Document KJQv2aJpZmXQb2aK1qedd5L7w
ENGINEERING REPORT
PRELIMINARY APPRAISAL SEDIMENT TRANSPORT RELATIONS UPPER HUDSON RIVER
for New York State Department of Environmental Conservation Albany, New York
April 1976
INTERIM REPORT
MALCOLM PIRNIE, INC.
MOWS 049359
TABLE OF COtJTEN'
I
II III
IV V VI VII VIII
IX
GLOSSARY
SUIli'iARY
INTRODUCTION Purpose Study Area Scope
RIVER HYDROLOGY AND HYDRAULICS
RIVER SEDIMENTS Fort Edward Pool Deposits Tractive Forces Sediment Transport Total Suspended Solids Discharge Sedimentation in River Pools
RIVER SUSPENDED MATERIALS
PCS CONCENTRATIONS
RELATED CONSIDERATIONS
IMPLICATIONS CF PRELIMINARY APPRAISAL
NECESSARY DETAILED STUDIES . Field Investigations Engineering Studies Evaluation of Alternatives Environmental Assessment"
REFERENCES
MONS 049360
GLOSSARY
Terns which have specific usage in this report are:
O Sedinent - soil particles with grain sizes greater than 0.001 mm.
0 Suspended Sedinent - Sediment suspended in the river water column.
0 Suspended Materials - material other tnan sedinent suspended in the river water column including:
Coiiodial Clay - soil particles with grain sizes less than 0.001 mm., and
0 Other Material - organic materials of natural and waste product origin. A special case in the Upper Hudson is wood debris from logging and sawmill operations.
0 Bed Material - The mixture of sediment, coiiodial clay and other materials wnich comprise the river bed and banks.
0 Bed Load - The mixture of sediment, collocial clay and other materials moving on or near (within 4 inches) of the river bed. Measured witn a bed load sampler.
0 Total Suspended Solids - The mixture of suspended sediment, coiiodial clay and other material suspended in the river water column.
o Total Suspended Solids Discharge - The weight of total suspended solids passing a given point during a period of time, usually day or year.
0 Voltatile Solids - Determined by the volatilization of organic matter in the total suspended solids.
0 Fixed Solids - Determined by subtracting volatile solids from total suspended solids.
0 Sediment Transport - The capacity of the river to move suspended sediment and bed load. Expressed as a concentration, parts per million (ppm), or tons per day or year (T/d or T/yr). Does not include suspended materials (as defined).
ONS 0*9361
SUd.lARY
This report has two primary purposes: a. A preliminary appraisal of river sediment
transport phenomena and the movement of other suspended materials and tne related movement of PC3 in the Hudson River between Troy Dam and Bakers Falls at Hudson River n.y. b. Preparation of a study plan for required field investigations, evaluation of alternative remedial measures and selection of a recommenced program for further identification and ultimate resolution of PC3 contamination in the study area. Computations presented in t.iis report ace based in part upon readily available information. Important additional field measurements and laboratory analyses were performed for this study ar.d related studies of PC3 contamination by NY DEC, NY Cepartmenc of rieaitn, and USG3 personnel. Complete fielo and laboratory data are not yet available at tne time cf preparation c: this report. The movement of river materials including: sediments and other materials present in the river bed oc suspended in the civer water column,, has been examined using a sediment transport equation and by observation of the movement of river materials.
MOMS 049362
S-l
Tne application of sediment transport tneor / to the Hudson Rivet must consider several conditions: a. Relatively low values of sediment transport in the
River (less tnan 100-200 pom measured at 100 year flood discharges) caused by low natural sediment yields from the river basin and the trapping of sediment in the seven reservoirs on the river between Hadley, H.Y. anc 3ak'ers Falls, tne Sacandaga Reservoir upstream of Hudson Falls anc eignt river pools formed oy dams between Troy 3a,a and Baiters Falls. o. The presence of relatively large amounts of organic material in the river bed and river water column. Total suspended solids in the river with volatile solids contents of 40-percent and more have been measured at low and flood flows. In addition to the common organic materials of natural and waste product origins, the upper Hudson River contains sigificanc amounts of wood debris. Wood particle levels as high as 70-petcent have been measured i.n the pool deposits of the former Fort Edward Bara, c. River hydraulics and thus tne sediment transporting capability of tne river is controlled by the eight dams in the study reach.
HONS Qj,93t>3
5. Predicted sediment transport capability has teen confirmed by measurement ot' total suspended solids and river bed load at three river discharges wnicn were equal to the low-flow exceeded 55 percent of the time, a medium rivet flow w'nicn was about equal to the mean annual flood and a high flow equal to tne estimated 100-year recurrence interval in tne Fort Ldward area ana probably a soraewnat lower frequency at Trcv Dam.
6. The predicted mode of movement of sediment and ether materials in the river is that under low flows and moderate flood flows there will be a tendency for sediments and suspended materials brougnt into the river pools from tributary streams and upstream sources to deposit in the pools. Heavier particles will settle out in the upper reaches of the pools. Lignter particles will cend to travel farther downstream because tne river has a tendency to be deeper at the lower end and the lighter particles have a lower fall velocity therefore taxing a longer time to reacn tne river oea. At flood flows the transport-capacity of
' the river increases, materials which could not be transported through the pool (i.e. carrieo over the dam) at low flows and low velocities will nave a tendency to be resuspended and carried out of the pool.
