Document GmVYXEZRg9eMJY2eeRE5N3jDm

UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGION 5 77 WEST JACKSON BOULEVARD CHICAGO, ILLINOIS 60604 SUBJECT: FROM: THRU: TO: CLEAN AIR ACT INSPECTION REPORT Equinor USA Onshore Properties Inc., Clarington, Ohio Sasha Letuchy, Environmental Engineer AECAB (MI/WI) Sarah Marshall, Section Supervisor AECAB (MI/WI) File BASIC INFORMATION Facility Name: Equinor USA Onshore Properties Inc. - Eisenbarth/Michael Pad (Equinor) Facility Location: 42240 Long Ridge Road, Clarington, Ohio (39.697662, -80.898985) Date of Inspection: 8/30/2022 EPA Inspector(s): 1. Sasha Letuchy, Environmental Engineer 2. Manoj Patel, Environmental Engineer Other Attendees: 1. Brad Dockter, Manager Contact Email Address: brado@equinor.com Purpose of Inspection: To assess compliance with NSPS Subpart OOOO and the facility's permit Facility Type: Oil and natural gas well pad Regulations Central to Inspection: New Source Performance Standards for Crude Oil and Natural Gas Facilities (OOOO and OOOOa) at 40 C.F.R. Part 60, Subpart OOOO and OOOOa Arrival Time: 10:00 am ET Departure Time: 11:30 am ET Inspection Type: Unannounced Inspection Announced Inspection OPENING CONFERENCE Presented Credentials Stated authority and purpose of inspection Provided Small Business Resource Information Sheet Emailed after returned to office. Small Business Resource Information Sheet not provided. Provided CBI warning to facility The following information was obtained verbally from Brad Doctors unless otherwise noted. Process Description: At the well pad, a condensate/gas/water emulsion is extracted from the Utica Shale formation through five wells and from the Marcellus Shale formation through four wells (two additional wells are under construction), located on the Eisenbarth/Michael well pad. The emulsion from each well goes to gas processing units, from which the gas is sent to the sales line and the condensate and produced water are piped to one of two tank batteries. One tank battery is made up of three condensate tanks. A second tank battery is made up of nine produced water tanks. The vapors from the tank headspaces are piped together and routed to a combustor for destruction. Each tank has a thief hatch. TOUR INFORMATION EPA Tour of the Facility: Yes Data Collected and Observations: During the inspection, emissions were routed to the combustor, but Burner Management System for the combustor was running on manual and showed that the pilot light, ignite light, and main light were not on. We recorded FLIR videos of emissions venting from thief hatches. Photos and/or Videos: were taken during the inspection. Field Measurements: were not taken during this inspection. CLOSING CONFERENCE Provided U.S. EPA point of contact to the facility Compliance Assistance: As EPA observed venting from the tanks with the FLIR camera, EPA communicated this information to Brad Doctors. Page 2 of 4 Concerns: EPA noted concerns about the design and operation of the vapor capture and control system at the facility. EPA is concerned about both venting of emissions from the tanks and monitoring issues with the combustor. DIGITAL SIGNATURES ALEXANDR ALEXANDRA LETUCHY Digitally signed by Date: 2022.10.25 Report Author: _A__L_E_T_U__C_H__Y__1_1_:39_:3_3_-0_5'0_0_' ____________ Section Supervisor: SARAH Digitally signed by SARAH MARSHALL _M_A__R_S__H_A_L__L__1_4:_29_:4_7 _-05_'0_0'______________ Date: 2022.10.25 Page 3 of 4 Facility Name: Equinor Facility Location: 42240 Long Ridge Road, Clarington, Ohio Date of Inspection: 8/30/2022 APPENDICES AND ATTACHMENTS 1. Digital video log Page 4 of 4 Facility Name: Equinor Facility Location: 42240 Long Ridge Road, Clarington, Ohio Date of Inspection: 8/30/2022 APPENDIX A: DIGITAL IMAGE LOG 1. Inspector Name: Manoj Patel (photos) Sasha Letuchy (FLIR videos) 2. Archival Record Location: Region 5 Electronic Records Center Image Number 2643 File Name MOV_2643 Date and Time (Eastern Time) 8/30/2022 10:07 AM* Description of Image Combustor MOV_2644 8/30/2022 10:19 AM Combustor 2644 MOV_2645 8/30/2022 10:33 AM Tank 9 thief hatch venting (Tag 1116) 2645 2646 MOV_2646 8/30/2022 10:45 AM Tank 4 thief hatch (Tag 1115) 2647 MOV_2647 8/30/2022 10:46 AM 0233 IMG_0233 8/30/2022 10:30 AM 0234 IMG_0234 8/30/2022 10:31 AM 0235 IMG_0235 8/30/2022 10:45 AM 0236 IMG_0236 8/30/2022 10:52 AM 0237 IMG_0237 8/30/2022 10:57 AM *The time zone was set incorrectly; therefore, all MOV files hours in this log. Tank 5 thief hatch venting (Tag 0545) Three condensate tanks Combustor stack Tank 1 thief hatch Tank battery Combustor PLC. The combustor PLC states that the system is on manual mode and the pilot light, ignite light, and main light were not lit time stamps were adjusted forward six Appendices Page 1 of 1