OPERATING MANUAL
D - 7^5
P V C REACTORS
ABERDEEN, MISSISSIPPI
OCTOBER, 1981
Vernon L. Thornhill Senior Process Engineer
J. [Ey Barton VinvG. Expansion Coordinator
DTH 000096679
TABLE OF CONTENTS
OPERATING MANUAL
P>7^5 PVC REACTORS
ABERDEEN. MISSISSIPPI
I. INTRODUCTION
A. Operator Responsibilities . . .
B. Process Information ....................... 1. Evacuation 2. Charge 3. Initiator 4. Polymerization 5. Recovery and Steam Stripping 6. Dumping
II. GENERAL PROCESS DESCRIPTION
A. Evacuation .........................................
B. Charge .................................................. 1. Precharge Preparations 2. Reactor Charge
C. Polymerization ................................
D. Recovery and Steam Stripping . 1. Recovery 2. Steam Stripping 3. Hydroquinone Injection 4. Recovery of Blowdown Tank
E. Reactor Dump and Rinse ....
F. Chem Wash and Rinse .......................
G. Water Swirl ... ...........................
H. Water Collection System . .
III. OPERATING PROCEDURES
A. Reactor Evacuation .......................
B. Reactor Precharge ........................... 1. Lead Operator Duties 2. "A" Operator Duties
Page No.
1 3
5 5
9 12
16 17 19 19
20 24 plH 000096680
Table of Contents Operating Manual D-1^5 PVC Reactors Page 2
III. OPERATING PROCEDURES (CONTINUED)
Page No.
C. Reactor Charge ................................................................... ...... ?8
D. Polymerization.................................................................................... . . 1. Lead Operator Duties 2. "A" Operator Duties 3. Emergency Shutdown
33
E. Recovery and Steam Stripping............................................................... 1. "A" Operator Duties 2. Lead Operator Duties 3. Recovery System Troubleshooting
39
F. Reactor Dump and Rinse ............................................................................ 1. "A" Operator Duties 2. Lead Operator Duties
46
G. Chem Wash and Rinse................................................................................ 48
H. Full and Partial Swirl............................................................................ 1. Full Swirl 2. Partial Swirl
52
I. Colloid Solution Makeup . . . .......................................................... 1. Lead Operator Duties 2. "A" Operator Duties
53
J. Hydroquinone Solution Makeup ............................................................... 1. Lead Operator Duties 2. "A" Operator Duties 3. Safety Precautions
58
K. Used Chem Wash Solution Disposal...................................................... 60
L. Initiator Handling and Storage .......................................................... 1. Safety Precautions in Handling 2. Physical Characteristics 3. Initiator Storage Freezers 4. Design and Operational Functions 5. Daily Operational Checks 6. Emergency Procedure for Catalyst Freezers 7. Circle Chart Responsibility and Change Schedule
61
DTH 000096681
Table of Contents Operating Manual D-7U5 PVC Reactors Page 3
III. OPERATING PROCEDURES (CONTINUED)
Page No.
M. Reactor Pressure Check................................................
70
N. Reactor Cleaning and Entry.......................................................... .... . 1. Reactor Manhead Opening Procedures 2. Reactor Cleaning and Entry
72
O. Housekeeping Guidelines........................................................................ 77#
IV. EQUIPMENT INDEX.................................................................................................. 78
V. INSTRUMENT INDEX.................................................................................................. 114
VI. ALARMS AND SAFETY EQUIPMENT
A. Continuous Flow Fresh Air System........................................................... 120
B. Alarms and Switches......................................................................................123
C. Firewater System ......................................................................................... 1. Fire Monitors 2. Hydrocarbon Analyzers 3. Deluge System
131
D. Fixed Point Monitors ................................................................................. 132
VII. EQUIPMENT OPENING PROCEDURES ..................................... . ........................... 133
VIII. APPENDIX
A. Equipment List B. Instrument List C. P & I Diagrams
DTH 000096682
OPERATING MANUAL P-7^5 PVC REACTORS ABERDEEN. MISSISSIPPI
INTRODUCTION A. Operator Responsibilities
The purpose of this plant is to safely and economically convert vinyl chloride monomer (VCM) into a useable form of poly vinyl chloride (PVC). This is accomplished by a batch process in which VCM, water, initiator and colloid solution are charged into the reactor and under carefully controlled conditions, PVC with the desired physical properties is produced. This chemical reaction, which changes VCM to PVC, is called polymerization.
The operator helps fulfill the plant's purpose by making sure that quality production is obtained from his equipment without endangering his fellow workers or his equipment. The operator is able to attain his goals in safety, job performance and efficient operation through a training period and on the Job experience and passing a written exam.
The operator fulfills his responsibilities by:
1. Demonstrating understanding of how his equipment functions.
2. Being able 'to explain what role each piece of equipment plays in the process.
3. Keeping a close and regular check on equipment.
4. Being able to demonstrate trouble shooting and corrective measures.
5. Keeping his area of responsibility safe and clean.
6. Keeping complete and accurate records.
DTH 000096683
Operating Manual D-745 PVC Reactors Page 2
I. INTRODUCTION (CONTINUED) A. Operator Responsibilities (Continued) The operating Manual will cover the normal responsibilities and duties of the Lead Operator and the Reactor "A" Operator. Each phase in the production method will be covered. In addition to normal operating methods, it will also discuss operations under abnormal and emergency conditions. The operator must be prepared to meet these situations with temporary measures until the abnormal condition is corrected or the emergency crisis ceases to exist.
The safety of the plant personnel and equipment Is to be care fully considered before any job is started. The Conoco safety slogan, "our work is never so urgent or important that we can not take time to do it safely", is an idea that can help make the work area safer for everyone when it is put into practice.