MONS 049364
S-3
7. The predicted node of movement of sediment and other
materials was confirmed by calculations and measurement
in the Thompson Island pool. This is the one pool of
the eight below 3akers Falls where computation of
sediment transport is warranted at this time since detailed hydcaulic computations are availaole for tnis
reach.
8. Total suspended solids, volatile solids and bed load
and associated PC3 concentrations were measured chrougn
the study area at three river flows:
.sarcn 13, 1376
Q * 3,600 cfs,
flow equalled or exceeded 55* of time
.larch 29, 1976
Q 17,000 cfs, mean annual flood (approximate)
April 2, 1976
Q 39,300 cfs, 100-year flood (approximate)
Additional relevant data on tocal suspended solids ano
PC3 levels nave also be utilized. Measured suspended
sediment concentrations at tne low flow of 3,600 cfs
show essentially no sediment transport inco or out of
the Thompson Island pool. An estimated value of 1 ppm
suspended sediment is presumed to reflect movement of
very small particles not susceptible tb settlement,
measurements at 39,300 cfs show an inccease of 140
percent in suspended sediments througn the pool. Tnis
value is consistent with the concept of scour of materials previously deposited at low and medium flows.
HONS OA9365
S-4
Suspended materials show an increase with larger streamflow and a slight increase in concentration
through the pool reach. This result is consistent with the suspension or organic materials as river valocieies increase anJ tne river's ability to carry tnem more oc less incependently of the transport forces present. 9. Tneoretical analysis and measured total suspended solids, volatile solids and bed load demonstrate tnat sediment and othec materials in the bed c the Hudson River will be transported thrcuc'nt the study area and into the Estuary and streanflows exceeded aoout 13 'percent of the time during an average year. 10. PC3 has been measured both in the .river bed material and in the suspended sediment and the suspended htaterial in the river water column. Curing periods of suspended sediment and suspended material movement VC3 concentrations were measured ac levels up to 9 poo. 11. Based upon the foregoing measurements 'and neglecting transport of ?C3 at river flows less than t.hose occuring 10 percent of the time, 5,000 to 10,000 pounds of PC3 per year, on the average, are transported down the Hudson River at Waterford and into tne Hudson River Estuary.
HONS 049366
S-5
12. Assuming tnat there ace curcentl/ no significant
discharges of PC3 to the Upper Hudson River; sources of the PC3 being moved ate principally the river pools ' behind each dam celow Fort Edward and tne remnant pool deposits at the former Foct Edward Dam. 13. An immediate program of fielo investigations ana
technical studies related to river dredging and otner remedial measures is recommended ir. order to cefine present understanding of the magnitude and extent of
PC3 contamination in the study area and to demonstrate the feasioility and cost of dredging.
The recommended program has four principal areas:
o Field investigations
Control Surveys Bed material sampling River depth surveys o Engineering Studies
'
Evaluation of dredging techniques Spoil site studies Pilot dredging operation Pilot treatment of dredge water
o Alternative Evaluations Dredge/Treatment/Spoil vs%PC3 Removal Alternate programs, cost estimates, schedules Contract documents
MGNS 049367
s-s
o Environmental issessiaent 14. S proyram of oiological and water quality monitoring is
recommended in addition to the above program in order to verify river conditions and to monitor the future progress in river restoration.
HONS 049368 3-7
I i.'irROouc-i'iOi-i
Purpose This evaluation has two primary purposes: 1. A prel iminary appraisal o river sediment
transport phenomena as it relates to the PCS contaminated sediments of the Hudson River Setween Troy Dam anc Bakers Falls at Hudson Falls, N.V.
2. Preparation of a study plan for required field investigations and the evaluation of alternative remedial measures for resolution of the PCb contamination.
This preliminary appraisal is part of the required response oy DEC to the Interim Opinion and Order in tne hatter of Alleged Violations of Sections 17-0510, 17-0511 and 11-0503 of tne Environmental Conservation Law of the State of Mew 'fork by: General Electric Company, File Kc. 2333, dated Feoruary 9, 1976. Section III, Outstanding Remedial Issues (page 75) of the Interim Opinion anc Order states, in part:
"Other issues include: 1. The extent to which GE should be ordered to
rectify tne effects of its prior discharges, including whether any practicable anc environmentally safe metnou exists or can oe devised to remove ?CS's from the river bottom, and the expected duration anc extent of FC3 contamination if no remedial steps are taken;" Tnis apocaisal will aic in tnat determination.
1-1 MOMS 049369
Discussions nave also been held with DEC personnel in order to characterize related considerations affecting tne Hudson River PC3 problem.
Study Area Tne study area for this preliminary appraisal is the
reach of the Hudson River from Troy Dam (mile 151.5) to Bakers Falls at Hudson Falls, Hew yatk (mile 137.1); a distance of approximately forty-six miles.
The river at the U.3. Geological Survey stream gage at Green Island, just aocve Troy Dam and just below tne -outn of the .lohawk River, has a drainage area of 3,790 square miles. The aohawx River drains 3,456 square miles at Conoes which gives a net upper Hudson drainage area of 4,534 square miles at Troy Dam. The drainage area of me Hudson River at the State Route 197 bridge three miles downstream of Hudson Falls, New y0rk is 2,313 square miles.
