Document JNkEw8b7q78MLQapdqkzoNqNO
SAFETY - A. H. Sather
Occupational Injuries
July
1981 Year-To-Date
1981 Year-To-Date
First Aid Medical Case Restricted Workday Cases Restricted Workdays Lost Time
'
1 0 0 0 0
2k
3 0 0 0
35 12
1
3 0
Injuries By Department
Vinyl Operations Compound Operations Maintenance Laboratory Receiving and Warehouse Office
0 0 1 0 0 0
3
6
15 1
1
1
12 11 21
3 0 1
Injuries By Type
Cuts and Abrasions
1 13
Eye Injuries
02
Burns
0 10
Bruises
02
Strains and Sprains
0
2
Other
01
23
k
5 10
k k
As of July 31 1981, the plant operated 757 days or 992,978manhours without a disabling injury.
Safety Meetings
The topic for July safety meetings was "Hand Injury Prevention". The slide and tape program "Think Before You Reach" was shown and discussed.
New Module Outage
A considerable amount of time was devoted to planning the shutdown checklist for the August 10, 1981 outage in the new module for expansion, maintenance and other engineering work.
Fi re School
J. R. McCrimon -Compound Operations Superintendant attended the Texas A & M
Industrial Fire School J4ly 26-31, 1981.
DTH 000021750
SAFETY - (continued)
Phase III Firewater Project
John Elkins - CED was in plant July 23, 1981 to review final equipment locations for Phase I I I of the plant firewater expansion project.
Health
Activity for the reporting period included routine monitoring for VCM, lead antimony and total particulates and a report of additional monitoring work done on plasticizers, tin, phthalic anhydride, chlorine and mercury. The results and overexposure are explained below.
Chemical
VCM Lead Antimony Total Particulates
PEL Number Pe rcent
Sb 97 5 100 5 100 3 100
PEL Number Percent
33 00 00 00
Overexposures
Three exposures occurred to vinyl operating area personnel. One occurred to a vinyl supervisor during a VCM filter pack o-ring failure in the new module 9 one to a chief operator who was removing used VCM filters from the filter
pack area and one to an "A" operator with no specific cause found. None of the above were wearing resp irators.
Other Monitoring
Additional monitoring was done on several other chemicals which were noted above. DIDP and 610P area samples were taken in ten locations with nine of the samples indicating less than 0.3 mg/m* and one at 3-3 mg/m* (610-P). There is no
established standard for these chemicals. The OSHA standard for di 2-ethyl hexl phthalate is 5 mg/nr*. Four area samples and seven personnel samples for tin
stabilizers indicated less than the detection limits. Several area samples for phthalic anhydride were taken on the charge floor of the plasticizer building and the results found to be less than 0.01 mg/m*. One phthalic anhydride per
sonnel sample was taken on a yard operator during the unloading of a phthalic anhydride tank car. Several problems were encountered during the operation and the sample result indicated 0.7 mg/m'. A total of 13 Drager tube samples were
taken during slug feeding of chlorine to the plant cooling towers. All samples indicated non-detectable results. Drager tube samples were taken in two areas for Mercury. The old I . E shop indicated results less than the detector tube detection limits. Sampling in the current I E shop indicated a result of 0.17 mg/m-* mercury following a small spill. The spill was cleaned up and the
area was resampled with nondetectable results.
DTH 000021751
VINYL - P. E. Markey
Month
Year to Date
1. Total Production, MM Lbs. 2. Production Rate, M Lbs./C.D. 3. Charges, Reactor Batches/C.D. 4. Total Charges 5. Reactor Stream Factor, % 6. Dryer Rate, Average Lbs./Hr.
7. Dryer Stream Factor 8. Accounting Days
23.5 765
20.2 628
90.4 5318
85.5 31
176.9 834
20.6 4372
87.5 5700
86.2 212
Vinyl Department production for July was 23.5 MM pounds or 94% of budget.
Reactor and dryer stream factors were 90.4 and 85.5%, respectively.
Reactors
1. Major repair work on D-400 agitator gear box resulted in a 2.4% reactor stream factor penalty.
2. Recovery and dryer imbalances resulted in a 3.1% reactor stream factor penalty.
3. Cleaning the condenser on 741 reactor resulted in a 0.6% reactor stream factor penalty.
4. Pluggage of the VCM charge header in the old module resulted in a 0.6% reactor stream factor penalty.
5. Replacement of both VCM charge valves on 743 reactor resulted in a 0.6% reactor stream factor penalty.
6. A main breaker failure in the old module resulted in a 0.35% reactor stream factor penalty.
In order to better match sales and maximize operating costs efficiencies the production target for July was reduced from 27 MM pounds to 25 MM pounds. Two cost savings measures adopted were the use of a single rather than dual initiators in 5425 production and usage of a high productivity initiator in
5385.
Dryers
The vinyl unit was essentially reactor limited for the month as described above.
DTH 000021752
VINYL - (continued)
Resin Quality Summary Resin Type
Prime Pounds
"BC" Grade
"H" Grade
% of Total Product ion
Budgeted Resin Product Slate, %
5305 5385 5425 5465 Sifter Overflow
4,381 ,474 13,836,560
4,998,941 109,180 -
29,250 214,000 100,950
-
-
9,750
-
1 1 ,250
-
(237,975)
18.8
59-9 21.8
0.5 ( 1.0)
3.9 70.6 22.2
3-3 N/A
TOTAL
23,326,155 344,200 (216,975)
100.0
100.0
Quality performance for July was 99.4% customer grade with 1.5% "BC" grade and (0.9%) "H" grade.
Variable Cost Performance
The variable cost variances for July totalled a favorable $709 M with $619 M due to price and $90 M due to efficient operation. The major price variance was $612 M due to below budget monomer pricing. VCM pricing for the month
was 21.084 i/lb. versus the budgeted 23.636 i/lb.
The favorable $90 M efficiency variance is comprised of favorable variances of $44 M for processing additives, and $62 M in the off-grade category which resulted from intensive upgrading efforts. The favorable efficiency was partially off-set by a unfavorable efficiency of $19 M for VCM.
Monomer consumption for the month was 1.022% pounds VCM/pound PVC versus the 1.01936 standard. The 108 VCM railcars weighed from Lake Charles in July showed an average shortage of 700 pounds per car versus the 650 pounds per car shortfall determined in June. Year to date VCM efficiency is 1.02215 pounds VCM per pound PVC.
General
1. Packaging activities for the month totalled 1.7 MM pounds.
2. Resifting activities for profit improvement totalled 829 M pounds.
3. Operating problems associated with 5305 production using Chain Transfer Agents were resolved during the month with R&D technicial assistance. The problems appear to have been associated with residual AMS levels in the recovered monomer. A formula revision to solely fresh VCM has enhanced particle size control and no further problems have been encountered. Resolution of CTA problem and optimum uas of blend tank capacity resulted in 4.4 MM pounds of 5305 production. This represents the highest monthly production of this profitable resin on record.
