Document KJ9GaJwNMwo0wOkwqzbaNmkor

1 KAISER ENGINEERS, INC. MIDDLETOWN, OHIO FINAL PROJECT REPORT ARMCO STEEL CORPORATION SITE DEVELOPMENT - STEPS I, II, & III PROJECT NO. 7112 NOVEMBER 3, 1969 Distribution: Armco R. F. Boschert V. J. Curtis T. R. Foley A. M. Greco C. G. Kramer D. C. Osborne P. R. Smith J. M. Thomas Kaiser* S. D. C. Anderson D. A. Daly V. L. Frankson B. P. Franceschi R. C. Hulseman S. G. Imherr E. D. Lowell D. R. McSparrin R. J. Wolf Central File Prepared by: D. C. Anderson Date Approved: *Jbn S. G. Imherr /lf'Z4i/&9 Date SMALL RED i AKE-003225 w ?yjit** mt; ) fe$! L7 i` 14 ffilCV P;'4jJ:{*!| fl.V' V'ljV-"1 yv*u- ft!1: lili'jiei a KAISER ENGINEERS, INC. MIDDLETOWN, OHIO FINAL PROJECT REPORT ARMCO STEEL CORPORATION SITE DEVELOPMENT - STEPS I, II, & III PROJECT NO. 7112 CONTENTS Project Summary General Description Project Authorization Project Personnel Project Progress Project Schedule Fmal Summary Cost andComparison General Arrangement Drawings & Photographs SMALL RED AKE-003226 fe;; :8: !(': M) Pfci-k. ffi' FINAL PROJECT REPORT SITE DEVELOPMENT - STEPS 3, II, & III PROJECT NO. 7112 1. 0 GENERAL DESCRIPTION* 1 * 3 4 This project was concerned with the entire scope of Site Development work for the Middletown Expansion Program. Step I dealt primarily with preparation of the site in the South Area where the new Hot Strip Mill is located. A final report has been submitted covering this step of the work. See Final Project Report for South Area Site Development, Project 7112-1. The general scope of work accomplished by project 7112 Steps II and III was as follows: (1) Demolition, removal and relocation of existing facilities in the Steelmaking Area. {2) Site development of the Steelmaking Area. (3) Grading for roadways, railroads, ditches and surface drainage in the South and Steelmaking Areas. (4) Storm drainage system including all sewers and culverts in the South and Steelmaking Areas. 1- - SMALL RED AKE-003227 (5) Paving of roads and parking lots in the South and Steelmaking Areas. (6) Yard lighting in the South and Steelmaking Areas. (7) Two (2) permanent guard houses. One in the South Area at Oxford State Road. The other is located at Lefferson Road near Highland Street. As a result of the earthwork study conducted as a part of this t: project, the floor elevation of 107. 50 was established for the r- Basic Oxygen Plant and Continuous Casting Facilities. A more detailed description of this project may be found in Engineering Report 7112 - Steps I, 11, and III, dated June 1, 1967. IL fel; 85*13 p8-i* (.* If e5:ft i'fe M te' SJCi m?I ppr?- fei> If fel- SMALL RED 2- - AKE-003228 2. 0 PROJECT AUTHORIZATION An Engineering Report for 7112 - Step II was issued September 24, 1965 and the "Request for Appropriation" was submitted September 24, 1965. Armco Corporate Management approved the request for $4, 696, 000 on December 28, 1965. On June 1, 1967, a final Engineering Report, 7112 - Steps I, II, and III, was issued combining the previous reports and included the final stage of Site Development, Step III. Armco management approved the consolidated appropriation request of $7, 706, 200 on July 25, 1967. SMALL RED AKE-003229 3. 0 PROJECT PERSONNEL Armco Program Engineers Armco Project Engineer Armco Project Engineer Electrical Mr. T. R. Foley Mr. J. M. Thomas Mr. R. F. Boschert Mr. J. J. Delaney Kaiser Project Engineers Mr. R. C. Hulseman Mr. D. E. Ernst Mr. D. C. Anderson SMALL RED AKE-003230 4. 