Scope
~
Tnis preliminary appraisal nas been based upon:
1. A review of existing pertinent reports and data on
river cross sections, river hydrology, pnysical
characteristics of civec sediments and river water
quality data.
,
2. Additional field data acquiceo by: Dt)C personnel:
Dr. Thomas Zimmie of Rensselaer Polytechnic
Institute under contract to DEC; and U.S.
1-2 MUNS 049370
Geological Survey (USdS) personnel of tne Aloany
district office. nr. Thomas haddock, Jr., of the U3GS National Center, FSeston, Virginia nas oeen consulted on the sedimentation engineering aspects
of tnese evaluations. riis services were made
availacle through the NY State USGS cooperative
agreement. ,-.t . Koberc Forest, Chief Engineer,
Hudson River-3iacx .River Regulating District,
provided valuable cooperation during field data
collection periods.
Evaluation of sedi.ment movement in tiie study reach nas
been based upon several factors:
`
o Sediment movement experienced with the Fort Edward Dam removal
o Tractive forces o Sediment transport theory o Sedimentation in river pools o Past data on river total suspended solids o Special river measurements
Computations of sediment transport have been focused cn
the river reach between Thompson Island Dam (also known as
Crocker's Reef Dam), mile 135.5, and the State Route 137
bridge at Fort Edward, mile 193.1. There ate several
factors which warrant this approach:
o Detailed water surface computations are avaiiaoie for this reacn (Reference 1).
o Present data indicate this to be tne most highly PC3 contaminated reacn of tne river.
o This pool is continuing to receive contaminated sediments from tne former Fort Edward Dam pool
area just upstream.
1-3
HONS 049371
Soir.e physical data are available cn tne seven pools
o below Thompson Island Cam. Assumptions required to evaluate
sediment transport capabilities and tractive forces in these pools are suen that tnese computations are not warranted at this time. Past and recent sediment observations in tne seven pools provide a reasonable oasis for present evaluations.
MOMS 049372 ! 1-4
II. RIVER HYDP.JLCmIY A.ID HYDRAULICS
Hudson River low flow and flood flow cnacaccer i st i cj in
tne vicinity of Fort Edward, N.Y. were developed tor the
report on the "Investigation of Conditions Associated witn
the Removal of Fort Edward Dam, Fort Edward,
February
1975", (Reference 1). Strea.nflow relations used in tms
study have been based upon this report witn adjustment cor
increases in the river drainage area between Fort Edward and
Troy Dam.
.
Water surface profiles (river levels) were developed in
the above report for the reach of river from a point
approximately 3,000 feet upstream of Thompson Island Dai?.
(Crocker's Reef Dam in report) to tne foot of Bakers Falls.
Profiles were computed for the river low flow equaled or
exceeded 90 percent of the time (2,500 cubic feet per
second, cfs), the mean annual flood ( 20,500 cfs) , five-year
and 100-year recurrence interval floods (25,000 and 41,400 (
cfs) and the Hay 4, 1972 flood (35,300 cfs, estimated
30-year recurrence interval). River cross section data and
computed energy gradients and velocities for the above river
discharges are presented in the report.
Characteristics of the river downstream of Tnorapson
Island Dam were developed from DEC data on river cross
sections (Reference 2). Data on river pools are summarized
in Table 1.
QNS 049373
II-l
CHARACTERISTICS OF RIVER POOLS
Pool Troy Dam Lock 1 Lock 2 Lock 3 Lock 4 Lock 5 Lock 6 Thompson Island
River Rile at Dam 153.9 159.3 163.4 165.8 168.0 103.2 186.1
138.4
Pool Long th
miles 5.4 4.1 2.4 1.7
15.2 2.9 2.3
5.2
Area acres
530 390 250 350 1,160 225 100
380
Average Width, feet
Average
Depth,
Volume
feet acre-f t mil gal
Drainage Area,
so mi
700
14
7,400
2,400
8,090
850
10
4,000
1,300
4,600
800
9 2,400
700 4,500
1100
9
3,300
1,100
4,400
600 12 14,100 4,600 3,700
650 13 2,900 940 2,900
600 9 940 305 2,930
550
12
4,400
1,400
2,920
SNOW
III. RIVER SEOZ.ic.NrS
Development of the Hudson River for water power and navigation in the early 1300's converted all out approx imately 4 miles of tne relatively steep stream reacnes and waterfalls in the study area into a series of eignt pools benind dams between Troy Dam and Fort Edward, a oistance of acout 40 miles. Tnese pools have typical depens of 10 to 20 feet and typical widths of 600 to 1,000 feet. From Fort Edward to Hadley, N.Y. seven additional dams varying in height from aoout 10 to 80 feet create additional Hudson River Pools. Sacanuaga Reservoir is a large reservoir near the r.iouth of a principal tributary of the Hudson near Heuley.
The average annual sediment discharge passing 3a.<ers Falls is on tne order of 40,000 to 50,000 tons per year based upon DEC water quality observations of total suspended solids at Fenimoce 3ridge, Hudson Falls (2,800 sc mi).*^
This is equivalent to 15 to 20 tons per square mile per year (T/sq mi/yr).