Good housekeeping is also an important responsibility of the operators. It requires careful attention for safety reasons and to maintain good working conditions. Cleaning up after job completion is the responsibility of the person doing the job. A Job should not be considered complete until all materials are picked up and properly stored.
DTH 000096684
Operating Manual D-7,45 PVC Reactors Page 3
I. INTRODUCTION (Cont.)
B. Process Information
Several types o resins are produced, Resin type is determined by
a set of physical properties such as particle size and viscosity
Each type of resin produced requires that a certain set of operating
conditions be closely followed so that the desired resin properties
are obtained. Minor changes in formulas or operating conditions can
cause major differences in the physical properties of the resin. Some
factors in determining resin properties are reaction temperature, which
helps determine viscosity, colloid, which influences particle size,
and the amount of recovered VCM charged, which also effects particle
size, amount of short-stop which effects stability and amount of
calcium stearate which effects drying and customer processing.
The phases of reactor operation and a brief description of each follows:
1. Evacuation
This step removed all air possible by steam ejectors. Too much air
left in a reactor will alter particle size. Evacuation should re
quire about five minutes.
2. Charge
Water, Colloid and VCM are charged to the reactor simultaneously
through a timed sequence system. The temperature of the reactor
contents at the end of charging is determined by the charge water
temperature. The reactor will be below run temperature at the end
of the charge and jacket steam will be used to raise the temperature
to the desired level. Charge should take about nine minutes for
D-741, D-742, D-743, and D-744. D-745 will require about fifteen
minutes to charge.
DTH 000096685
Operating Manual D-T^+5 PVC Reactors Page 4
I. INTRODUCTION (Cont.) B. Process Information (Cont.) 3. Initiator The initiator is manually loaded into the initiator injection pot and charged into the reactor after reactor charge is complete. 4. Polymerization This is the time from the initiator addition until most of the VCM has been converted to resin. The reaction generates heat continu ously as liquid VCM becomes PVC resin. Heat that is generated is removed by cooling water on the reactor jacket and condenser. Reaction time varies, but generally requires five to six hours for D-741, D-742, D-743, and D-744. D-745 will require about Ah to five hours. 5. Recovery and Steam Stripping Recovery and steam stripping removes most of the "Unreacted VCM from the reactor via a compressor-vacuum pump system. Steam is added to the bottom of the reactor and rises through the PVC and water slurry to help remove unreacted VCM. Recovery and steam stripping takes about 60 minutes for D-741, D-742, D-743, and D-744 with D-745 taking about 90 minutes to recover and strip. 6. Dumping The PVC resin, after reaction is complete, is in a slurry form. The slurry is dumped to a sweco and dump tank and is pumped to blend tanks in the Dryer Room for drying. Dump requires about 25 minutes for D-741, D-742, D-743, and D-744 and 35 minutes for D-745.
DTH 000096686
Operating Manual D-7^5 PVC Reactors Page 5
II. GENERAL PROCESS DESCRIPTION A. Evacuation Before charging, the inerts present in the polymerization reactor are removed by evacuation. The interlock selector switch is placed on "evacuation" position. The main condenser valve is opened, the reactor evacuation valve is opened, the evacuation header valve, and the steam supply valves to the ejector system to be used are opened. Any condensate in the steam to the ejector is removed by a cyclone separator. The emergency cooling water supply valve to the reactor is then opened. When the reactor reaches 28.5 inches of mercury vacuum, as indicated by the pressure indicator in the control room and a manometer at the reactor, evacuation is complete. This portion of the cycle requires about five minutes. B. Charge 1. Precharge Preparation After evacuation, the reactor is ready to be charged. In pre paration for charge, adequate quantities of VCM, hot water, collibd solution, and initiator are made ready for the charge sequence.
Prior to charge, fresh VCM is transferred from the VCM storage
sphere to the fresh VCM storage tank. This transfer of VCM begins
automatically when the VCM liquid level falls below a certain level.
Whenthe high liquid level is regained, the transfer process shuts
down automatically. Two 1B0 gpm VCM transfer pumps are used to
transfer the VCM from the VCM storage sphere.
DTH 000096687
Operating Manual PVC Reactors
Page 6
II. GENERAL PROCESS DESCRIPTION (CONTINUED) B. Charge (Continued) Process water is automatically supplied to the hot water tank when the water level drops below a certain point. The water is filtered by the process water filter, and is heated in the hot water preheater, enroute to the hot water tank. The hot water tank temperature is maintained by the external steam coils on the hot water tank. The colloid solution, previously madeup, remains in the makeup tank until tested and approved. The colloid percent total solids must be 1.40 - 1.60. The colloid is then pumped from the makeup tank to the colloid charge tank.
After each reactor charge, colloid is transferred at 50 gpm from the storage tank to the colloid charge tank by the colloid circulation pump. When the makeup tank contains less than one charge, the full charge tank will contain sufficient colloid to charge seven reactors. The colloid charge tank can be emptied to less than one charge while the new colloid solution is being made up and analyzed. Immediately before the reactor is to be charged, the initiator injection system is made ready for charge in the following manner. First, the initiator injection pot, at the reactor to be charged, is drained to the sdwer. One gallon of water is manually added as indicated by the local flow totalizer.
DTH 000096688
Operating Manual DVf^-5 PVC Reactors Page 7
II. GENERAL PROCESS DESCRIPTION (Cont.) B. Charge (Cont.) 1. Precharge Preparations (Cont.) The initiator is then manually added to the initiator injection pot. The pot is then blocked in and pressurized with high pressure service water to at least 180 psig. The initiator injection system is now ready for the reactor charge. When the charge is complete. CAUTION: The initiator should never be left in the charge pot if the charge is aborted. It is to be dumped to the sewer and the pot flushed with water.