0 PROJECT PROGRESS Feasibility studies and scoping drawings for 7112 - Step 11 were started in mid-1965, and completed with the issuance of the engineering' report September 24, 1965. The 7112 Step III scoping information was completed with the issuance of the consolidated 7112 - Steps I, II, and III report June 1, 1967. The "Requests for Appropriation" were approved as outlined in Section 2. 0. Detail design for Step II began in August, 1965. All steps of the 7112 site development design program were completed in January, 1968. A total of 168 drawings and five (5) sets of specifications were issued for construction for Steps I, II, and III of this project. Stripping and grubbing of the Steelmaking Area site was started in November, 1965. The South Area storm sewers and drainage system was started by Kaiser Engineers in March of 1966. Earth and slag embankment in the steelmaking area was completed to approximate design grade during the first quarter of 1967. Completion of this work provided a working grade for the Basic Oxygen Shop, Continuous Casting, Mold -5- K. SMALL RED ! AKE-003231 ft:* ) m": *V: / fsi, &' 'i? !' ?bj!Vi:h-,=<Sr;., )>> V;| !;:; aI-!-...' Yard, Stripper Building, Trackwork, Roads and other miscellaneous facilities located within the Steelmaking area. Several subcontracts were awarded in connection with Step II and III of this project. The following is a list of the major subcontracts: S/C Number Type of Work Subcontractor 7112-1965 -2084 Roadway Paving Armrel Construction Co. 7112-1730 Roadway Paving John R. Jurgensen Co. 7112-1768 Roadway Paving Triasco Corporation 7112-1109 Slag Removal and Embankment W. L. Harper Construction Company 7112-1629 Storm Sewers Steelmaking Area Delta Pipeline Construction 7112-1667 Yard Lighting Westinghouse Electric 7112-2276 Lefferson Road Guard House S K Construction Co. 7112-1077 Fencing Davis & Siehl The final completion inspection of the Steelmaking Area was held on August 6, 1969. The final inspection of the South Area was held August 13, 196 9. Punch list items, clean up, and additional work items extended the final completion date to the end of October, 1969. 6- - SMALL RED AKE-003232 5. 0 PROJECT SCHEDULE The schedule outlining the theoretical and actual project progress is attached. This schedule shows the combined progress for all steps of the site development work. RED -7- AKE-003233 --8-- AKE-003234 f;: M i% SMALL RED PROJECT NO. 7 1 1 2 -1 & 2 & 3 *, DENOTES RESCHEDULE KAISER ENGINEERS, INC. REPORT DATE F IN A L - ------------------------------- r $T*Vr': I- * r fe;. |v:i- SMALL RED nO IBC J Hg 7112-1, z & 3 . AKE-003235 KAISER ENGINEERS |MC FINAL COST & COMPARISON TO ENGINEERING REPORT BUDGET _____ _________ ___ ___________ Appropriations The following is the chronological history of appropriations for the Site Development Project from the inception of Phase I to the present: September 30, 1 964 $ 10,000 January 13, 1965 1,816,000 September 24, 1965 4, 696, 000 June 16, 1967 1, 184, 200 February 9, 1968 150, 000 May 20, 1968 (679, 296) $7, 176, 904 Costs The final costs of the project shows an underrun of $1, 04 9, 823, reflecting a savings of $352,430 in direct costs, $30, 393 in indirect costs, and the entire contingency of $667, 000. A summary of final costs as compared to the engineering report budget follows. -10- SMALL RED AKE-003236 [ fs;5' fi !! 