(1) lscimate is~3asea upon ooseTveu relation oeeweerf iixec suspended solids and stream flow. Fixed suspended solids - Total suspended solids - volatile suspended solids. Volatile suspended solids approximate tne natural and waste pcoduct organic naterials in tne river.
I1I-1
HONS 0493 75
As a comparison, tne Delaware River at Trenton, .lew Jersey (6,780 sq mi) has a measured suspended load ot 150 T/sq ni/yr.^ ^
Sediment transport through tne study area, therefore, has a relatively low value. This results from the low values of natural sediment yield from tne river basin and tile tendency for the river pools above Fort Edward to trap sedimen ts. Fort Edward Pool Deposits
A striking example of the limited sediment carrying capacity of the Tnompscn Island Pool below Fort Edward was observed subsequent to tne removal cf tiie Fort Edward Cam in tne summer of 1973. As reported in the previously referenced study (Reference 1), approximately 850,300 cuoic yards of deposits were scoured from tne former pool curing July 1973 - July 1974. 775,000 cubic yards of this material was deposited between the dam site and the Champlain Canal below Foct Edward. This deposited material was removed and deposited in spoil areas on the west bank of tne river. The difference in scoured material and in deposited material is due in part to transport of sediment ana otner suspenaeu material down the river.
(1) as reported in Reference 5, page 76.
III-2
HONS 049376
Anotnec interesting feature of tne pool deposits is tno large volume of wood oeoris present. Tests indicated tnat the amount of wood varied from 9 co 72 percent based on dr/ weight of coring samples. The wood aeoris consists of logs, wood slacs and chips and sawdust; all waste products of tne once flourisning AdirondacK lumDering industr/. The relevance to the present concern over ?C3 transport is the fact that much of the material subject to movement from tne former Pert Edward pool to the .Thompson Island Pool, ana in other portions of the river, have transport and settling characteristcs different from natural sediments.
Tractive Forces
..
Water flowing over the stream bed exerts a shearing
stress or tractive force. The ability of tne stream cea co
resist tne tractive force depends upon the grain size
distribution of tne bed sediments and the cohesive forces
which may exist due to the presence of silt or clay
particles.
Tractive forces experienced in the T.nompson lalanc Pool
have been computed for three flow conditions. Results of the
analysis ace presented in Table 2.
Median grain sizes for river bed sediments vary from *
0.2 to 0.7 mm as measured at five pool locations from 3a<ers
Falls to Waterford. The tractive force which would caust
MONS 049377 III-3
:/ i.r.n ?. Tl ^C'l l Vi. ) Of Cl
l,t ot ion< 1)
liiver ai lc
1530U 19:00 IfiiiOO 3 20
111.9.9
sot ilnrat ion 1 ov* 1 1 OVi
^=2, 91)0 els
V 0.33 o. <io i. ft 3 0.-17
T 0.0007 n.nnon 0.0 01! 5 (i. om
ik on /`iiniKil K] ooc<
(=70 , ^Ct) cl n
VY 1.5 0.01 2. o 0.04 3.0 0.0 5 2. 0.035
1 OO-yi-at n no.'
.'=.11 , -1P0 etc
vv
7.3 0.0.7 4. A 0.1)0 A.r, O.P.o
1.3 0.0I1
(1)
stations lor r jv-:i cross s;ct ionsi trow Ufelorcnco 1
v - it-c-tto cIkii.iioI velocity, I t/soc
T - trs-.r. livt: lurro ci.!! ut i ,i rt
ruct ion 11 o.<. nv. r;-.u-
ciiMiiii'l Hi..' tii, velocity ;iih! cpcr.jy 'ii<u!i< ut livi.-o
in (;! 1.1 c c. in.'-
l;./n tt.
MONS 0 4 9 3 7 8
movement of conesionless sediments with these sites is
approximately 0.004 to 0.003 lb/sc.ft
Critical near,
water velocities for these grain sizes (sufficient to move the bed sediments) are 0.5 to 0.7 ft/sec.
This tractive force analysis, although approximate and
based upon limited information, snows tnat river forces are
sufficient to move observed bed materials at flows exceeuing
low flows. analysis.
This finding is consistent with subsequent
Sediment Transport
Sediment transport capabilities of tne Thompson Island
Pool have been estimated by use of the .ladaock sediment
transport function (Reference 4). Values were computed for
the upper pool section at the State Route 197 bridge
(Station 43920) and at tne lower pool section near the
Thompson Island Oam (Station 15300). Channel hydraulic
characteristics for these sections were taken from
Reference 1.
Computed values for sediment transport are given in
Table 3. Tnese values can be used to estimate tne movement
of sediment into and out of the Tnompson Island Pool.
ID SeTereuce T7 ? 4-9.
