Document LJ7pmBo1Ln6ymV3k5oMQpZoj3

Inspection Entry Date/Time Inspection Exit Date/Time Weather Media Statute(s)/Program(s) Type of Inspection EPA Region 10 Enforcement and Compliance Assurance Division INSPECTION REPORT 02/16/2023 11:30 AM (PT) Announced: No 02/16/2023 12:30 PM (PT) Access: Granted Sunny, 45F Water Clean Water Act, NPDES, Industrial Industrial Stormwater Inspection Permittee Name Site Name Site Physical Address City, State, Zip Code County Facility GPS Coordinates Mailing Address City, State, Zip Code Interstate Concrete and Asphalt Interstate Concrete and Asphalt - Prosser Facility 2500 SR 221 Prosser, WA 99350 Benton 46.2069091796875, -119.738960266113 P.O. Box 3366 Spokane, Washington 99220-3366 FRS ID Permit Number NAICS WAT4839378716 WAG507221 327320 - Ready-Mix Concrete Manufacturing 327390 - Other Concrete Product Manufacturing Lead Inspector: RAYMOND ANDREWS Date: 2023.04.11 07:26:22 -07'00' Digitally signed by RAYMOND ANDREWS Raymond Andrews EPA Region 10 andrews.raymond@epa.gov (206) 553-4252 Supervisor Review: PETER CONTRERAS Date: 2023.04.11 09:55:53 -07'00' Digitally signed by PETER CONTRERAS Peter Contreras EPA Region 10 contreras.peter@epa.gov (206) 553-6708 Page 1 of 5 SECTION I - INTRODUCTION Interstate Concrete and Asphalt - Prosser Facility WAG507221 Site Entry and Inspection Objectives I arrived at the Interstate Concrete and Asphalt - Prosser site ("Site" or "Facility") for an unannounced industrial stormwater inspection. I presented my inspector credentials to Jana McDonald and informed her I was there to determine compliance with the Clean Water Act (CWA) and the Washington Department of Ecology's (WDOE) Sand and Gravel General Permit. This report is based on information and documentation supplied by Interstate Concrete and Asphalt and direct observations made during the inspection. In addition, information gathered prior to or after the inspection from a review of EPA, State, and/or public records may be included in this report. Attendees Organization Attendee Name Title Present in Present in Opening Conf. Closing Conf. EPA Region 10 Raymond Andrews Lead Inspector Yes Yes CRH Americas Jana McDonald Environmental Manager Yes Yes Materials, Inc CRH Americas Kelby Johnson Ready Mix General Yes Yes Materials, Inc Manager CRH Americas Jimmie Roper Ready Mix Site Yes Yes Materials, Inc Superintendent Site Information Responsible Official What is the principal product generated? Type of Operation What are the raw materials used? Size of Facility Outfalls Mike McBreen, Vice President, michael.mcbreen@na.crh.com Concrete is the only product generated at the Prosser facility. Concrete Batch Plant Sand and Gravel 2.6 acres There are no outfalls identified in the Site Management Plan or the Site map; however, there is an outfall identified as G001 in the Notice of Intent. Page 2 of 5 SECTION II - OBSERVATIONS Interstate Concrete and Asphalt - Prosser Facility WAG507221 The Prosser site consists of two primary operations, the concrete batch plant and the truck washout. The concrete batch plant is solely to produce dry concrete. Equipment used on site includes feeders, conveyors, weigh hoppers, cement storage silos, and mixers. The stockpiled material (Photo 1) is transferred by frontend loader to the batch plant feeder. The sand and gravel go to a weigh hopper and then into the mixer truck drum. Cementitious products are pneumatically transferred from a tanker/delivery truck into a silo. It is transferred from the silo into the weigh hopper and then into the mixer drum. Concrete admixtures and petroleum products are stored inside the shop building. Photo 1/P1010591 - Stockpiles of Concrete Manufacturing Inputs The Prosser site also maintains a truck washout facility to clean the mixer trucks. The washout facility is on a concrete slab that drains to concrete lined settling ponds (Photo 2). Sediment settles out of the water which is then recycled for reuse. Sediment is removed from the ponds as needed. The washout also receives stormwater that falls nearby. Photo 2/P1010290 - Truck Washout Page 3 of 5 SECTION III - RECORDS REVIEW Interstate Concrete and Asphalt - Prosser Facility WAG507221 I reviewed the following documents: Notice of Intent (Renewal) - dated September 29, 2020 Site Management Plan (SMP) - dated October 15, 2018 SMP Site Map - dated September 2020 Discharge Monitoring Reports (DMRs) - February 2022 through January 2023 EPA's Integrated Compliance Information System - January 1, 2018 through February 28, 2023 Any issues found during Records Review are in the Areas of Concern. SECTION IV - AREAS OF CONCERN The presentation of Areas of Concern does not constitute a formal compliance determination or violation. AOC Reference #: RA1-RR-NT Records Review Regulation and/or Permit Requirement S5.D.2.a of the Permit states, in part, the site map must "assign a unique identifier up to four characters (e.g. S001, S002, etc.) to each outfall and monitoring point." AOC: The Prosser site map shows two stormwater monitoring points, labeled MP#1 and MP#2, but does not show an outfall point. The Notice of Intent Renewal Application, dated September 29, 2020, only shows one monitoring point, labeled MP1, and includes a discharge point/outfall, identified as G001. The Site Management Plan (SMP), dated October 15, 2018, identifies a single monitoring location, labeled MP1, and does not include a discharge point or outfall. AOC Reference #: RA1-RR-NT Records Review Regulation and/or Permit Requirement S5.D.2.b of the Permit states, the site map must "show the drainage area for each point." AOC: The Prosser site map did not show the drainage area for each monitoring point. AOC Reference #: RA1-RR-NT Records Review Regulation and/or Permit Requirement S5.D.2.d of the Permit states, the site map must "label whether the discharge is to surface water or groundwater." AOC: The site map did not label if stormwater discharges to surface water or groundwater. Page 4 of 5 SECTION V - CLOSING CONFERENCE Interstate Concrete and Asphalt - Prosser Facility WAG507221 I conducted a closing conference with Facility personnel at 12:30 PM. During the closing conference, I discussed observations made during the inspection. I informed the attendees my observations and Areas of Concern have not been evaluated for a formal compliance determination. SECTION VI - LIST OF APPENDICES 1. Photo Log Page 5 of 5 APPENDIX: PHOTO LOG P1010590 - Truck Washout P1010591 - Stockpiles of Concrete Manufacturing Inputs