3T II llr? i'MM'-. li fe ffc IPS' K; : 'f itirv' ` Costs Project Section Description Budget Estimate 101 102 103 104 105 106 107 110 111 112 113 115 116 117 118 119 120 131 151 152 153 154 155 156 161 163 172 173 176 179 180 181 201 202 203 252 253 880 Demolition Remove & Salvage Clearing & Grubbing Seal Exist. Wells &. Cisterns Earthwork Slag Culverts Perimeter Fencing Gen. Site Clear. -So. Area Roadways - South Area Parking Lots - South Area Coil Conv. Overpass Bridge Fencing - South Area Culverts - South Area Storm Sewers - South Area Yard Right - South Area Park. Lot at No. 2 O. H. Traffic Signal - South Area Demolition &. Removal Alter Middletown Sewer Gen. Site Clear. - SM Area Culverts - S. M. Area Storm Sewers - S. M. Area Clean Out & Fill Exist. Oil Ponds Refuse Dump Roadways Oil Recovery Area Roadways - S. M. Area Parking Lots - S. M. Area Fencing - S. M. Area Yard Lighting - S. M. Area Yard Light. Crawford St. Ent. Traffic Signal - S. M. Area Interplant Signs Flag Pole at New Guard House Guard House - So. Area Fabricating Shop Guard House - S. M, Area Elect. Sub Ovhd & Fee 3, 500 20, 000 25, 000 600 653,600 821,000 48, 400 50, 900 559, 400 313,300 77, 700 47, 700 14,200 70, 300 1, 405, 100 139, 700 9, 100 5, 000 89, 400 17,000 800, 700 272.000 424,400 22,500 2, 800 17, 700 158,800 37, 600 9, 200 138,700 6, 800 - 172,100 9, 300 23,000 $6, 483, 900 -0 oo& Estimate at Completion 3, 476 20, 000 25, 000 600 653,563 820, 927 48, 332 50, 818 687, 450 282, 206 35,856 42, 218 7, 885 53,708 1, 172, 029 118, 880 9, 064 8, 762 85,763 2, 774 74 3, 34 9 233,041 356, 887 20, 377 2, 74 3 17, 437 189, 046 10, 463 17, 055 125,038 26, 118 1, 787 881 65, 874 172, 073 17, 600 2, 390 $6, 131, 470 (Over) Under Budget 24 - - 37 73 68 82 (128, 050) 31,094 41,844 5, 482 6, 315 16,592 233,071 20, 820 36 (3, 762) 3, 637 14,226 57,351 38, 959 67,513 2, 123 57 263 (30, 246) 27,137 (7, 855) 13,662 (26, 118) 6, 800 (1, 787) (881) (48, 474) 27 (B, 300) 20, 610 $352,430 -11 - SMALL RED t AKE-003237 Isra m in SMALL RED AKE-003238 7. 0 GENERAL ARRANGEMENT DRAWINGS & PHOTOGRAPHS The following project general arrangement drawings are attached: 625167 625168 625169 625171 625170 Roads and Roadway Lighting South Area Roads and Roadway Lighting Steelmaking Area Roads and Roadway Lighting Steelmaking Area Storm Sewers South Area Storm Sewers Steelmaking Area AKE-003239 SMALL RED AKE-003240 SMALL RED AKE-003241 SMALL RED AKE-003242 f11if.i,:?im; ft'-111". ft'5 fc fi fe !: Bi ig..\ ':; K-.;- 3, Ph-- i' |;i SMALL RED AKE-003243 MI|WJ.WpffiJTf.lTI SMALL RED AKE-003244 PHOTO NO. 1 - SOUTH ALFA WORMS SOUTHEAST, SHOVIIHG INITIAL STAPFS OF SI,OHK AM) HOT STjilF HILL taSmSSSS^JSSmk MALL RED AKE-003245 it'.-.-'. EA i PHOTO NO. 2 - AERIAL VIS'/ LOOKING NORTH, SHOWING INITIAL CONSTRUCTION STAGES OF THE HOT STRIP MILL AND ROUGH GRADING OF THE SOUTH AREA, OCTOBER 1965. SMALL RED AKE-003246 .T...TTTm--rTJT^rIX~lll^7~^n 1 uij P% " p<*-. a';,*/ ' . ., v < "r~_________ . . . -S^?;:ivv.'. SMALL RED AERIAL VIEW LOOKING NORTHWEST, SHOWING THE SOUTH AND STEELMAKING AREA SITES. THE ROADS, DRAINAGE, AND SITEWORK ARE IN THE FINAL STAGE OF CONSTRUCTION, FEBRUARY 1969. AKE-003247 SMALL RED AKE-003248 AERIAL VIEW LOOKING NORTHEAST, SHOWING STEELMAKING AREA SITE IN THE FINAL STAGE OF CONSTRUCTION. SMALL RED AKE-003249