*
III-4
HONS 049379
ooO
TAl-Lb 3
SLDlHbNT TKANttfUMT TIlOUPtiON ISLAM) POOL
Location
River flow, els
Predicted U^liacnt Concentration lor a Median Grain Size ot:
dr,n, I>pi
Miwer Klow,
i t-asured Sik}{jpi*Ic<1(2)(3)
Sediment Concentration, Mx
K'jcurcd Vulitile solids Concentration
(organic matei ials)
0.5 ailc above dan (mile 1U8.9) lowc end ot tool
2,500 20.600
41,400
0.001 " -
*
0.01 -
40
0.1 0.2 -"
--
3,600 17,000 39,300
1 loU) ao
4 10 45
(route 197 - Ust Qiarmel (mil* 194.1) upfer era! of pool
2,500 20,600
y
-
2,530*
35 10
3,600 13,500
i X
3 X
41,400 V
*
4,345* 70 30
39,300
35
* 40
Total SnSfcnited Out ids
n
5 20
125 4
W<*)
75
(1) (2)
(3)
{4)
(5) (-1 (*) (X)
Lx|iected total 6cdimcnt. concentration { suspended and bed load) Ot the sediment mixture with a median grain size as indicated. Computed by Haddock relation (Hctcrencc )
Inorganic traction o( total Measured suspended sediemnts determined by subtracting volitle solids trom total sus|>ended
solids. heJiau grain sites ol collected simple not yet available.
.
Crab sumples collected by ULC personnel at these ami olhci riyer locations {except as*noteJ) arc supi>ortud by suspended sediment aeasurcncnta by USdS which results are not yet available. Values shown ace rounded to relied probable accuracy.
riedian gram size of this coi.cen tr a t ions expected to be less than 0.00! mm but no dcterMination ul grain size made on this
suMpI e.
Average of 2
Suspended Sediment measurements.
.
Indicates no transport capacity tor sediment mixtures with median grain size indicated.
Indicates sediment mixtures with this mol tan grain size are not ant ic ipoied.
Indicates not measured.
.
OBE6<>0 SNOW
i
Field neasunaencs - The validity of tne estimates of
sediment transport capability nas been confirmed by several sets of field ooservations of river sediment concentrations.
A comparison of computed ana measures sediment transport is
given in Taole 3.
Selected results of observed total suspended solids and
volatile solids througn the study area are shown in Taole 4.
All values in Table 4 are "grab samples" collected uy DtC
personnel. !JSGS measurements at comparable river discnarces
have been made but results are not yet available.
J
.As indicated in Table 4, measured sediment
concentrations (as estimated by fixed solids) at tne low
flow of 3,S00 cfs show essentially no sediment transport
into or out of the Thompson Island pool. The value of 1 pem
suspended sediment is presumed to reflect movement of very
fine pacticles not susceptible to settlement. .'leasureinents
at 39,000 cfs shown an increase of 140 percent in suspended
sediments through tne pool. Tnis value is consistent with
the scour of materials previously deposited at low and
medium flows. Suspended materials (as estimated by volatile
solids) show an increase with larger streamflow and a slignt
increase in concentration through the pool reach. This
result is consistent with the suspension of organic
materials as river velocities increase.
III-5 MONS 049381
TABLE 4
OBSERVED SUSPENDED SOLIDS CONCENTRATIONS ppm
Location
Mile
March 18, 1976 Q = 3,61)0 cfs SSI Duration
Tot. Vol. Fix
March 29, 1976
Q = 17,000 cfs i Annual Flood (approx) Tot. Vol. Fix.
Troy Dam Mohawk River lit. 4 Ur.,
ba ter ford Lock 1, Dam Lock 2, Dam Ur., Meehanicville Lock 3, Dam Lock A, Dam F.t. 6 7 Qr .,
S ti1lwa ter lit. 29 Br.,
Schuyer v il le Lock 5, Dam Ht. 4 Br . ,
hor thcumberland Lock 6, Dam Thompson Is. Dam Rt. 197 Br.,
Ft. Edward Fenimore Bridge
153.9
156.5 159.3 163.4
165.8 168.0
168.1
183.2
.183.5 186.1 188.4
194.1 19 7.1
12 13
5 7
2 11
Xoz 7
o* S6 ^5
4
4 3
4 4 1 4
5
4 4 3
8 10
1 3 1 7
2
2 1 1
66 15 76 16
61 15
51 60
46
34 12
22
22 11 `
11
April 2, 1976 Q *= 39,300 cfs 100-year Flood (appro: Tot. Vol. Fix.
185 30 155 206 33 173
171 46 125 210 48 162
175 38 137 171 43 128
125 33 92
104 39 65 133 53 80 123 44 . 79
75 42 33 60 25 35
Note: Grab samples by DEC.
Tot. Total Suspended Solids Vol. = Volatile Solids Fix. = Fixed sol ids
DEC uonitor Stations - Total suspended solids ana
volatile solias measured at DEC water guality monitoring
stations are also available. stations have been examined:
Data from the following
.iile 197.1 - Hudson Falls ule 194.1 - Fort Edward, East Channel wile 183.5 - Mute 4 3ridge, Nor thumber land Mile 163.1 - Route 57 Bridge, Stillwater wile 156.5 - Route 4 3ridge, Waterford
Bed Load measurements - 3ed load measurements at tne
three river flows identified in Taole 4 have been made by
Dr. Thomas Zimmie under contract to DEC. Preliminary
results indicate that ced load movement is measuraole,
especially at the 100-year flood discnacge. Total weight of
bed load material moved, however, is small compared to the
total suspended load based upon preliminary estimates of Zz.
Zimmie.