2. Reactor Charge After evacuation is completed, the interlock selector switch is moved to the "charge" position. If the following precharge con ditions are met, the charge sequence is ready to begin: a. Levels in the fresh VCM storage tank, the hot water tank, and the colloid charge tank are adequate for a complete reactor charge. b. There is sufficient pressure in the initiator injection pot and in the high pressure service water header. c. The charge meters are reset to the charge quantities. Steam is usually applied to the reactor jacket at the start of charge by manually opening the steam valve from the Control Room. DTH 000096689
Operating Manual D-7-45PVC Reactors Page 8
II. GENERAL PROCESS DESCRIPTION (CONTINUED) B. Charge (Continued) 2. Reactor Charge (Continued) This aids in heating Che reaction mass to the desired temperature during and immediately following charge. The automatic charge sequence begins with the hot water charge. The hot water is pumped from the hot water tank, to the reactor by the hot water charge pump. After a predetermined quantity of hot water has been charged, the colloid charge pumps and the second hot water charge pump start. The next step in the charge sequence begins with the fresh and recovered VCM charges. The fresh VCM is pushed to the reactor from the fresh VCM storage tank, by one of the two VCM charge pumps. The recover ed VCM is pupped from one of two recovered VCM storage tanks by the recovered VCM charge puaq> into the suction of the VCM charge pump. The recovered VCM is filtered in the recovered VCM filter and the total VCM charge is filtered enroute to the reactor by the VCM charge filter.
Shortly after the beginning of the VCM charge, one of the hot water charge pumps shuts down until the VCM charge is com
pleted and then restarts. This insures that there will be
an adequate amount of water charge remaining to flush out the charge line except on D-745 where the VC line is separate.
Both hot water charge pumps continue to run until charge
is completed.
DTH 000096690
Operating Manual D_jli5 PVC Reactors Page 9
II. GENERAL PROCESS DESCRIPTION (Cont.) B. Charge (Cont.) 2. Reactor Charge (Cont.) When the VCM, water and colloid charge is compftele, the initiator is charged by opening the initiator charge valve from the reactor by the "A" operator. Loading the initiator and preparation of the initiator charge pot was discussed in the precharge preparation section. C. Polymerization After charge is completed, the reactor interlock selector switch is placed in the "polymerization" position, and the reactor temperature controller is placed on automatic. When the reaction mass reaches 3 below ddsired set point temperature the steam is turned off. The reaction mass temperature is automatically controlled by varying the amount -of cooling water th$t is passed, through the top-mounted knockback condenser and the reactor jacket. The reaction mass is continually mixed and kept in suspension by the bottom-mounted single speed agitator. The agitator mechanical seals are lubricated and cooled by seal oil from anoil pressure unit. During polymerization, mechanical seal purge water is injected into the reactor through the reactor cleaning nozzle and through the agitator mechanical seal. The water is added to keep the reactor
DTH 000096691
Operating Manual g-7^5 PVC Reactors Page 10
II. GENERAL PROCESS DESCRIPTION (CONTINUED) C. Polymerization (Continued) cleaning nozzle and agitator mechanical seals clean. The purge water flow for each service is indicated with a rotameter and manually adjusted.
The inerts present in the reactor during polymerization from initiator decomposition, suspending agent and water accumulate in the reactor condenser head space. These inerts are vented to the recovery system to prevent inert blanketing.
When the desired degree of polymerization is reached and the reactor pressure has dropped to the desired pressure, the reaction is stopped by manually adding a mixture of AMS and Naugard (the short stop solution) to the reactor. High pressure service water is used to pressure the short stop solution from the initiator injection charge pot into the reactor through the same piping as the initiator charge piping. The charge pot is then blocked in and refilled with the short stop solution which will be used at the middle of steam stripping.
An emergency AMS kill pot, located at grade, is provided to pressure AMS into the reactor to kill the reaction in the event of a power failure or upon loss of agitation. The AMS will be injected into the reactor through nozzles in the reactor head, using push buttons on the control panel or by manually operated valves in the field.
DTH 000096692
Operating Manual D_745 PVC Reactors Page 11
II. GENERAL PROCESS DESCRIPTION (CONTINUED) C. Polymerization (Continued) The pots for D-741, D-742, D-743 and D-744 will contain 15-20 gallons of AMS. The material will be pressurized into the reactors using nitrogen. A nitric oxide (NO) short stop addition system is provided to inject NO into the reactors in the event of power failure, major VCM releases, fires, or other emergencies. The system is activated locally. NO is supplied from the emergency NO short stop bottles and is injected into the reactor through the same piping as the agitator mechanical seal purge water.
DTH 000096693
Operating Manual D-7^5 pvc Reactors
Page 12
II. GENERAL PROCESS DESCRIPTION (Cont.)
D. Recovery and Steam Stripping
1. Recovery
When reaction is completed, the interlock selector switch is
moved to the "recovery and steam stripping" position. The
following sequence then occurs. The recovery compresssor seal
water systems, the water recirculation systems for the recovery
knockout drums, and two of the three recovery compressors are
manually started from the board. Cooling water to the recovered
VCM condenser and the water recirculation cooler starts automati
cally with the compressors, and the hydroquinone injection system
starts with the compressor seal water systems.
The vapor from the reactor flows through a pressure control valve to
two resin knockout drums in series which cool the vapor and remove
carryover resin. The ppessure control valve prevents excessive carry
over of resin from the reactor by limiting the pressure to the
recovery system to about 35 psig. Each of the knockout drums have an
i internal water spray system and a recirculation pump. Both knock -
out drums have on-off level control system which, on high liquid level
divert i the:discharge of the water recurqulation pumps to the water
stripper. A water recirculation-cooler, (the function of which is
explained in the steam stripping portion of the recovery system
process description).
