MA Supreme Court Ruling Deals Blow to Access Northeast ~ By JeremiahShelor on August 18,2016 at 12:00 a.m.
Share: in
f
V
The Supreme Judicial Court of Massachusetts on Wednesday dealt a setback to t he proposed Access Northeast pipeline project when it overturned a gas-electric harmonization plan approved by the state's Department of Public Utilit ies (DPU).
Algonquin Citygate Winter Average Forward Prices Through 2023 Traded Before & After MA Court Ruling
S6800
811512016 8117/2016
$6600
:,
.;; S6400
2 ::E
. S6200
Cl.
.,; ,; S6000
.. $5800
11 II II II II S5.600
~nter '161'1 7
Winter '17'18
Winter '181'19
'Mnter '19'20
w..ter '20"21
IMnl er '21f22
1/mler '22/23
Source NG/'s Forward Look, NG/ calculations
The DPU, in response to a petition last year from the state's Department of Energy Resources, approved a plan to allow electric dist ribution companies (EDC) in the state to enter into long-term capacity contracts on natural gas pipelines and recover the costs through rates. The EDCs would then release their contracted capacity to electric generators or back into t he market.
Sierra Club v. Dept of Energy, 4:25-cv-5027
SC_EVERSPLIT0027168
The plan came in response to recent commodity price volatility in New England during the capacity-constrained winter months and was designed to work around the problem of electric generators being unwilling to sign up for the long-term capacity contracts needed to stimulate pipeline construction.
The court concluded that, while Massachusetts state law tasks the DPU with regulating contracts for both natural gas companies and elect ric companies, respect ively, the department ultimately "erred in interpreting" the relevant code "as authorizing it to review and approve ratepayer-backed, long-term contracts by electricdistribution companies for natural gas capacity."
The plaintiffs challenging the capacity release plan in Massachusetts were Engie Gas & LNG LLC and the Conservation Law Foundation.
Midstream Solutions Built for Producers
I
PROOUCEJtS hUOST1IEAM
Produce~ Md-stream partners with U.S operol0r$ todesign ond detNer right-SU~ turnkey systems. lhot moximite ~tboclt and ensure flowouuronce.
Allowingstate-regulated EDCs to purchase pipeline capacity is a key component of the Access Northeast project as currently proposed. The mostly brownfield Access Northeast-- under development by Spectra Energy Partners LP along with EDCs Eversource Energy and National Grid - would add around 900,000 Dth/d to Algonquin Gas Transmission LLC's (AGT) system to serve electric generation demand in New England and address the region's recent winter price blowouts.
National Grid spokeswoman Danielle Williamson told NG/ that the court's ruling "is a disappointing setback for the project, which is designed to help secure New England's clean energy future, ensure the reliability of the electricity system, and most importantly, save customers more than $1 billion annually on their electricity bills. We will explore our options for a potential path forward with Access Northeast and pursue a balanced portfolio ofsolutions to provide the clean, reliable, and secure energy ourcustomers deserve."
Sierra Club v. Dept of Energy, 4:25-cv-5027
SC_EVERSPLIT0027169
Matt Hoza of BTU Analytics LLC said the state supreme court's decision is "definitely a blow for Access Northeast." Hoza said he's waiting "to see ifSpectra has any legal recourse or if there is a loophole that they might be able to exploit'' before making any final assessment on the project's future.
"There are some smaller AGT projects this year and next, but really Access Northeast was the big project into New England that was going to provide some basis relief," he said." If it does go down, expect basis to beJust as volatile as it has been in the past and LNG imports to remain an important fuel source during winters."
Hoza pointed to a small bump in winter 2018/ 19 forward prices at AGT Citygate following the court ruling.
According to NG/'s Forward Look, for winter 2018-19, Access Northeast's target inservice date, the strip atAGT Citygate increased from $6.11/ MMBtu to $6.14 between Monday and Wednesday; the w inter 2022-23 strip increased from $6.69 to $6.73, with every winter in between also seeing a bump of2-3 cents.
NGl' s markets analyst Nate Harrison said the timing ofthe ruling, coming before Thursday's storage report, "allows us to better visualize the possible pri ce impact on Algonquin winter strips in isolation from other major market news."
The Spectra-operated AGT filed with FERC in February seeking approval of a tariff revision needed to move forward with Access Northeast's proposed EDC capacity commitments, setting off a debate that has drawn numerous filings from stakeholders on both sides (see Daily GP/,~).
The revision would allow Algonquin to bypass the Federal Energy Regulatory Commission's capacity release requirements in order for EDCs owning firm transportation contracts to give up their capacity to generators as part ofa stateregulated electric reliability program. Opponents of the proposal have described it as anti-competitive and said it would artificially suppress the value of the capacity, while backers have said it would improve reliability and save ratepayers money by avoiding price spikes.
Representatives from Engle and Repsol Energy North America, another New England liquefied natural gas (LNG) player, effectively argued against Access
Northeast during a June conference in Boston, pitching the region's LNG capacity as the best method for meeting short-term winter peak demand (see DailyGP!, .J.u.ntl.3) .
Last month, Maine utility regulators approved a ratepayer-backed reliability plan similar to the one struck down Wednesday in Massachusetts (see Daily GP!, July_ ll).
Sierra Club v. Dept of Energy, 4:25-cv-5027