DTH 000021753
VINYL - (continued) General - (continued) 4. Trial production runs were successful in producing a 0.68 viscosity 5305
resin. This represents a key step in the development of improved fittings and bottle grade type resin. 5. Trial production runs were conducted with increased levels of calcium stearate in 5385 production. Batches were produced at 4 gallons, 8 gallons, and 16 gallons stearate levels. Samples were forwarded to PAL for testing. Further testing is planned for August. 6. An extended trial of the high productivity L-46 initiator was begun in July. Testing shows the L-46 initiator to be more active than L-223- However, reactor venting on L-46 is more severe than L-223 even at reduced initator loadings.
DTH 000021754
COMPOUND - J. R. McCrimon
Compound Production
Montn
Per Day
Y.T.D.
Line i, M Pounds Line V, M Pounds Line III, M Pounds Total , M Pounds Accountings
1,487 43
3,012 4,542
31
49.6 43-3 97.2
146.5
8,740 1 ,981 20,643 31,094
212
Line 1 operated 30 days during July at an average rate of 49.6 M pounds pe day. Major items affecting production efficiency were: product changes (45-3 hours), dicers (37-8 hours), blender conveyor (37-5 hours), bag charging resin (17-3 hours), quality control adjustments (8.0 hours), blender scales (5.9 hours), and blender conveyor clutch (5-5 hours).
Line V operated 1 day during July at an average rate of 43-3 M pounds per day. Major items affecting production efficiency were: screw change (2.6 hours) and Orbitran (2.3 hours).
Line III operated 31 days during July at an average rate of 97-2 M pounds per day. Line III production was affected by: product changes (40.3 hours), mill maintenance (9.0 hours), FCM (7-0 hours), dicers (6.6 hours), quality control (10.9 hours).
Quality performance for flexible compound was 3-5% off-grade of which 76.8%
was due to mill scrap. "BC" production was -2.98% (135 M pounds reblended).
The raw material requirement for flexible compounds was 1.01037 pounds of raw material per pound of compound versus 1.01301 standard. (Y.T.D. is 1.00982)
The variable cost variance for compound was $18.8 M with $48.9 M due to price and ($30.1 M) due to efficiency. The variance due to product mix was ($1.5 M), and the variance due to off-grade was ($35.2 M).
There were no major efficience variances or price variances for the month.
Dry Blend
Month
Per Day
Y.T.D.
Production, M Pounds Accounting Days
3,791 31
158.0
28,447 212
Dry Blend operated 24 days during July at an average rate of 158 M pounds per
day. Production included 80273G, 80174, 90171, 80274, and RP-100 BW. Dry blend production was affected by: quality control (47-3 hours), product changes (21.8 hours), Brabender repairs (19-1 hours), and out of resin (5.7 hours). RP-100 BW and 90171 production to boxes also contributed to reduced rates.
Quality performance for the month was 99-98% customer grade.
DTH 000021755
COMPOUND - (continued)
Dry Blend - (continued)
The raw material requirement for dry blend was 1.00618 pounds of raw material per pound of dry blend versus a standard of 1.00576. (Y.T.D. is 1.01114)
The variable cost variance for dry blend was $32.3 M with $24.8 M due to price and $7.4 M due to efficiency. The variance due to product mix was $21.9 M. There were no major efficiency variances and only one major price variance $11.4 M for titanium dioxide.
Plasticizer
Month
Per Day
Y.T.D.
Production, M Pounds Accounting Days
805 50.3 31
7,205 212
Plasticizer operated 16 days during July at an average rate of 50.3 M pounds per day. Production included: D0P, DIDP, and 61 OP.
VRP production totaled 72.9 M pounds (9-1%). Production was limited by: R-2 stub shaft repairs, R-2 vacuum valve replacement, R-4 safety disc replacement, and R-4 instrument repairs. Two other major factors limited plasticizer production: steam allocation due to boiler repairs and out of ALF0L 610 due to rejected shipment for high moisture.
The raw material requirement for plasticizer was 1.06691 pounds of raw
materials per pound of plasticizer versus a 1.10500 standard. (Y.T.D. is
1.11320)
The variable cost for plasticizer was $9-1 M with $9.14 M due to price and ($0.04 M) due to efficiency. The only major price variance was $11.3 M phthalic anhydride and the only major efficiency variance was ($12.7 M) for phthalic anhydride.
The variance due to product mix was ($1.7 M).
General
Total customer grade compound inventory increased from 8.9 to 10.1 MM
pounds during July.
Line I Banbury repairs are scheduled for August in order to reduce the mill scrap production rate.
Two new compounds were produced for Belden du'ing July.
DTH 000021756
MAINTENANCE - S. J. Vincent
Vinyl
There were no reactor seal failures in this period. One reactor condenser was cleaned and one gearbox experienced a failure. The condenser cleaned was on the 741 reactor in the new module. The gearbox failed on the D-400 reactor. The gearbox and seal housing had to be removed from D 400 reactor. The seal housing was sent out for sleeving and the gearbox was overhauled. The motor was also removed for a service check. The safety valves were tested and the safety discs were changed on both the D-300 and D-400 reactors in the old module. The VCM charge header in the old module from the filters to the charge meters was removed for cleaning.
The VCM turbine meters were pulled and cleaned twice. There were five major valves replaced in this period. In the old module the inlet valve to the north VCM filter and the VCM charge valve on D-400 reactor were replaced. In the new module the slurry dump valve and the recovery valve were replaced on 741 reactor and the vent valve on 742 reactor.
In the old module the south recovered VCM receiver was opened for cleaning and the south recovery condenser. The flow controller for "B" recovery compressor was replaced. The level control for D-300 and D-400 cooling tower was calibrated.
There were fourteen repairs to pumps and compressors in the vinyl production area in this period. In the old module the recovered VCM charge pump and rinse pump were overhauled and then the spare "A" vacuum pump was installed. Seals were replaced in the east and west VCM return pumps, east and west VCM charge pumps, "A" compressor outboard seal, "A" vacuum pump inboard and outboard seals, 705 emission recovery compressor outboard seal and the 703 emission recovery vacuum pump outboard seal. In the new module the third recovery compressor was reinstalled and the seal replaced on the west chem-wash pump.
Repairs to the vinyl drying equipment were to change out the #6 centrifuge and gearbox twice, and the #5 centrifuge and gearbox once. The repairs were the result of plugging and resulting plastic accumulation in the conveyor section. The drum drive gearbox on #2 dryer was overhauled with the drive sprocket and chain being replaced. Several blend tank level transmitters were checked.