000096694 DlH
Operating Manual D-745 PVC Reactors Page 13
II. GENERAL PROCESS DESCRIPTION (Cont.) D. Recovery and Steam Stripping (Cont.) is provided and can be used in the water recirculation loop of either scrubbing stage. The VCM vapors from the knockout drums are compressed by the recovery compressors. The recovery compressors are constant volume liquid ring compressors with a water seal. The discharge streams from the compressors flow to two parallel seal water recirculation systems which operate as follows. Seal water is separated from the VCM vapors in the seal water separators, filtered by the seal water filters, cooled by the seal water coolers, and pumped back to the compressors by the seal water pumps. The flow of seal water to each compressor is controlled at 50 gpm. The seal water temperature is controlled just above the VCM condensation temp erature (95-105F). Automatic draining of the seal water separators to the water stripper is provided to maintain the correct water level.
The VCM vapors from the seal water system are condensed in two
recovered VCM condensers. The condensed VCM is collected in the re
covered VCM collect tank which is on automatic on-off level control.
VCM is transferred to the recovered VCM storage tanks by the recovered
VCM transfer pump when there is high liquid level in the VCM collect
tank.
Inerts are bled from the collect tank to the ineineratqf,
vu ^n'v
DTH 000096695
Operating Manual D-745 PVC Reactors Page 13
II. GENERAL PROCESS DESCRIPTION (Cont.) D. Recovery and Steam Stripping (Cont.) is provided and can be used in the water recirculation loop of either scrubbing stage. The VCM vapors from the knockout drums are compressed by the recovery compressors. The recovery compressors are constant volume liquid ring compressors with a water seal. The discharge streams from the compressors flow to two parallel seal water recirculation systems which operate as follows. Seal water is separated from the VCM vapors in the seal water separators, filtered by the seal water filters, cooled by the seal water coolers, and pumped back to the compressors by the seal water pumps. The flow of seal water to each compressor is controlled at 50 gpm. The seal water temperature is controlled just above the VCM condensation temp erature (95-105F). Automatic draining of the seal water separators to the water stripper is provided to maintain the correct water level.
The VCM vapors from the seal water system are condensed in two
recovered VCM condensers. The condensed VCM is collected in the re
covered VCM collect tank which is on automatic on-off level control.
VCM is transferred to the recovered VCM storage tanks by the recovered
VCM transfer pump when there is high liquid level in the VCM collect
tank.
Inerts are bled from the collect tank to the ineineratqf,
vu ^n'v
DTH 000096695
Operating Manual D-745 PVC Reactors Page 14
II. GENERAL PROCESS DESCRIPTION (CONTINUED) D. Recovery and Steam Stripping (Continued) 1. Recovery (Continued) When the reactor pressure drops to 8 psig, the two recovery vacuum pumps automatically start. The VCM flow from the recovery knockout drums and the seal water flow are both diverted to the vacuum pumps which discharge into the suction of the compressors. 2. Steam Stripping In order to reduce residual VCM in the slurry, the slurry in the reactor is heated and stripped with steam. At the start of a normal recovery, steam addition to the reactor is manually started from the control room and the slurry mass is heated. When the temperature of the reactor has risen to the desired temperature, the steam stripping operation is completed.
As recovery proceeds, less and less VCM is recovered from the
reactor. To supply sufficient VCM vapor to the recovery vacuum
pumps and compressors, a VCM backpressure system is used. This
is done to prevent cavitation and overheating of the vacuum
punps and compressors. Before entering the recovery knockout
drums, the steam and VCM from the reactor are combined with a
bleed stream of VCM from the recovered VCM storage tanks. The
amount of VCM bled into the recovery system is adjusted by the
backpressure control valve such that a set supply pressure to
the vacuum pumps is maintained.
DTH 000096696
Operating Manual D_7U5PVC Reactors Page 15
II. GENERAL PROCESS DESCRIPTION (CONTINUED) D. Recovery and Steam Stripping (Continued) 2. Steam Stripping (Continued) The majority of the steam is condensed in the first knockout drum described in the normal recovery process description. The first stage of the scrubbing system consists of a recovery knockout drum with an internal water spray system, a water recirculation pump and the water recirculation cooler. The water cooler reduces the water temperature sufficiently to allow the internal spray system in the knockout drum to cool the VCM and condense much of the steam in the vapor stream. After leaving the first Btage of the water scrubbing system, the VCM vapor flows to the second stage of the scrubbing system and then to the rest of the recovery system in the same manner as during normal recovery. 3. Hydroquinone Injection The VCM removed from the reactor during recovery still contains a small amount of initiator. As a result, the VCM will continue to polymerize, resulting in plugged recovery lines, charge lines, and recovered VCM storage tanks. Polymerization is significantly reduced by the addition of an inhibitor such as hydroquinone to the VCM stream as it is being recovered.
A 4.6 percent solution of hydroquinone in water is prepared in the hydroquinone storage tank.
DTH 000096697
Operating Manual D-7^5 PVC Reactors Page 16
H. GENERAL PROCESS DESCRIPTION (Cont.) D. Recovery and Steam Stripping (Cont.) 3. Hydroquinone Injection (Cont.) The hydroquinone solution is pumped by the hydroquinone injection pump into the suction of the recovery seal water pumps. The in jection pump starts and stops automatically with the seal water pumps. The metering pump has a variable stroke which can be adjusted manually to maintain the preset hydroquinone injection rate. 4. Recovery of Water Stripper The water stripper is to collect the various steam and water streams containing VCM from the four-reactor module. The emission recovery system is used to recover VCM vapor. The water is transferred to the Vslirwater strippers and recovered by the emission recovery system, E. Reactor Dump and Rinse After the reactor is recovered and steam stripped, the reactor inter lock selector switch is moved to the "dump" position. The appropriate dump valves are opened from the control room and the slurry flows by gravity to the dump system. The slurry passes through an enclosed vibrating slurry strainer where the PVC culls are collected until dump is completed. The slurry then flows to the slurry dump tank. The slurry transfer pumps transfer the slurry to the blend tanks. The dump tank level is automatically controlled.