Total Suspended Solids Discharge - The total suspended solids moving through the Thompson Island pool has been
estimated for the 9-aay flood period narch 31 - April 8, 1976; approximately a 100-year flood event. Total suspended
solids concentration variation with river flow is 'cased upon
observed values. Total inflow computed at Fort Edward is
36,000 tons. Total pool outflow is estimated at 45,000
tons, a net increase in total suspended splids, or a pool scour, of 9,000 tons is indicated. If it is assumed that
this scour took place in the lower one-tnird of the pool,
III-6
MONS 049383
where finec materials would be located, an average bed lowering at 0.05 ft or 0.6 inches is inuicacea.
On an annual average basis approximately 70,000 tons o total suspended solids enter the Thompson Island pool. About 60 percent of this transport will occur at river flows equaled or exceeded about 10 percent of the time. Currently available data indicate that approximately 00,000 tons of suspended solids will leave the pool on an annual average basis. This increase of aoout lOt is subject to confirmation and may r.ot be meaningful. Sedimentation in River Pools
Sediment transport estimates in the Thompson Island Pool reach (Taole 3) shows that sediment deposition taxes
-1*
place in the pool at low and medium stream flows. Tnis prediction can fee confirmed for the Thompson Island Pool anc extended to the remaining pools in the study area through application of sedimentation theory.
Sedimentation tanhs are commonly characterized by overflow rates. Overflow rates for the Hudson River pods below SaKers Falls at three river discharges ace shown in Table 5. These rates are generally within the range of can* design.
III-7
MONS 049384
TABLE 5 RIVER POOL OVERFLOW RATES
Pool
River Mile
At Dawn
Pool Area
Acres
Pool Volume mi/cjal
Q 90
Overflow Rate - gal/day/sq
At
Q 2.3
0 100
Troy Dam
153.9 530 2,900
-
-
-
Lock 1
159.3 390 1,300
100
1,400
2,300
Lock 2
163.4
390
780 150
2,100
3,500
Lock 3
165.8
350
1,100
100
1,500
2,500
Lock 4
168.0
1160
4,600
30
300
700
Lock 5
183.2
225
940 200
1,400
2,700
Lock 6
186.1
100
305 500
3,100
6,100
Thompson Island
300 1,400
100
800
1,600
> Q 90 = Flow equaled or exceeded 904 at the t iine = 2,500 cfs at Ft. Edward
Q 2.3 = Mean annual flood = 20, 600 cfs at Fort Edward
Q 100 = 100-year recurence interval flood = 41,400 cfs at Fort Edward
MQNS 049385
The preliminary evaluation of percentage of suspended
particles removed in the river pools for inorganic particles (specific gravity 2.3) and sawdust particles (specific
gravity 1.05) are as follows:
gal/d/sc ft
SG*=2.3 0.1 mm 0.01 mm
3G=1.0 5 0.1 mm 0.31 mm
100 1000
130 100
55 10
75 4 25 0
2003
.8 5 5
13 0
Comparison of the rivec pool overflow rates contained
in Table 5 witn the corresponding range of removals for
various particles shown aoove, indicates tnat a marxed
difference in settling of inorganic par tides '(suspended
sediments) and sawdust particles exists. At high river
flows (i.e., hign overflow races) essentially ail sawdusc
particles and related suspended materials will pass through
the river pools. Under high flows much of the suspended
sediments greater than about 0.1 mm in size will be trapped
in the river pools.
MUNS 049386 III- 8
IV. RIVtR SUSPE..iDD flATL RIALS
For tne purpose of the study, suspended Materials being
transported by the river are defined as colloidal clay
J
particles with grain sizes less than 0.0C1 mm and other ' materials consisting of organic materials of natural and
waste product origin. Ot.ner suspended materials include
algae, microorganisms ar.d wood ceoris.
These materials are significant in the Doper Hudson cor
two reasons:
. 1. Because of tne low sediment transport of tne river organic suspended materials may makeup as mucn as
I 50 to 75 percent of tne total suspended solids
being transported by the river during low stream
flow. Observed total suspended solids must be
corrected, therefore, to give a better indication
of suspended sediments. The test for volatile solids has been used as a measure of organic material.
2. Colloidal clay particles and organic materials
have very low or zero settling rates. These
particles are not lixely to settle out in the
river pools even under the most favorable
conditions for settling. At streamflows experienced most of the time, therefore, observed
river total suspended solids will consist largely
MONS 049381
IV-1
of colloidal clay and organic materials, rlocculation of suspended materials may take place in the river and result in increased setcli.ng rates. Suspended materials do not follow tne ordinary sedimen transport relations applied in Section III. Tne measured values of organic material as indicated cy volatile solids at the sampled streamflows (Tacle 4) have been used in suspended material estimates.
IV-2 HONS 049388
V pcs coiiCt.rrRAnojj
The amount of PC3 associated with river tea material
and in the river water column have been determined in
several 9roups of DEC and USG3 samples.
Variations in PC3 levels in river bed material nave been reported in a DEC report^* and ip recent DEC data from
surveys conducted during the period Feoruacy 24 - ..arch 9,
1976. These data shew a marked reduction in ?C3 levels from
the Thompson Island Pool to below Lock 1 and into the Lower
Hudson River. t
River Water Column - River water column levels of PCS
are available for a number of points in the study area.
