief to allow the burning vinyl car to burn itself out so escaping vapors did not saturate the area, re-ignite, and flash back.
-2-
A decision was then made to allow the evacuees to return to their homes, with the exception of those living in the immediate area. This decision was based on the likelihood that when the liquid was completely vaporized and the cor pressure gone, there might be a flash back into the car, drawing in oxygen, and could result in an explosion.
To accelerate the burn off, the tank shell was warmed up with ambient temperature fire water. The tank shell had a heavy frost line at the liquid level, 4-6F., in comparison to the fire water at 60-70F. The warm water increased vaporization, accelerated the burn, and shortened the time required for burn off. The other derailed cars were retrucked and moved away. Penn Central brought two tank cars full of water and spotted them. Water was pumped from these cars which were continuously filled from a hydrant one-half mile away
Early Monday morning the fire died down. After checking the frost line of the liquid on the exterior of the car, it was found to be down to approximately 150-200 gallons of liquid. The decreased surface of liquid reduced the amount of vaporization and the rate of burn. The water was cut off and after two hours the car was examined again; no frost line was found, indicating the liquid was gone and only the vapor remained.
At this point, not knowing what would happen in the final burn out with the loss of pressure, it was decided to snuff the flame. Two fire hoses were tied and aimed directly at the fire. One fireman started the pump and the fire was snuffed at 11:15 a.m. (Monday, July 23, 1973), Water was continued for some twenty minutes and then one hose was shut down and a twenty foot section of 1-1/2" pipe was attached to it. The pipe was inserted into the car through the puncture, which was only 3" in diameter. The water on this hose was turned on again, flooding the car.
The adjacent area was then checked with explosimeters and found safe. The car was completely filled with water and monitoring of the area continued. At this point'the Calvert City Team was released. The situation was well under control and their services were no longer needed. They left the scene at approximately 12:00 a.m., Monday, July 23, 1973.
HW/kats
Attachments
cd: Plant Managers
Plant Safety Engineers Safety Council T. H. Smith R. A. Kelley R, C, Johns
V.-V * //' /: ff
H, Waltemate
fJ
R&S 140796
R&S 140798