DTH 000096698
Operating Manual Dr?745pvc Reactors Page 17
II. GENERAL PROCESS DESCRIPTION (CONTINUED) E. Reactor Dump and Rinse (Continued) Near the end of duiqp, the reactor condenser is flushed with water by turning on the condenser rinse system from the board. Hot water is pumped from the hot water tank by the hot water charge pumps through the cleaning nozzle in the reactor condenser. The rinse water mixes with any remaining slurry and is pumped with the slurry to the blend tanks flushing out the slurry transfer lines.
The slurry strainer and the slurry dunqp tank are equipped with a water wash system to remove resin from the equipment between production of different types of resin. F. Chem Wash and Rinse
If it has been determined that the reactor needs cleaning, the
reactor interlock selector switch is moved to the "clean and rinse"
position after the dump and rinse is completed.
DTH 000096699
The chem wash solution is a caustic solution. The cleaning solution pump or spare pumps the solution at 500 gpm from the cleaning solu tion tank through the cleaning solution heater to the reactor condenser spray nozzle. The reactor atmospheric vent must remain
closedtto prevent splashing out of the reactor. Steam to the clean ing solution heater is automatically adjusted such that the exit temperature of the chem wash solution is 190F. When the level in
the reactor is above the agitator blades (approximately 5,000 gallons)
as determined by the level change in the cleaning solution tank> n more solution is added to system. Recirculation is then started with
Operating Manual D-7U5PVC Reactors Page 18
II. GENERAL PROCESS DESCRIPTION (Cont.)
F. Chem Wash and Rinse (Cont.)
the cleaning solution being pumped from the reactor at approximately
250 gpm and back to the reactor through the reactor cleaning nozzle.
Large PVC particles picked up in the reactor cleaning process are
removed from the cleaning solution in the cleaning solution strainer
before entering the suction of the cleaning solution pump. When the Chem
Wash has ended, the solution is pumped back to the cleaning solution
tank at 500 gpm by the cleaning solution pump. For D-741, 742, 743, and
744, the process required ten minutes to fill the reactor through the
condenser, five minutes to wash the reactor, and ten minutes to empty
the reactor, for a total of twenty-five minutes. For D-745, the process
requires a total time of forty-one minutes--twenty-one minutes to wash
through the condenser, ten minutes to wash the reactor and ten minutes
to empty the reactor.
After the Chem Wash is completed, the reactor is rinsed with hot water
from the hot water tank. The hot water is pumped by the hot water charge
pumps to the reactor. The water first enters through the condenser clean
ing nozzle and then the reactor cleaning nozzle. The Chem Wash and rinse
system is manually controlled from the control room. The operator monitors
the bullseye at the sewer drain to be sure the reactor is empty. When
the reactor amps have dropped to the no load amps indicated on the
ammeter. The lead operator opens the rinse valve for a short period
of time. By observing the water flowing from the bullseye he can determine
that the reactor is empty.
DTH 000096700
Operating Manual
13-7^5 pvc Reactors
Page 19
II. GENERAL PROCESS DESCRIPTION (Cont.)
G. Water Swirl
If the resin formula calls for a water swirl, the reactor interlock
selector switch is place in the "swirl" position after the Ghem
wash rinse is completed. Cold or hot water enters the suction of the
hot water charge pumps, and is pumped through the reactor charge line
into the reactor. When the water charge reaches a preset amount, the
water charge system is automatically shut down. The reactor agitator is
then used to swirl the water for approximately 25 minutes. The lead
operator then drains the water to the sewer. This completes one reaction
cycle; the reactor is now ready for evacuation.
H. Water Collection System Various waste water streams from the process must be collected in an
enclosed system for treatment. Water streams containing PVC and VCM
from the recovery system, the VCM storage tanks, line and vessel purges,
and miscellaneous flush and seal waters are intermittently sent to the
blowdown tank.
When the liquid in the blowdown tank reaches a level 22 inches from the
top of the tank, a high level alarm sounds in the control room. The
"A" operator also checks the level gauge on the tank twice per shift to
be sure the level doesn't go above 22 inches from the top of the tank.
The operator will then start the tank's transfer pomp and send the
waste water to the batchwater stripping tanks in the V-ll module. The waste .water is then stripped with steam and vapors are recovered with
the emission recovery system. Once stripping has been completed, the
wastewater is drained to the sewer.
DTH 000096701
Operating Manual D-745 PVC Reactors
Page 20
III. OPERATING PROCEDURES
A. Reactor Evacuation
Evacuation of the reactor is required prior to charging in order
to remove as much of the air as possible. Air is introduced into
the reactor during previous phases of the reactor batch cycle since
dump, rinse, and chem wash require that the reactor be vented to
the atmosphere. Air in the reactor during reaction causes poor
temperature control during polymerization and may alter the particle
size of the resin.
Evacuation is accomplished using one of the two-stage steam jet
ejector systems. Evacuation is controlled by the lead operator from
the board. The "A" operator must confirm that all process equipment
is operating correctly during evacuation.
Procedure
1. If the reactor has been opened, follow procedure given in the
"Reactor Cleaning and Entry" section on how to close the reactor
manhead.
2. The lead operator puts the interlock mode selector on "evacuation."
3. The lead operator checks to see that all valves are closed.
4. The lead operator opens the condenser recovery valve and the
reactor evacuation valve. Then the lead operator opens the steam
supply valve and the evacuation header valve to the steam ejector
system to be used as follows.
&TH 000096702
Operating Manual D^T^5FVC Reactors Page 22
III. OPERATING PROCEDURES (Cont.) A. Reactor Evacuation (Cont.)
Procedures (Cont.)