A major problem developed with the use of the Conoco HD calcium grease. Several bearing failures were directly attributed to the breakdown of this grease. Information has been received that indicates there may have been a blending problem with the HD calcium. Due to the recommendations of our equipment suppliers and the bearing failures experienced, an alternative grease has replaced the Conoco HD calcium and we are currently completing our stock changeover.
DTH 000021757
MAINTENANCE - (continued)
Compound, Dry Blend, Plasticizer and Resin Storage
The major repairs in the compound area were to replace the FCM seals, rotary joints, the conveyor belt to the mill and the mill rotary joints on line three. The bucket clutch and flex line to the mill rotary joint were replaced on line one. Line I blender conveyor bucket continues to drop from its chain and cause problems. Dicer blades continue to be a major maintenance cost item for both compound lines. Two dicer motors were repaired.
The dry blend unit was shut down to replace the #2 bowl and to repair the #1 Welex bowl. The switchgear was also serviced. The mixer blades were replaced in both Welex units and the screen was replaced in the south Kason screener. Several blender and feeder valves were repacked. Repairs to the plasticizer unit were to replace seals in the PA charge pump, tank 109 pump and to overhaul 110 tank pump. The safety disc was replaced on R-4 reactor.
Utilities and Service
There were six repairs to the plant air system compressors during this period. Valves were repaired twice in the #2 and #3 compressors and once in the #1 and //6 compressor. The plant breathing air system revisions were completed in this period. The //I and #3 boilers were shut down for inspection and repair. All boiler tubes were hydro-blasted, followed by chemical cleaning. There were two tubes plugged in #1 boiler and eight tubes plugged in #3 boiler. The refractory was repaired in both boilers.
The tool room mechanics completed bench testing of the new safety valves for the relief valve modification and expansion projects. The plant machinest and air conditioning mechanics were very productive this month, machining parts and maintaining the plant air conditioning systems.
Planner
There were 78 work orders planned and estimated in this period.
There were 22 registers closed and 23 new registers issued.
Material was ordered for 26 projects.
The planner worked with Tom Knuckles from MED on planning the upcoming new module shutdown.
Miscellaneous
Four mechanics were given- training in the operation of the plant crane.
New columns have been installed in our plant gas chromatographs. The conduit and cable have been installed to add amp meters in the old module recovery system. The installation of the instrumentation for the spare inert vent incinerator has been started. New level controls were also installed in the dry blend use bins.
DTH 000021758
MECHANICAL ENGINEERING - J. A. Dixon
AFE's Submitted, Approved, and Closed
The following AFE's were submitted and approved during July:
AFE No.
Title
Authorized
9671
"^1-------- " 9691 9701
9711 9721
New VCM Railspu?2!7> Miscellaneous Projects Under $10,000 Reactor Agitator Two Speed Motors Miscellaneous Energy Savings Projects
Under $10,000 Plasticizer Spill Containment Emergency Cooling for Reactors
$194,000 145,000 40,000 25,000
42,000 190,000
The followin g AFE's were closed to field charges during July:
AFE No.
Title
Authorized
9639 9719 9590 9521
Revisions to Emission Recovery System Aberdeen PVC Resin Expansion Critical Spare Equipment New VCM Rai1 spur
$100,000 850,000 59,000 11,000
A completion report was issued for the following AFE:
AFE No.
Title
Authorized
9751
Centrifugal Air Compressor Repair
$ 45,000
Design
Design work is in progress on the following projects:
Resin Reclaim System Emergency AMS Kill System Modifications to Make Profile Dry Blend Compound Line III Debottlenecking Fire Protection Improvements - Phase III V-10 Centrate Heat Recovery Vinyl Initiator Charge Pots Reactor Seal Access Platform Slurry Delumper New Storage Track Plasticizer Irritant Control CenIrate Heat Recovery
AFE Activity
1 . AFE 9729 ~ Fire Protection Improvements - Phase III - M. Ingle & J. P. McKee
Construction of the pump house is complete. The jockey pump has been installed. Piping and electrical are 95% complete.
DTH 000021759
MECHANICAL ENGINEERING - (Cont.) AFE Activity - (Cont.) 2. AFE 9570 ~ Replace T-101 P. A. Tank - J. P. Windham
Drafting and purchasing is complete. Construction bids have been requested. 3- AFE 9600 - Calcium Stearate Addition System - M. S. Richards
The storage tank and agitator are on order. Tie-ins are planned for the shut down in the new module. Electrical design is in progress. **. AFE 9630 ~ Water Stripping (Air) - M. Ingle & J. L. White This project is operational. Minor modifications are in progress.
5. AFE 968O - Fixed Point Monitor Data Computer and Warning Lights - R. B. Harned
Construction is progress. There was a delay in shipment of the computer from Ponca City. The delay should not affect project completion. 6. AFE 9710 ~ Fire Protection Improvements - Phase III - J. B. Elkins & W. J. Modica Engineering is approximately 70% complete and drafting is 50% complete. 7. AFE 9730 ~ Compound Line III Debottlenecking - J. J. Tomek Structural design is in progress. Request for quotes were sent out for all major equipment. Planning data is being prepared to evaluate the alternate silo locations. 8. AFE 9760 - Emergency AMS Kill System - J. L. White Piping drawings for the new reactor area are being checked. Instrumentation drafting is in progress. 9. AFE 9770 ~ Reactor Pressure Relief Modifications - J. L. White All material has been been received. Installation of relief valves and reactor studding out 1ets are scheduled for August. 10. AFE 9790 ~ Resin Reclaim System - P. H. Meiers & M. S. Richards Design is approximately 50% complete. Piping approval drawing are read for review and comments. Equipment purchasing is proceeding. 11. AFE 9800 - Plasticizer Irritant Control (Air) - R. Milner & R. B. Harned Design work is complete for installation of the pond aerators. Bid packages have been prepared and bids are due in August.
DTH 000021760
MECHANICAL ENGINEERING - (Cont.)
12. AFE 9531 ~ Vinyl Initiator Charge Pots - S. Jones & J. P. Mckee Piping drawings are being revised per approval comments. Instrumentation engineering is 50% complete and drafting has just begun.
13- AFE 95^1 - VCM Tank Farm Modifications - R. B. Harned The contract has been let for the mechanical installation. The electrical and instrumentation bid packages have been issued and bids are due in August. Piping tie-ins will be installed during the august shutdown. AFE 80-895 - Interplant Communication - Phase II - R. B. Harned The Gaitronics stations have been received. The installation of conduit for the additional stations is nearly complete.