Observed ?C3 levels at Fort Edward (Route 197 Bridge),
Thompson Island Dam and near Uorthumberland, are plotted vs.
the mean daily flow at Spier Falls in Figure 1. The
following observations plotted in Figure 1 were made
subsequent to September 1975.
.
Tl) PCS .'lonTtoFing in the Upper iiuuscn River Basin, nY BLC, Octooec 1975.
HONS 0^.9389
V-l
lU U*.
q f-or-h GJuotcfj
ft7
T'honif)cc'>i. /c/att<J Oati-L,
A TJorrhunih-frhitcf
HONS 049390
/ooO
A'oc>oa
/oo tPr.'C'
)/cr
D/St /vn^e}
'/jure. /
Point on Fiqure 1 Date
PC 3
1 13/28/75 0.3
2 11/13/75 0.6
3 12/16/75 0.6
4
4/2/76
4.4
5 3/29/76 0.27
6 3/29/76 2.5
7
4/3/76
3.8(1)
8
4/2/76
8.7(2)
9 3/29/76 1.3(3)
Spier Falls Discnarge, cfs Location
884 0 10440
8340 39310
3600
17250
33360
39310 '
17250
Ft. Edward Ft. Edward Ft. Edward Ft. Edward
Northurr.oerland be lev/ Lock 5 Thomson Is. Dam
Wor tnur.ibe eland Route 4
iiorthcumceriar. Route 4 Ft. Edward
(1) average of 2 values (2) values foe araclor 1221 and 1254 only (3) estimated from value for laboratory filter
A similar plot for ?C3 levels at Waterford is shown in
Figure 2. This figure is based upon the following*
observations made subsequent to Soetaraber 1375:
Point on Fiqure 2
Date
PCB PPb
via ter ford Discharce, cfs
1
10/10/75
0.3
7170
2
10/20/75
0.9
3
11/7/75
*
4
10/10/75
*
5
11/20/75
*
6
12/5/75
*
7
12/18/75
*
8
12/22/75
*
9
1/6/76
*
3024 0
5320 5320
9270 6910 6670 5165 2640
10
1/28/76
.3.6
13000 ice
cond i t ion( 1)
11
1/29/76
*
isoood)
12
3/15/76
0.1(2)
5300(1)
13
3/23/76
0.11
15000U )
14
3/31/76
2.1 ' 33000(1)
15
3/18/76
0.18
4100(1)
* less than C.l (1) Discharge estimated from relation with Spier Falls. (2) Estimated from value for laboratory filter.
HONS 049391
V-2
?6E6*0 SNOW
/ 0/n /
K*ll*l LtiOfCCATRClMiIrMt lC
4--b - 1 -
acwrrti uua co.
'/*>
4 \ /0
i 4 7011
i.'iiiiii:
m
i!
. lets i!yi^
?
ill!
tFK
/ooo
/OOOO
/on ooo
/?/.-.r^j<12. . c-'&
pH
Irr :rii
mi
ill:
iiii I!-.
i; : [ijji iij.
C
Tne average annual transport of PCS to the Lower Hudson River has been estimated using the relation for Water ford presented in Fiyure 2. For flows equaled or exceeded 10 percent of the time (16,000 cfs at Waterford) the PC3 transported will total 5,000 to 10,000 pounds per year. A range of transport is given to allow for the scatter snawn in tne data in Figure 2. PCS transport at flows wnich occur 90 percent of the time have beer, neglected in this estimate.
V-3 HONS 049393
VI. RELAI'EiD CO(J3I.DESAC 10;.3
In addition to potential ?C3 transport by river
sediments and suspended materials, tnree additional
transport mechanisms are identified:
o floating materials
o dissolved pnase resulting from direct uischar.:e
and/or release of PC3 from contaminated river ced
materials
o food weo.
A complete appcaisal of ?C3 transport and its
environmental consequencies requires consideration of tne
above mecr.anisms. Such considerations ere being carried out
or coodinated through DEC.
'
MQNS 049394 VI-1
VII IMPLICATIONS Of PRtLI.-iIlJAAY APPRAISAL
The estimates of sediment and suspended materials movement and deposition through tne eight river pools between Bakers Falls and Troy Dam nave been confirmed by measurements at low, medium and hign flood flows. The computed and measured cjata demonstrate cnat the Hudson River is a relatively low sediment yielding stream which is significantly affected by tne characteristics of tne river pools in the study reach. Even at high flood flows (approximately 100-year recurrence interval) a relatively low volume of sediment and other suspended materials is moved.
However, PCB contaminated sediments and suspended materials are continuing to move over the Troy Dam. Calculations of ?C3 transport based upon currently available measurements show that a 0.1 ppb PCS threshold at Waterford will be exceed about 10 percent of the time with PCS concentrations up to of 9 ppb..
Contaminated materials orignace primarily in the former Fort Edward and the Thompson Island pools with the assumption that there are currently no significant discharges of PC3 to the Upper Hudson River. These pool areas contain the highest measured lavels of contamination and are also subject to low inflows of unconta.minated materials which might cover existing contaminated deposits.