4. Continued
(a) For D-741, 742, 743, and 744, the operator will open valves CV-230 and CV-.226. THis starts the ejector system located
between D-742 and D-743. (b) For D-745 the operator will open valves CM-222 and CV-224.
This will start the ejector system located between D-743
and D-744 reactor structure.
The operator then opens the emergency cooling water valve, which
supplies cooling water to the reactor coridenser.
NOTE: In the following steps, 5-10, the operators prepare the
initiator for charge while evacuation is in progress.
5. The "A" operator will go to the initiator freezer and bring the
specificed amount of initiator to the initiator injection pot.
Extreme caution must be exercised by the "A" operator to be sure
that no VCM is allowed to get back into the initiator injection
pot. When a small amount of VCM is mixed with a large amount of
initiator, an extremely fast reaction takes place giving off heat
and pressure. To guard against this situation, the operator must
know that he has an adequate water supply and pressure. The reactor
initiator injection valve must never be opened unless the bomb is
fully pressurized with the inlet water valve open.
DTH 000096703
NOTE: The following precautions must be taken when handling
initiator.
Operating Manual D-7^5 PVC Reactors Page 22
III. OPERATING PROCEDURES (Cont.)
A. Reactor Evacuation (Cont.)
Procedures (Cont.)
5. Continued
(a) Plastic gloves must be worn while handling initiator.
(b) If any initiator is spilled on skin or clothings,
immediately flush with water.
(c) Should any initiator remain in the containers, return
it to storage.
(d) Take all empty containers to trash and split side of
of all containers.
(e) Never put the cap back on the empty bottle. Dispose
of the cap separately.
(f) Do not allow the initiator to stand in the bomb for more
than 10 minutes. Drain it to the sewer and flush with water.
6. The "A" operator must check the injection bomb to be sure that
it is empty. Close the drain valve. Open the initiator addition
valve.
7. The "A" operator will manually open the HPSW inlet valve, until
the initiator water totalizer shows that 15 counts of water are
in the initiator to the inejction pot.
8. The "A" operator will now add the initiator to the injecttion pot.
9. The "A" operator will now close the initiator addition valve and inform the lead operator that the initiator loading is complete
and the bomb is ready to be pressurized.
DTH 000096704
Operating Manual
D-lk5 PVC Reactors
Page 23/ III. OPERATING PROCEDURES (Cont.)
A. Reactor Evacuation (Cont.) Procedures (Cont.)
10. The "A" operator will now open the 1" valve which supplies high pressure service water to the initiator injection pot and pressure the pot to 180 pounds.
11. The lead operator will stop evacuation when a vacuum of 28.5 inches Hg is attained. The reactor vacuum is double checked by the "A" operator on top the reactor with a mercury manometer. The lead operator stops evacuation by closing the condenser recovery valve, the reactor evacuation valve, the evacuation header valve and steam supply valve to the ejectors. This shuts off the evacuation steam jets. He then closes the emergency cooling water valves.
12. Evacuation is now complete.
DTH 000096705
Operating Manual D-T^5 PVC Reactors Page 24"
III. OPERATING PROCEDURES (CONTINUED) B. Reactor Precharge The reactor precharge procedure includes a series of precharge checks and precautions that must be carried out by the lead and "A" operators. If the necessary precharge conditions are not met, the Modicon (a small computer which controls the automatic charge sequence) will not allow the automatic charge sequence to begin.
It is the responsibility of the lead operator to see that all pre charge checks and precautions are carried out. He should also read the log book at the start of the shift, covering the period since he was last on the job. This will alert him to any changes in formula, mechanical, or operational procedures that may not have been passed on verbally.
1. Lead Operator Duties
a. Check level in fresh VCM receiver to see tfyat it is ade quate for charge. 80% reading on the level gauge at
the panel. b. Drain water in the recovered VCM receiver to the water strip
per. Valves from the recovered receiver are manually opened from the board until pressure rise in the blowdown
tank indicates all the water is out and VCM is being trans
ferred. Valves are then manually shut from the board.
c. Fill out the reactor charge sheet.
d. Check the hot water tank level and temperature. Tank level should
be 85% and the tank temperature 160F.
__ DTH 000096706
Operating Manual D-7^5 PVC Reactors Page 25
III. OPERATING PROCEDURES (CONTINUED)
" B. Reactor Precharge (Continued)
1. Lead Operator Duties (.Continued)
e. Check to see that all valves on the reactor are closed.
f. Have the "A" operator make a precharge check and reading
>-
of the following:
(1) Dura-Seal* oil level and pressure.
(2) Mechanical seal purge water pressure and rate to the
reactor agitator seal.
(3) Colloid charge tank level and temperature.
g. Record the readings on the charge sheet as they are trans
mitted by the "A" operator.
2. "A" Operator Duties
a Check Dura-Seal* level and pressure. There are two Dura-
Seal* units. One supplies seal oil pressure to all-five
reactor agitator mechanical seals and the other is a spare
and starts automatically when the operating unit has low seal
oil level or discharge pressure. If both units fail, an
emergency supply of seal oil is provided by the emergency
seal oil drum that is nitrogen pressurized. Valves must be
opened manually at the unit if the emergency seal oil system
is used.
Registered Trademark
DTH 000096707
Operating Manual -Dr-745 PVC Reactors Page 26'
III. OPERATING PROCEDURES (CONTINUED) B. Reactor Precharge (Continued) 2. "A" Operator Duties (Continued) NOTE: When the primary and spare Dura-Seal* oil units are down and the emergency system is in operation, reactors are not to be charged until at least one of the DuraSeal* oil units is operating. The emergency system is designed to be a backup system that should be used short term only.
When one of the Dura-Seal* oil units is not in operating condition, inform the lead operator so that repairs can be made.