15- AFE 9551 - V-10 Centrate Heat Recovery (Energy) - S. Jones & J. P. Mckee Foundation drawings are complete and mechanical drawings are being checked. Instrumentation engineering is 1*5% complete and electrical engineering is 25% complete.
16. AFE 9561 - Cooling Tower Fan Controls - R. B. Harned Specifications for control sequences and thermowells were finalized. Control units are scheduled to ship in August.
17- AFE 9581 - Dryer Building Ventilation - J. P. Windham Installation of the fans in the dryer buildings is in progress. Electrical installation is scheduled for early August.
18. AFE 9591 ~ Sifter Overflow Reclaim System - J. P. Windham & R. E. Milner The control system design has been revised and completed. Equipment specifi cations are being prepared. Purchasing of instrumentation is in progress.
19- AFE 96*41 - Slurry Delumper - M. S. Richards The mechanical design is 65% complete. The electrical design is in progress. The piping tie-in will be installed during the August shut down.
20. AFE 9671 " New VCM Rail spur - Herzog-Hart & J. A. Dixon The constract was let in July. Construction is scheduled for August and September. Completion is scheduled for the first week in October.
DTH 000021761
MECHANICAL ENGINEERING - (Cont.)
Construct ion - G. A. Morgan The following projects were completed in July: 1. No. 2 Pond Bypass. 2. Fire Protection Jockey Pump 3. Demolition work - Batch Water Stripping k. Curbing of Fire Training Ground and Plasticizer Tank Farm Fuel Storage Areas. 5. Air Conditioning of Warehouse Ladies Rest Room. 6. Noise Abatement Projects 7- V--11 Dryer Building Walkways 8. Clean out of API Separator 9. Painting of 281-677 Silo Walkway 10. Miscellaneous roof leaks 11. Breathing Air Modifications The following contracts were issued during July: l. New VCM Rai1 spur 2. NPD No. 2 Pond Bypass 3. Revise Main Restroom Ventilation k. Installation of Piping, Equipment and Structural for VCM Tank Farm Revisions. 5. Installation of Relief Valves, Piping and Structural for New Module Relief
Valve Modifications. Forty register tickets were issued during July.
DTH 000021762
ABERDEEN AUTHORIZATIONS REPORT
(?) Thru July, 1981
AUTH. CAPITAL NO. DESCRIPTION
DATE
AUTH.
APPROVED AFE AMT.
(1) EXPENDEO TO DATE
(2) COMMITTED
TO 0ATE
FINAL TOTAL EST. COST COMP.
UNDER (OVER) AUTH. AMT.
EST. EST. COMP . CL0S. DATE DATE
REMARKS
9609 9629 9639 9689
Reactor Inert Vent System Air Compressor
Revisions to Emission Recovery Sys. Diking of Sphere & Curbing of
Drum Storage Areas
6/28/79 7/9/79 7/12/79 9/15/79
90.000 340,000 100,000 170,000
14.541 302,079
80,260 137,578
14,541 307,808
96.849 159,078
90,000 308.000 100,000 170,000
0 32,000
0 0
12/81 3/82 6/81 9/81 7/81 10/81 9/81 12/81
Project on hold. Closed to field charges. Closed to field charges. Revisions in progress.
9699 9709 9719 9729
9759 9530 9550 9560 9570 9590 9600 9630 9660 9670 9680
9690 9700 9710
Plant Oryer Debottlenecking
9/15/79
Facilities for Multiple Grade Resin 9/20/79
80,000 870,000
Aberdeen PVC Resin Expansion
9/10/79
850,000
Fire Protection Improvements Phase 11
10/1/79
490,000
Aberdeen PVC Resin Expansion Spare Incinerator
12/10/79 11 ,150,000
1/23/80
650,000
P.A. Handling Improvements
3/3/80
63.000
Safety Equipment
3/12/80
25,000
Replace T-101 P.A. Tank
3/27/80
119,000
Critical Spare Equipment
3/26/80
59,000
Calcium Stearate Addition System
4/2/80
84,000
Water Stripping
4/30/80
810,000
Hot Water Charge Tank Replacement
6/4/80
160,000
Laboratory Equipment
7/9/80
32,000
Fixed Point Monitor Data Computer and Warning Lights
9/4/80
113,000
8reathing Air Modification
9/9/80
21,000
Compound Fines & Streamers Removal 10/1/80
95,000
Fire Protection - Phase ill
10/14/80
385,000
47,670 496,690 887,200 353,624
74,950 660,625 887,200 381,828
6,737,800 9,542,300
394,203 450,225
32,470 32,574
26,575
29,288
64,699
70,590
11,431
60,406
12,929
18,726
382,294 389,261
141,632 141,948
30,334 31,034
40,870 79,870
9,394 0
1,707
15,144 29,524 1,707
80,000 725,000 887,200 490,000
10,450,000 550,000 63,000 29,288 119,000 60,406 84,000 510,000 160,000 31,034 113,000
21,000 95,000 385.000
0 12/81 3/82 145,000 12/81 3/82 (37,200) 7/81 10/81
0 9/81 12/81
Construction In progress. Construction in progress. Closed to field charges. Construction in progress.
700,000 12/81 3/82 100,000 10/81 1/82
0 12/81 3/82 ( 4,288) 5/81 8/81
0 12/81 3/82 ( 1,406) 7/81 10/81
0 12/81 3/82 300,000 10/81 1/82
0 6/81 9/81 966 12/80 9/81
0 9/81 12/81
Construction in progress. Construction in progress. Engineering In progress. Closed to field charges. Bids requested. Closed to field charges. Engineering in progress. Revisions in progress. Closed to field charges. Closed to field charges. Construction in progress.
0 8/81 11/81 Project operationaT. 0 10/81 1/82 Engineering scheduled. 0 10/81 1/82 Engineering in progress CED.
