Document KRYnVEwoBY77J4B4B2OBj3RG0

ENVIRONMENTAL COST BREAKDOWN CORPPS CHRISTI REFINERY .1. Perform Site Survey 2. Disposal of PCB's (Electrical Equipment) (Assume sane order of magnitude as Enid Refinery - $700,000) $700,000 x 3 3. Asbestos Disposal (Assume same order of magnitude as Enid Refinery - $50,000) $50,000 x 3 4. Disposal of Crude and Peed Tank Bottoms 200' Dia. Tank 3'deep 95,000 cu.ft. 95.000 " 3500 cu.yds. 27 3,500 cu.yds. x 8 tanks " 28,000 cu.yds. 28.000 x (150/yd for disposal) 5. Disposal of Lead Sludges from Leaded Gasoline Tanks (Assume 3 times Enid 17 x 3 - 51 tanks) 51 tanks x 5 yds/tank - 255 cu.yds. 255 x 150/yd. 6. Sandblast and Test leaded gasoline Storage Tanks for Dismantling (Enid cost $250,000 x 3 - $750,000 7. Clean-up Lead Contaminated Soils Enid cost $47,000 x 3 - $141,000 8 Heavy Oil Tank Sludges (Decant oil. No. 6 Oil) Heavy oil tanks will contain some tank bottoms that will be disposed of at the land farm. (Assume 2,000 bbl and 5 tanks " 10,000 bbls. Sapling and analysis $ 5,000 Hauling to land farm - $2/bbl 20,000 Placing on land farm 5.000 $30,000 $ 80,000 2,100,000 150.000 4,200,000 38,000 750.000 140.000 30,000 CH 009321 -1- 9. Dispose1 of Cokg Conramlnated Soil in West Plant Corpus coke fines concaln heavy metals particularly Vanadium which will require disposal as toxic wastes. Remove top of coke yard and sell as coke with no charge to project. Scrap top six inches of top soil and coke and dispose of at dump @ $150/cu.yd. 1000' x 500' x .5' - 250,000 cu.ft. 250.000 9,260 cu.yds. 27 say 10,000 cu.yds. x $150 m 10. Recovery of Hydrocarbons below Grade Enid costs estimated to be $4 MM net of credit for recovery $4 MM x 3 over 5 years 11. Cooling Hater Tower Sludges Assume 4" of sludge in 6 CWTs 75' x 100' x .33 x 6 - 14,850 cu.ft. - 550 cu.yds. 550 x 150 - $82,500 say $83,000 12. Disposal of CUT Construction Materials The wood and plastic materials are contaminated, i.e., chromium, perservatives etc., and would have to be disposed of at a controlled dump. 75* x 100' x 20' x 6 - 300,000 cu.ft. 3 300,000 x 11,000 cu.yds. x $150 13. Tend Land Farm Rototlll 4 times a Tear for 5 Yrs. Cost of equipment rental and operation $100/Day 5 days/quarter - 500 x 4 x 5 14. Rototilling Spills in Place Assume 30 spill areas rototlll 4 times a year in place one day/spill area - 30 x 4 x 100 15. Consulting Services and Testing 3 years 9 $100,000/yr - $300,000 2 years 9 $ 50,000/yr 100.000 $400,000 $ 1,500,000 12,000,000 83,000 1,650,000 10,000 12,000 300,000 Cjt 009322 -2- 16. Establish 4 "Borrow Pit" areas This site will need "clean" dirt for closure activities and backfill for the pond areas In both East and West Plants. Site will also need areas to dispose of concrete, brick, etc. Engineering survey $ 50,000 Strip and store top soil 20,000 Establish borrow pits 20,000 Operation covered In dlsmantlenent costs -- Fill, cover, and grade 40.000 $130,000 $ 130,000 17. Closing of Ponds (4 ponds) Assume pond bottoms will be non-hazardous. Lake bottoms will be removed by dredging and dewatered by aeration. 500' x 500' x 3' x 4 3,000,000 cu.ft. 3 MM cu.ft. 111,000 cu.yds. 27 Dredging 111,000 0 $10/yd - $1,110,000 Dewatering (aerate) @ $10/yd * 1,110,000 Landfarm 111,000 0 $12/yd 1,332,000 Back Fill ponds 500' x 500' x 10' 4 - 10 MM cu.ft. 10 MM " say 400,000 cu.yds. 27 400,000 0 $5/yd 2.000.000 $5,552,000 5,552,000 18. Land Farm Closure and.Post Closure As required by RCRA, the landfarm also will be closed and a 30-year post closure monitoring Instituted. The land mu3t never be sold. Enid estimated costs: Survey Closure Post Closure (30 yrs) $221,500 x 3 - $664,500 $ 20,000 81,500 120.000 $221,500 - TOTALS Say 665.000 $29,490,000 $30,000,000 Range $20 to $40 MM CH 009323 -3- Breakdown- of $27 MM S.D Costs for Eaat Plant Enid S.D. started Oct. 1, 1983, and continued through October 31, 1984. The booked cost was $9 MM. General breakdown is as follows: Electrical Power Fuel gas Abandonment costs (Tank and line cleaning SD of Units) Miscellaneous $ 1 MM 2 MM 5 Mi 1 MM $ 9 MM Enid had 8 operating units with contiguous offsite tankage and pipelines. Corpus has 17 operating units In the East Plant, has separate offsite areas, l.e., 90-91 area. Docks 1, 2, 3 and 6, PPG dock, S.W. dock, Deep Sea Terminal, and West Plant. Due to number of units and complexity of offsites a factor of 3 times Enid costs is considered in the ball park for factoring to Corpus. CH 009324