The seal oil level should be checked in both units. The discharge pressure should be checked and be in the range of 205-250 pslg. If the pressure falls below 205 pslg, the spare unit will automatically start up and the primary unit shut down. The spare unit will also automatically start up and the primary unit shut down when a low seal oil level is detected in the primary unit. Report the seal oil pressure to the lead operator.
*Registered Trademark
DTH 000096708
Operating Manual D-7^5 PVC Reactors Page 27 III. OPERATING PROCEDURES (CONTINUED)
B. Reactor Precharge (Continued) 2. "A" Operator Duties (Continued) b. Check the mechanical seal purge water pressure and rate of flow to the agitator mechanical seal. Pressure should be 180-220 psig. Adjust the water flow rate to that given in the formula. Report the seal water pressure and flow rate to the lead operator. c. Check the colloid charge tank level to be certain enough is in the tank to complete a charge. Notify the lead operator of the level present. A level of at least 26 inches should be shown on the sight glass before charge is started. d. Inform the lead operator when checks are completed and the reactor is ready for charge.
DTH 000096709
Operating Manual D-17H5 PVC Reactors Page 28
III. OPERATING PROCEDURES (Cont.) C. Reactor Charge This section includes vacuum break and reactor charge. The reactor charge is one of the most critical operations in terms of product quality. Care must be taken to assure that all the raw materials are added in the proper order and amount.
Procedure
1. When evacuation and precharge checks are complete, the lead operator can move the interlock mode selector to "charge."
2. The lead operator should take the following steps and see that the following conditions are met before charge: a. VCM transfer should be in auto. b. Recovered VCM charge should be in auto with either the primary or spare pump selected for charge. c. Fresh VCM charge should be in auto with either the primary or spare pump selected for charge. d. Hot water charge should be in auto. e. Colloid charge should be in auto with either the primary or spare pump selected for charge. f. Select recipe to be charged by dialing recipe number on the recipe selector on on the board. gl. Push the meter reset button, which resets all charge meters. DTH 000096710
Operating Manual D-.745PVC Reactors Page 29
III. OPERATING PROCEDURES (CONTINUED) C. Reactor Charge (Continued) Procedure (Continued) h- The charge light will now come on if all the following conditions are met: (1) The fresh VCM storage tank, hot water tank, and colloid charge tank all have a level adequate for one complete charge. (2) One reactor is in charge mode. (3) The high pressure service water header is at least 150 psig. (4) The reactor being charged has at least 28.5 inches Hg vacuum. (5) The initiator injection pot is at least 180 psig. 3. When a charge light is obtained on the panel, the lead operator will inform the "A" operator to stand by for breaking vacuum. The lead operator will break vacuum by: a. Manually opening the reactor VCM charge valve from the board. b. Manually opening the reactor charge valve from the board. c. Turbine meters will start counting as VCM flows into the reactor. d. As soon as a positive pressure is indicated in the reactor, close the VCM charge valve.
DTH 000096711
Operating Manual D-745 FKC Reactors
Page 30
III. OPERATING PROCEDURES (Continued) C. Reactor Charge (Continued 4. The "A" operator will then watch the pressure gauge at the top of the reactor. When the pressure rises above zero, start checking the following: a. Inspect manhead visually and listen for escaping vapor. b. Check safety disc gauges for pressure. Any pressure indicates a leaking or ruptured disc. c. Turn flush water (injection water) on sprayhead. The purpose is to keep spray heads free of resin. Set rate according to recipe. d. If all checks okay, notify lead operator. If not, notify lead to hold on charge until problem can be corrected. 5. The lead operator can now push the charge button. In rapid sequence, the following occurs: a. Reactor water charge valve opens. b. "A" hot water pump starts, valves open, and water starts into the reactor. c. The valves from the fresh VCM receiver to the VCM charge pump and discharge valve open. d. At set point No. 1 on water meters:
Registered Trademark
DTH 000096712
Operating Manual ~n-745pvc Reactors Page 31
m. OPERATING PROCEDURES (CONTINUED)
C. Reactor Charge (Continued)
Procedure (Continued)
(1) "B" hot water pump starts and discharge valve opens.
(2) The colloid charge pump discharge valve will open and
pump will start. The preset amount of colloid will be
pumped into the reactor. When the colloid meter set
point is reached, the colloid charge pump will cut off
and the discharge valve and reactor colloid charge valve
will close.
NOTE: The lead operator will turn on reactor jacket steam
during colloid and water charge to assist reactor
heatup.
e. At set point No. 2 on water meter, the reactor VCM charge
valve opens and the VCM and recovered VCM charge pumps start.
f. At set point No. 3 on the water meter, "B" hot water pump
stops and discharge valve closes. This allows time for all
VCM to be charged to the reactor before the water charge is
completed.
NOTE: A partially plugged filter pack can cause slow VCM flow,
and it may be necessary to cut off "A" hot water pump also.
If this should happen, be sure to have a minimum of 50 counts
left or water charge meter. This is enough to clean lines
and manifold of VCM. When the VCM is within ten counts
of being complete, put "A" and "B" hot water pumps back
on automatic and complete the charge.
DTH 000096713
Operating Manual D-745 PVC Reactors
Page 32
III. OPERATING PROCEDURES (Cont.)
C. Reactor Charge (Continued)
NOTE: When a filter is known to be fouled, isolate and switch
to the spare unit. If you continue to try to force VCM
through fouled filters, the high pressure will cause the
filter elements to collapse and greatly increase the time
taken to change them out. Collapsed filters also will cause
a gel problem affecting the quality of the resin.
g. When VCM meters reach the set point (two meters running in tandem,
first to reach the set point cuts pump off and closes valve),
the VCM pump, outlet valve, inlet and discharge valve to
VCM charge pump, and reactor VCM valve close. This action
also starts "B" hot 1^0 pump and opens discharge valve.
h. At set point No. 4 on the water meters, "B" hot water pumps
stop, and the valves close.
i. At set No. 5 in the water meters "A" hot water pump stops
and the valves close. At this time the main dump valve also
closes.