9720 9730
Reactor Agitator Replacement Compound Line III Debottlenecking
10/14/80 420,000 10/16/80 1 ,350,000
9740 Modifications to Make Profile Dry Blend
10/27/80 200,000
9750 Rotary Dryer Insulation (Energy)
11/10/80
22,000
9760 Emergency AMS Kill System
11/15/80
335,000
9770 Reactor Pressure Relief Mod.
11/25/80 560,000
9780 Centrate Heat Recovery
12/8/80
300,000
9790 9800
Resin Reclaim System Plasticizer Irritant Control (Air)
12/14/80 12/15/80
727,000 80,000
9810 Replacement Gearbox for Farrel Mixer 12/18/80 . 73,000
9511 9521 9531 9541
Miscellaneous Projects Under $10,000 1/9/81
New VCM Rail spur
1/30/81
Vinyl Initiator Charge Pots
1/21/81
VCM Tank Farm Modifications
1/21/81
170,000 11,000
165,000 90,000
80-895 Interplant Communication-Phase II
1/22/81
55,000
9551 V-10 Centrate Heat Recovery (Energy) 2/17/81
125,000
9561 Cooling Tower Fan Controls (Energy) 2/17/81
40,000
9581 Dryer Building Ventilation
3/20/81
23,000
9591 Sifter Overflow Reclaim System
3/20/81
200,000
9601
Compliance with EPA VCM Standard (Air)
3/25/81
72,000
9611 Recovery System Revisions
3/25/81
30,000
9621 Laboratory Equipment
3/25/81
42,000
9631 9641
Ground Water Monitoring (Solid) Slurry Delumper
3/24/81 5/14/81
30,000 35,000
9651 9661
Safety Equipment Waste Water Treatment Rev. (Water)
6/8/81 , 6/19/81
106,000 560,000
9671 9681
New VCM Ra i 1 spur
6/30/81
Miscellaneous Projects Under $10,000 7/31/81
194,000 145,000
9691 9701
Reactor Agitator Two Speed Motors
Misc. Energy Savings ProJ. Under $10,000
7/2/81 7/13/81
40,000 25,000
9711 Plasticizer Spill Containment
7/27/81
42,000
9721 Emergency Cooling for Reactors
7/30/81
190,000
191,623 17
16,969
191,753 69,517 55,460
420,000 1,350,000
200,000
20,000 66,996 98,333 23,967 123,133 28,557
0 115,798
17,612 5,534
26,676 0
7,641 0
1,101 0 0
27,391 94,367 338,849 61,528 234,610 31,810 69,400 187,820 17,612 39,505 49,154 31,755 23,739 19,840 15,149 14,877 12,434
27,391 335,000 460,000 300,000 727,000
80,000 73,000 170,000 17,612 165,000 90,000 55,000 125,000 40,000 23,000 200,000 72,000
7,415 31,400
467 0 0 0 0 0
0 0
14,110 38,516 17,071 20,746
0 0 189,512 2.478
0 0
30,000 42,000 30,000 35,000 106,000 560,000 194,000 145,000
40,000 25,000
0 0 42,000 0 0 190,000
0 10/81 1/82 Agitators received 0 6/82 9/82 FCM barrel to ship 10/81. 0 10/81 1/82 Engineering in progress.
( 5,391) 8/81 11/81 0 10/81 1/82
100,000 12/81 3/82 0 3/82 6/82 0 3/82 6/82 0 9/81 12/81 0 10/81 12/81 0 12/31 2/82
( 6,612) 7/81 10/81 0 11/81 2/82 0 1/82 4/82 0 9/81 12/81 0 5/82 8/82 0 11/81 2/82 0 9/81 12/81 0 3/82 6/82 0 12/81 3/82
803 complete. Engineering in progress. Construction in progress. Engineering In progres.. Engineering in progress; CED Engineering in progress. Gearbox to ship 10/81. Sixty-two projects approved. Closed to field charges. Engineering in progress; CED Construction in progress. Revisions In progress. Engineering in progress; CED Equipment on order. Construction in progress. Engineering in progress. Engineering in progress.
0 12/81 3/82 Revisions in progress. 0 8/81 11/81 Equipment on order. 0 10/81 1/82 Contract let. 0 2/82 5/82 Engineering in progress. 0 6/82 9/82 Engineering scheduled. 0 9/82 12/82 Engineering scheduled. 0 12/81 3/82 Construction in progress. 0 12/81 3/82 Five projects approved.
0 4/82 7/82 Updated quotes requested. 0 12/81 3/82 Engineering scheduled.
0 1/82 4/82 Engineering scheduled. 0 4/82 7/82 Engineering scheduled.
EXPENSE
9020 Repairs to Line 1 Compounder
11/24/80
38,000
0
0
38,000
0 11/81 2/82 Parts ordered in January.
DTH 000021763
PERSONNEL - R. A. HILLER
EMPLOYMENT Romona Faulkner - Steno Clerk TO/FROM LEAVE OF ABSENCE None. TRANSFER/PROMOTION John Sutton transferred from the Compound Department as a Compound Operator to the Warehouse Department as a Warehouse Worker "B". Bernard Garth transferred from the Service Warehouse Department to Trans portation Warehouse. RETIREMENT None. TERMINATION Frank Brewer, Casual Labor Cleveland Brown, Jr., Casual Labor David Volz, Casual Labor OTHER During July there were 15 casual labor employees on payroll. Total hours worked were 2583.75.
DTH 000021764
CONOCO CHEMICALS Aberdeen, Mississippi
July 1981 MONTHLY PERSONNEL REPORT
Salaried Employees
87
Minority Employees #
Hourly Employees
161
Salaried
6
n
Total Employees Employees (Hourly)
248*
Hourly Total
59 m 65 26
New Employees Terminations
Hourly Min. Hired % Min. Hired
Hourly Min. Term. % Min. Term.
DEPARTMENTS PAR # EMPLOYEES min. emp: . % MIN. NEW HIRES YTD TERM. YTD TURNOVER YTD
Warehouse
11
9
' 1
11
0 0 00 0 0
Gen. Plant Maintenance
11 52
13 48
5 38% 0 10 0 0 0 0 8 17% 0 0 0 | 5wV 0 0
Laboratory Compound
22 37
20 35
4 20% 0 0 0 0 0 0
26 74% 0 0 0 0 0 0
Vinyl
Plasticizer -
40 4
32 4
13 b0% 0 0 0 0 0 0 2 50% 0 0 0 -0 0 0
Number of Applicants:
Month
0 Year to Date 103
APPLICANT BREAKDOWN:
# Minority ^ Female
0 0
% Minority % Female
0 0
, 'Includes eight (8) temporary employees. **lncludes one (1) retirement. Retirements
are not included in turnover rates.
Hires (Hourly) :
Month
a
Year to Date
Terminations (Hourly) :
10
Month
0
Year to Date
1 *'
Overall Turnover
0
Projected Annual Turnover _____ 0
DTH 000021765
4)
10
o
Loi
i m 0)
W^
ia u>
w
^n
w <k>
ca cr\ O -a-
<r**->*
ca
<K> d-P
** O
<rK^>. o<*o?
-a- -r
d-p cnj
<h> --
o
oo
d-e ca
to t--
O
&$
<0
(ft o 03
43
o tA c eft
43 43 eft c -Q
<u to
o cdP o o
*? o oo
&?&$&?
dP
oo o
o
la o o o o 0 a\
rsJtOCg-3-COOOOCO
tA -- CA
OO
LA --
CO
Xto
CO cn >* 3
cc
LlJ
> o
L. 1_ 43 4-1
> to
oo vO *3" -- CO
LAAJ
H Jal 0i-3 t3-
4-* O
to X
LrA*>LA rgOLAtAcMO orL,*A .iOAPvLA.rLsA
03 vD N \C<A Cr-O* r.--- to CAr-. oo oo
CT3
Lr-A.
