Contents
introduction
The discovery and production of hundreds of
natural and synthetic maler.als including as; bestos-cement products has in some in
stances prompted the need lor special pro\ leclive equipment and practices that shouc
be employed by all in the industry where dust is created.
INTRODUCTION . . .
Manulaciurers of asbestos-cement products ! have for years been taxing protective meas
ures to eliminate exposure of their workers to the inhalation of dust.
HOUSEKEEPING ,..
SHIPPING, HANDLING AND STORAGE ...
The fabricating, handling and applying of asbestos-cement products are diverse and range from the installation of a single piece to extensive operations involving cutting-and machining by mechanical equipment. While
care should always be exercised, special pre-
FABRICATION. AND
t cautions are necessary when dusts in excess
APPLICATION ....
I of federal, state or provincial allowable thres
hold limits are generated as the result of saw
ing, drilling or other operations. Respirators RESPIRATORY EQUIPMENT ...................... 7 j should be worn.
i The following practices are recommended (or SUMMARY .................................................. 7 1 fabricating, handling and applying asbestos-
cement products in the building and construc-
I lion industries. Contractors and applicators
Asbestos-cement products. In place and un der normal use. p'esent no known hea'tn risk
to me use' or ge-.e'ai public
are urged to study these recommended prac tices carefully and to see that they are obse'nved by all workers It is in the best interest of both employer and employee to see that
these recommended practices are strictly ob
$1910 acpa
served.
23
o
Ho meiUicOa^L\-s-oW/ k'
\
Shipping, Handling and Storage
[
1. An organized housekeeping program should be maintained in all areas and on all operations at all times.
2. A major source of dust is from loose materials, scrap and debris distributed throughout the job area which are disinte grated by being trampled upon, run over, etc. Much of such dust can be eliminated by exer cising simple good housekeeping practices.
3. Specific standards and practices de signed for jirovicir.g safe, clean a^d orderly working conditions should be defined.
4. Efficient supervisory control, planning ol systematic cleaning plus d3y-to-day foiiow-up are the basic requirements tor environmental control and injur/ prevention.
4
1. Under normal conditions, unit load han dling and storage of asbestos-cement prod ucts present no environmental problems.
2. When handling individual pieces of flat and corrugated asbestos-cement sheets, care should be taken when placing one sheet on top of the other to avoid creating breakage and dust
3. If breakage of asbestos-cement products occurs, broken pieces of material should be cleaned up and disposed of to avoid disinte gration by then being trampled upon, run over. etc.
4. Handling and storage of c-">gs containing asbestos fioer, cements, etc., present no problem prov.ding that bags are unopened and not broken. Open or broken bags should be.repacked, resealed or discarded to prevent dust distribution. Spillage should be cleaned up immediately.
5
c
t-acncaiicn anc /"Applicator:
Respiratory Equipment
Or../ L' S 5ureau o' Mines 3cc.'0ved 'espiratory edvi.omev. is recommenced tor use Tre e"ic-e''c,- arc effectiveness of this ec. ; m.ert is dependent upen p-coe' ca'e. c:ea- -g and maintenance. A systematic procec-'e should be es'jbiisned to insure mat tn.s s
i cor-e. i A list of aoo'eved resP'rato"> ecu-ome'-: car
be obtained from.
1. When moving asbestos-cement products to and from the fabrication site, individual pieces of materials should oe handled with care to avoid breakage and dust.
2. Fabrication of asbestos-cement products involving cutting drilling, sawing, etc , ShoulC be dene m a manner that will minimize dust The use of prepe' methods, tools and equip ment is essential.
American Industrial Hygiene Association
14125 Prevost
Detroit, Michigan 48227
U. S. Department of the Interior Bureau ol Mines Nineteenth and E Streets, N.W. Washington, D. C. 2C240
3. When cutting, drilling, sawing, etc., on a repeated basis with power equipment, me chanical dust collecting systems adequately designed to remove dust from the source should be used.
4. Fabrication of asbestos-cement products
in confined spaces requires adequate me chanical dust collecting systems designed to collect dust at the source. Where these sys tems are impracticable, approved respirators should be worn.
5. Provide waste containers at all fabrication and application areas. Dispose of unus able material. Keep floors and surfaces dean. Vacuum-'Cleamng equipment is recommended to remove dust and small particles. If vacuum equipment is impracticable, wet down waste material before sweeping and shoveling. Res pirators Should be worn during clean-up operations.
Summary
Three major points to keep in mind in the fabricating, handling and applying of asbestoscement products.
. . . Keep dust to a minimum.
. . . Wear U. S. Bureau of Mines approved respirators when exposed to dusts above federal, state or provincial allowable threshold limits.
. . . Maintain good housekeeping at all times.