HONS 049395
VII-L
VIII .JbCbsSAR? DC'PAI LCO ST'JDida
Altnougn significant conclusions can be Jrawn frcm t.-.is
preliminary appraisal, detailed field investigations and tecnnical studies ate -arranted in a proolei.i of tne
magnitude and complexity of tne PC3 contamination of tne
Hudson River. Refined data and detailed analysis of sediment and suspended material movement in tne civet and
associated elements of the PCD orocleir. are justified for three reason:
1.
Reduction of present uncertainties related to tecnnical aspects of the proolem, such as,
dredging techniques, treatment of dredged
materials and alternative met.-.ods of reducing tne PCS contamination to an acceptable level,
2. Determination of the location and characteristics of PC3 contamination in the cools of tne study area in detail adequate to optimize the
cost-effectiveness aspects cf alternative remedial programs, and
3. Preparation of an environmental assessment of alternative remedial pcograms.
Performance of adequate and reliable evaluations of
alternative courses of action in resolving the PC3 preoia.?
is necessary in order to assure tne public and many
interested groups and agencies tnat -a proper solution nas
been implemented.
VIII-1 HONS 049396
The cetaileu studies necessary involve lour categories:
1. Field Investigations
2. Engineering Studies
3. Evaluation of Alternatives
4. Environmental Assessment A brief statement of the purpose and scope of these categories, as t.ney relate to engineering solutions, is
given in the following paragrapns.
Because of tne critical nature of tne PC3 problem t.iese
studies should be initiated at the earliest opportunity.
, Field investigations - Field investigations '..ill
involve three principal work areas:
`
o Survey of baseline for control of field '
measurements and -ossicle future remedial
Jredging. o River deptn measurement at selected cross
sections.
o Collection and analysis of bed sediments.
It is anticipated that the survey baseline ar.d river depth
nisdsur e rr. 6 n t s will be limited to the pool areas that would
reguire remedial dredging. 3eu sediment samples anc a
limited number of flood plain samples will be collected anc
analyzed for PCS cn a reconnaisance oasis in all of tne
pools in the study reacn. Approximately tnree to five
samples will be collected in each pool. This data will
VIII-2 MONS 049397
Confirm that remedial measures can be limited to specific pool reaches. ..ore detailed sampling will be carried out in the critical reacnes. Detailed sampling will lively consist Of three samples across tne river at 2000 to 3000 foot ihtervals along the river. River depths will oe determir.ee t etch sample section. Tne detailed sampling art aeptn measurement will be controlled cy tne survey baseline.
Engineering Studies - Engineering studies will emphasize tne technical and economic aspects or rivet dredging programs. There ace five study areas:
Dredging Evaluation: Evaluate the performance and cost of alternative dredging techniques and their impacts on loss of fine materials at tne dredge head, interference with river navigation, ability to control depth of cut and weex in shallow river areas.
. Spoil Sites: Identify and analyze potential spoil sites including their storage capacity, acquisition cost, wetland anc ground water impacts, present anu subsequent land use potentials and tneir compatibility witn dredging program needs.
V1II-3
MUNS 049398
o Water Treatment Pilot Plant: Conduct laboratory and field pilot scale studies of alternative treatment techniques in ordec to develop performance - cost functions for treatment of dredge return water flow.
o Demonstration Dredging: Conduct demonstration of dredging techniques to confirm per cor.nance wi cn Hudson River conditions.
o wodel of Rivet Sediment movement: ,-iodify, as necessary, existing computer models and apply to analysis of river hydraulics and sediment and other materials movement through the river pools. This analysis will aid in refining evaluations of necessary dredging areas. (1)
Alternate Evaluations - Evaluate performance - cost relations cor alternative remedial programs including dredging of critically contaminated areas and otner viable programs that may be developed. Work areas include; description of the relations between PC3 removal from tne environment and the uredging/treatment/spoil system, program cost estimates and sciiedulas and contract documents for the recommenced program.
11) i\n example or sucn a pcourara is! Scour ano~5e?ositron in Rivers and Reservoirs, U.S. Corps of Engineers,, Hydrologic Engineering Center; Septemoer 1975.
VIII-4
HONS 049399
Environmental Assessment - An environmental assessment will be prepared oased upon:
o Necessary baseline data, o Participation in the field surveys and
Investigations undertaken, o Review engineering studies and alternative
evaluations.
049^00
HONS
VI1I-5
ZX REFERENCES 1. iialcolm Pir.nie, Inc., Investigation o Conditions
. Associated with tr:e Removal o: Fort cuwaru Dam, Fort Edwarc, ..w ic r<, ..'I State Department or t.nv iron ter. ta I Conservation, February 1375. "
2. tlew York State Department of Environmental Conservation Field Surveys, July-August 1967, Unpublished Data.
3. U.S. Soil Conservation Service, Plsnnino anc Desicn or Open Channels, Technical Release ..o. 73, uo-,.
4. riaddcck, Thomas, Jr., Equations for Resistance to "low and sediment Transport in Aiiuvial cnar.nsis ,~~ater Resources Researcn, 12:1, 11-21, FeoruaFy i`37 6 .
5. Leopold, Luna 3., i-i. Gordon Wolman, Wm. p. niller. Fluvial Processes in Geomorohology, l.n. Freeman. 1969 .
MONS 049401