(N
aO-
-3*
LA LA vO r-.
AJ
O
vO oo -a*
CN
41
O >*
4) C
4->eft 03 o
3
o
C 43
03
01 4) C 0
CL
a4)
01 3
<D X
.o 01
41
3
O X
01
c 43 o 03
N CO Q_
U
>* (ft C 03 >K
03
(ft c
o
eft c o <0
l_ a> m a.
L. o
43 O. c
o
c >. <0 *o
> <0 *o
(ft
X
0> (ft
4) c
o
03 (ft C
L-
o
5
*o c (0
> <0 *o 03
c
0 -C 1_
0 01 3
c *o
oc
0) (ft t_ >.
o3 01 "O
L- O
03
3 01
03
0) C Uo
0c3
(ft L.
3
O L.
o
2
01
O
3
Oi
4) 4)
3
o
03
01 C
E
L.
o 4) 5 > O0
03
c TJ
3
o
4X3
DTH 000021766
PROCESS ENGINEERING - R. A. Frohreich
A. Expans ion
Work is continuing in all areas of this project. Tie-ins in the new module reactor area will be made during the scheduled shutdown of the area in early August. Also utility tie-ins will be made at this time. A meeting was held with PED to review the initial issue of the Fluid Bed Dryer oper ating manual. The plant is preparing the operating procedures for the other areas. Change orders for spare cooling water supply pumps, a deaerator for the boilers, a boiler feedwater pump, a spare rotating assembly for the centrifuges, an additional product silo, and a reactor seal access platform were approved. Engineering on these projects will begin in August.
B. Emergency Reactor Cooling System
The class "A" design to provide emergency cooling and backup instrument air was issued and the AFE request for the project was submitted.
C. Dryer Area Vacuum Clean-Up System
The class "A" process design to provide a vacuum cleaning system for the dryer areas is being prepared.
D. Reactor Venting Problem
Work has began to determine the composition and source of the inerts which build up in the reactors during polymerization.
E. Normal Kill Solution Addition System
The class "A" design to provide mixing, storage, and metering the normal kill solution was issued. This design consists of a tank, a drum pump, a transfer pump, a filter, and piping to the reactor injection pots in both reactor modules.
F. 10-8 Plasticizer Production
The class "A" design to provide 10-8 alcohol and 10-8 plasticizer storage and transfer facilities is being prepared.
G. Glycerin Make-Up System
The class "A" design to revise the glycerin make up system is being prepared.
H. Dryer Optimization Study
Several tests were conducted on rotary dryer number 1 in which drying air flow rates were reduced. Preliminary results indicate that energy savings may be realized without adversely affecting dryer resin rates. Further tests will be conducted toassure that drying rates are not reduced at the lower air rates.
DTH 000021767
PROCESS ENGINEERING (Cont.) I. Batch Water Strippers
Process engineering continued to provide support for the operation of the batch water strippers. A process design to install an automatic flush for the new module transfer, 1ine was issued. J. 1982 Capital Budget Work continued on preparation of the 1982 Capital Budget. The second issue of the budget was issued.
DTH 000021768
ENVIRONMENTAL - V. E. Messick
Particulates
Two dryer exhausts were sampled for particulates and were within allowable 1imit s .
Water
All parameters were within NPDES limitations in July.
The quarterly NPDES discharge monitoring report was submitted to the state of Mississippi.
The API separator was cleaned out in July. The material removed from the API was placed in drums and prepared for disposal at Chemical Waste Management.
VCM
The compliance test for the batch water strippers was conducted on July 2$. Stripping results were well below the 10 ppm VCM process waste water limit. test report is being prepared.
The
Hazardous Waste Management
A total of 320 drums of hazardous waste were shipped to Chemical Waste Manage ment's Alabama site for disposal. Manifests have been received for two of the four shipments.
DTH 000021769
Flow GPM
Jan. _ Ave. 1069 Max. 1297
Feb. - Ave. Max.
757 819
Mar. - Ave. Max.
753 790
Apr. - Ave. 946 Max. 1200
May Ave." 846 Max. 1200
June _ Ave. Max.
' July Ave. Max.
739 917
746 922
Aug.
Ave. Max.
Sept. - Ave. Max.
Oct.
Ave. Max.
Nov. _ Ave. Max.
Dec.
Ave. Max.
NPDES
Ave. Max.
.
-
TABLE I
-WATER COMPLIANCE WITH
NPDES PERMIT PARAMETERS
BOD PPM LB./DY.
39 504 57 887
COD PPM LB./DY.
69 888 106 1650
Sus. Solids PPM LB./DY.
7 93 9 114
Diss 02
11
95 ,
43
382
18
154 .
56
479
10 90 11 103
36 330 51 466
10 118 20 253
31 360 41 519
12 125 14 163
43 470 54 629
20 I83 34 314
12 107 16 130
56 502 79 729
39 339 53 420
7 65 8.9-9.8 10 86
11 93 8.3-8.9 17 139
13 151 8.2-8.9 19 240
13 138 7.4-8.4
17 198
-
18 157 6.2-8.2 27 249
22 190 28 209 6.2-7.5
32 431 43 800
_ 1462 - 2713
_ 674 - 1396
6.0
-=r
0
1
LTV
OO
ph 7.4-7.8 7.5-7-9 7.6-7.7 6.9-8.1 7.3-8.0 7.6-7-9 7.7-8.0
6.0-8.5
DTH 000021770
ENERGY CONSERVATION
J. F. Perez-Velasco
I. Plant Operations
Total energy consumption for July was 10^4.037 MMM BTU's. The energy consumption per pound of product increased to 3188 BTU/lb. as compared with 3088 BTU/lb. for June.
I I. Plant Energy Conservation Program
Steam Leaks
Twenty-one (21) steam leaks were repaired in July.
Boiler
Boiler #1 and #3 were shut down for repairs during July. Opportunity was taken at that time to acid clean the tubes and make visual check of boiler #3 economizer.
Energy Reporting
Second quarter report was prepared during July. A CMA adjusted energy
savings of 38.8% was obtained for the three month period versus 1972
equivalent energy usage.
DTH 000021771
ITEM
Control Period
Production, MM Lbs.
Resin Dry Blend Compound Plasticizer
TOTAL
Natural Gas
Consumption, MSCF Conversion, BTU/SCF Energy Consumption, MMM BTU
Electricity
Consumption, MM KWH Conversion, BTU/KWH Energy Consumption, MMM BTU
Propane
Consumption, M Gal. Conversion, BTU/Gal. Energy Consumption, MMM BTU
Total
Energy Consumption, MMM BTU Energy Consumption , BTU/Lb.
Boiler Operating Data
No. 1 No. 2
No. 3
ENERGY CONSERVATION DATA
1981
July
23.4 3.8 4.5 0.9
32.6
49354
1020
50.341
5.3696
10000
53.696
0 .92000
0
Avg. Stack Temp. 1981
360 367 328 415
293 413
O
CO CP
104.037
3188
Avg. % Excess Air
1981
1980
52 25 31 27 38 23
1980
July
17.0
2.2
3.4 0.9 23.5
33298
1020
33-964
4.2555
10000
42.555
0 92000
0
76.519 3256
DTH 000021772
LABORATORY - R. D. Jackson
CUSTOMER COMPLAINTS
Customer
Products
Complaint
Report By
L. B. Plastics, Inc.
80273G
Wet Dry Blend
RDJ
WAIVERS
Date
Identification
Product
Customer
Reason
7-6
7-7 7-20 7-20 7-24 7-24 7-28 7-28
7-29
CONX 45258 CONX 45755 PLCX 43707 CONX 45713 CONX 45797 CONX 45768 PTLX 41835 CONX 45718 T2 8ll
80273G
5385-3 5385-3 5385-3 80273G 80273G 5385-3 5385-3 5305
Kebco World of Plastics World of Plastics Charlotte Pipe Northern Waterworks Kebco World of Plastics Charlotte Pipe Celanese Pipe
Equi librium Torque Particle Size Bulk Density Particle Size Equilibrium Torque Equi1ibriurn Torque Particle Size Particle Size Viscosity
PRODUCT SERVICE & DEVELOPMENT
CJM RDJ ELK ELK CJM CJM ELK ELK RDJ
Sample Shipments
Ship Date
Product
Amount (Lbs.)
7-1 7-1 7-1 7-2 7-3
7-8 7-10 7-14 7-14 7-17 1-11 7-28 7-29 7-30 7-31 7-31 7-31
16851 CL BL 50
25
5425-0G
20
35851 Nat.
50
5385
10
5385-1
10
5425
10
5465
10
38631 Nat.
50
34711 Grey
100
38551 Nat.
100
16851 CL BL 50
100
5305-1
4,500
RP 100 DB
20
5305
2,000
5385-1
10
80273G DB
220
5425 0G
' 4,500
5385-3
150
16851 CL BL 50
50
Customer
Americhem Inc. Ca r1 on Interstate Wire Corp. Conoco, Ponca City Stauffer Chemical Co.
Requested By
KJQ NBB KJQ RBM DLG
Taylor Cable Co. Atco-Flex Inc. Taylor Cable Co. Advanved Plastic Corp. Conoco , Ponca City Jim Walter Research Corp. Conoco, Ponca City Fritz Airfreight Mitsui & Co. Inc. Bristol Products Petrolite Corp. Therma Tru
MFM JFN MFM MFM COEDS CJM COEDS JPM COEDS COEDS COEDS DD
DTH 000021773
LABORATORY - (continued)
COMPOUND DEVELOPMENT AND SERVICE
Special Compound Testing
Specification tests were run on five (5) production lots of Western Electric compounds - 1 lot each of 3^861 Gray 546, 34862 Gray 546, and 36862 Natural and 2 lots of 36861 Natural. Plasticizer content and flammability were tested on eleven (11) shipment samples.
Testing is partially complete on the first production lots of 48651 and 48961 for Bel den.
Compound Property Verification
Property testing is complete on twenty (20) active compounds.
Dry Blend Development
Quality control standards were prepared for 80174, 80273G and 90171 dry blends.
QUALITY CONTROL TESTING
Resin
Regular Samples = 442 Bag Samples = 41 Other In-Process Samples = 3092 Bulk Shipment = 181 (Railcars =
99; Trucks
82)
Dry Blend
Blenders Produced = 410 Blenders Tested = 408 Blenders Adjusted = 17.8* Other In-Process Samples = 558
Bulk Shipments = 36 (Railcars
15; Trucks
21)
Compound
Blenders Produced = 720
Blenders Adjusted = 2.5%
Line 5 Production = 33 skids Other In-Process Samples = 223 Bulk Shipments = 16 (Ra i 1 ca rs
13; Trucks
3)
DTH 000021774
LABORATORY - (continued)
QUALITY CONTROL TESTING (continued)
Resin Heat Stabi1 i ty
Oven heat stability tests were run on fifty-eight (58) blends of resin. All the samples were acceptable, and 5305 and 5465 resins continue to average a little better stability than 5385 and 5425.
Raw Material Testing
Eighty (80) lots of plant raw materials were tested and accepted. Several lots of Ongard 2 flame retardent would have been rejected for poor dispersion if the supplier had been able to supply better materials. They insist that better dispersing Ongard 2 will be available soon.
Two samples of Halthal EP lead stabilizer have been tested and compared with
Cyastab 988 and Dythal XL. The Halthal EP disperses easily but does not
stabilize quite as well as Cyastab 988 or Dythal XL.
Americhem 2013"T1 gray color concentrate has been tested and approved as a
substitute for Wilson 32-GY-18 in making Western Electric 34861 Gray 546.
Americhem 1943-T2 gray color concentrate was tested and approved as a sub stitute for Wilson 32-GY-16 gray. We are replacing Wilson products with other materials due to Wilson's deteriorating quality and poor response to our complaints.
RVCM of Shipment Samples
The following shipment samples were tested.
Product
# Samples
Average RVCM, ppm
5305 5385 5425 5465 Dry Blend
120 48
15 3
11
1,1 0.4
0.1 0.1 0.4
MISCELLANEOUS PROJECTS
Volume Resistivity Testing
Samples of 5425 and 5465 resin were tested for volume resistivity (VR) and all values were good. Twenty-seven (27) specimens from Ponca City were tested for VR and reported. Their resistance testing equipment was out for repair.
DTH 000021775
LABORATORY - (continued)
MISCELLANEOUS PROJECTS - (continued)
RVCM Of In Process Samples
The following in process samples were tested for residual vinyl chloride (RVCM).
Sample Type
# Samples
Average 1
Reactor slurrys Batch Water Stripper 5305 Drier Sarnples
624
47 124
165 6.4 2.2
None of the reactor daily averages exceeded 400 ppm.
Viscosity
A total of 751 dilute solution viscosity measurements were made on resin in July.
Spec! al
A total of 110 special samples were tested in July. Most of these were the waste water samples for COD analysis.
Dosimet ry
A total of 111 personal dosimetry samples were tested for VCM content in July.
Computer
New programs were prepared for the lab computer to permit L S N particle size data to be entered and stored implace of screen data.
DTH 000021776
TRANSPORTATION - J. E. Stark
Shipment By Product - M Lbs.
Res i n PIasticizer Dry Blend Compound
TOTAL
Jul y
15,617 76
3,220 3,557 22,470
Year to Date
137,754 672
27,092 27,111 192,629
Number of Shipments by Mode R/C
O.T. Bulk
O.T. Van C.O.T.
C.C.
TOFC CPU TOTAL
Resin
- Bulk
77 49
126
- Package
7 2 9 18
- Export
8 35
43
PI asticizer
22
Dry Blend - Bulk - Package - Export
18
7 3
Compound - Bulk - Package
TOTAL
9 To?
3 28
~To "80
Backhauls for July
27
Number of Shipments by Month - Year to Date
0
21 39 7 3
12 5 15 48 7 IT T7 ~23$
3 30
R/C Bulk Var. C.O.T. C.C.
TOFC CPU Tota 1
January February March April May June July
91 48 200
91 55 172
132 65 208
96 38 181
111 49 120
123 55 104 60
74
80
2 91 0 40 6 54
0 11 03 05 07
0 55 487 0 58 416
0 74 539 0 69 395 0 68 351 0 50 307 0 47 298
Material Handling Report
Packaged Resin from Production Packaged Compound, Dry Blend from Prod. Transferred from Main to Prairie Transferred from Prairie to Prairie Reverse Transfer Resin to Plant Reverse Transfer Cmpd. to Plant Shipment from Warehouses Special Packaging Transferred from Prairie to Main
TOTAL
M/Lbs. 2,228
3,119 2,349
81 810 243 1,903
1,539 1,580
13,851
T/L
55
77 58
2
20
6
47 38 39 3W
DTH 00002177l
TRANSPORTATI ON - (continued)
Off-Grade In Storage
Material
Sifter Overflow Resin "BC" Resin "H" Mi 1 1 Scraps Compound "B" Compound "H" Dry Blend "O.G."
TOTAL
M/Lbs.
598 3,^87
5 kk 7k
1,28k 16
602
S"505
T/L
15 86 13
2 32
0 15 TSJ
DTH 000021778
LOCATION MAIN-East
TOTAL M SQ. FT.
48
Prairie 12-1
12
12-2 12-3
22 21
12-4
12-5
22 21
12-6
21
12-7 12-8 12-9 12-12
21 21 21 21
Total
251 _
CONOCO TRANSPORTATION
. ...July 31. 1981
ABERDEEN WAREHOUSE CONTENTS
ESTIMATED MM POUND ON FLOOR OPEN TO
Compounds
6. 0
Dry Blend
.3
Export Resin
.4
Conoco Resin
HDPE
Dry Blend Conoco Resin
.4 .1 2. 4
____k.7. 3.3 10.0
....... 5. :ii.,o
2.4 i .i
1.5 3.5
Conoco
.3
Export Resin
.8
1 . 1 2 .4 3.5
Conoco Resin Resin O.G.
4. 4
*' 4* A
*
3.5
Mill Scraps
.1
Cmpd O.G.
.8
Dry Blend O.G.
.5
Sifter Overflow
.3
Resin O.G. Compound
.2 .1
1.9
.6 2.5
ro
00
Resin
Raw Material
.2
3.1
. 4 3.5
Resin O.G.
3. 3
3.3
. 2 3.5
Conoco Resin
4. 0
* 4.0
3.5
Conoco Resin
.6
. 6 2 . 9 3.5
Dry Blend O.G.
.1
S.O. .. 3
Comp. O.G.
Mill Scarp Sub-Total (Plug-Aisles)
Total Conoco
.4
_____ u-L
DTH 000021779
. 9 2 . 6 3.5 * 42,0
28 . 9 14 5
1. 4 43. 4
MED I CAL CASES
8
ABERDEEN CHEMICAL PLANT INJURY PERFORMANCE
6
b
2
0
40 30 20 10
0
REQUENCY = TOTAL INJURIES (FA OR MC) X 12 TOTAL EMPLOYEES
DTH 000021780
MONTHLY HOURLY TURNOVER
10 9 8 7 6 5 4 3 2
1
DTH 000021781
ENERGY USAGE
Monthly 12 Month Moving Average
DTH 000021782
MM POUNDS
ABERDEEN PLANT PRODUCTION
MM POUNDS
60 50 40 30 20 10
40 35 30 25 20 15 10 5
I
25 20 15 10 5
----------- ACTUAL ----------- CUMULATIVE
DTH 000021783
ABERDEEN PLANT QUALITY PERFORMANCE
STANDARD 1.35
v. DTH 000021784
ABERDEEN PLANT EFFICIENCY
1981
STANDARD 1.01936
0
1.020 1.010 1.000
STANDARD 1.01300
STANDARD 1.00580
1.250
j)l-200
1.150 1.100 1.050
)
j'EEEE 1",.ii --------------
-------------------- --------------------- 1
.... .,.
---------------- -t--------------------
-P--------
RAW
TALrCONSUMPTj ION
---------------
1--------------- 1---------_-------- j--------------------- ,
--
______
------------------- f-------------- --i-------------------1_______ _____ 1__________ J
--I--------------- 1-------------------- {--------------- ----
1 1--7 I
---------------------------- ---------------------
_ i__
------------------- j
'-------------------- 1--------------------
1--------------------------------
----------
---------------- S\1 /-
----- --- /----- 1 "5____ ------- -------------1
v
r,
:
_____ ____ 1_____________ ______________ 1_______
1 ...
"I
. ------------- ------- {-------------------
---------------
-- --, r
----
-------------------- r. -----------
------ ^...... - ' -t................... mm
--------- , . 1 L J T------.-..--- . .;
^---------------------
\!
1~
. ___i____
________
-- -------------- --------------------------- -- ------------------
4 ' 1
... - .\---------- ~ * ... ------- ----------- -
1--------..-,;:-_-_--_-_--_-_-----------' 41--" ---.-.-.-..-.
+
--
*-41
' -
--- - T -- -t"
: -.1
JAHUAftV Ni*CM
Mir
. 1. 4
-------- -- i_____ r:
*
JUNE J'JIA 1 AUGUST SfniMPfr | OCICBit
______________ 1_____________
i
1 9 Ai_
-- -- --
-------------------- -
NOVEMBER OCCFMlR
STANDARD 1.10500
MONTHLY CUMULATIVE
000021785 dth
ABERDEEN PLANT INVENTORIES
4.0-: 3.0. 2.0 1.0-
0-
B
}
DTH 000021786