6. When the automatic charge sequence has been completed, it is safe to
charge the initiator.
7. The "A" operator charges the initiator by opening the initiator reactor
charge valve and flushing the initiator into the reactor with 50 counts
of high pressure service water.
8. The lead operator will now record the final recator temperature. Adjust
reactor temperature set point to setting called for in the formula
and put temperature controller in "auto" position.
DTH 000096714
Operating Manual D-745 PVC Reactors Page 33
m. OPERATING PROCEDURES (CONTINUED)
D. Polymerization
Polymerization is the phase of the reactor cycle in which liquid
VCM is converted into solid PVC. This portion of the reactor cycle
is mainly accomplished by accurate instrumentation. The primary
area of responsibility for the lead operator is coordination of
the activities of the "A" operator. The "A" operator is required
to kill tfte`Taction when polymerization has progressed to the
tp&int that product quality Is- satisfaGtery. 1. Lead Operator Duties
a. Change the interlock mode selector to "polymerization."
Monitor the temperature and pressure closely until the
reactor reaches the desired set point and lines out.
b. Cut off steam valve to jacket at two to four degrees below
set point, depending on the rate of temperature rise. c. Have the "A" operator sample the reactor 1 hour after reading
heat up. a fresh.'.air mask must be- worn and personnel cleared
of the general area befdta Sample is taken.
d. Examitie the resin." At thih stage the resin shoiild be formed
into individual separate particles. Notify the shift super
visor if you notice the following:
(1) Stringers - Resin particles are stringy and stuck together.
` (2) Hard Particles - Gritty resin particles which are harder
ahd larger than most.
DTH 000096715
Operating Manual D-745PVC Reactors Page 34
HI. OPERATING PROCEDURES (CONTINUED) D. Polymerization (Continued) 1. Lead Operator Duties (Continued) If either of the above conditions are observed, have the "A" operator take samples every fifteen minutes until 1&S Shift "supervisor makes the decision*.as to what co corrective action should be taken.
e. It may become necessary to remove the inerts. Inerts in
the condenser will cause the reactor pressure to rise as they blanket the condenser and do not allow VCM vapor to
be condensed. Under these conditions, less heat can be
removed even though the condenser water flow will be full
open. Vent the inerts through the main condenser valve to
the recovery system.
Start the compr-ssears ^nd put the
pressure controller in manual and close the control valve.
Open the reactor condenser valve* and recovery valve..Set
the controller on 35 psig and put it back in automatic.
f. Irregularities during polymerization: (1) Slow Heatup--May be caused by weak or no initiator. Slow heatup can also be ^caused by no steam on reactor jacket or the cooling water valves may be open. Contact the shift supervisor if this condition persists. DTH 000096716
Operating Manual
B-745pvc Reactors
Page 35
III. OPERATING PROCEDURES (CONTINUED) D. Polymerization (Continued) 1. Lead Operator Duties (Continued) (2) .Long Reaction Time--Caused by l?w initiator level, weak initiator, long heat up, low reactor temperatures or chem wash solution setting or chem-'wash solution in the batch. If there is only slow reaction and the resin cheeks okay, the shift supervisor will give word on what to do. If caustic is in the reactor, the batch will turn slightly yellow and coarsen. If this is found to be true, kill immediately with the amount of short stop solution speci fied in the formula. (3) Simultaneous Temperature and Pressure Rise--Check cooling water temperature and valves. The reactor is producing more heat than the cooling water can remove. Also could be an overcharge of initiator. Notify shift supervisor for instructions. (4) Simultaneous Temperature and Pressure Drop--The cooling water valves are probably wide open. This happens more often in freezing weather when relays freeze up. Throttle manual valves until malfunction is found and corrected. (5) Agitator Kicks Out or Power Failure--Most power failures are of short duration (seconds to two minutes), and the reactor pressure does not have time to build to a dangerous level. If outage is prolonged, the pressure will build.
DTH 000096717
Operating Manual D-745 pvc Reactors Page 36
III. OPERATING PROCEDURES (CONTINUED)
D. Polymerization (Continued)
1. Lead Operator Duties (Continued)
If this situation occurs, follow the procedure in Section III.D.3
which outlines action to be taken during emergency shutdowns
(such as during a power failure).
2. "A" Operator Duties
a. When charge is complete, recheck water injection rates
through the cleaning nozzle and seal flush.
b. On instruction from the lead operator, resin samples will
be taken from the reactor. This normally occurs 1 hour after
heat up. If the first sample shows formation of undesirable
resin particles, additional samples may be called for every
fifteen minutes until a decision is made about what should be
done with the batch.
When taking a sample from the reactor a fresh air mask must
be worn and personnel cleared of the general area.
c. When the lead operator instructs the "A" operator to do so,
the batch is killed by adding short stop solution to the
reactor. The amount of short stop solution and the procedure
for adding it depends on the product. The kill procedure
is as follows:
5305 (normal) - 1% gallons AMS
5305 (CTA)
3h gallons AMS/3J5 gal. Naugard
5425
lh gal. AMS/21s gal. Naugard initially and again at 170F.
5465 5385
2h gal. AMS/3I5 gal. Naugard initially and again at 170F.
DTH 000096718 gal. AMS/3% gal. Naugard
Operating Manual jD-745 PVC Reactors Page 37
III. OPERATING PROCEDURES (CONTINUED) D. Polymerization (Cont.) It is very important that the proper amount of short stop solution be added since it effects the quality of the resin. High pressure service water is used to pressure the short stop solution from the initiator put into the reactor.
3. Emergency Shutdown The following steps are to be taken during emergency shutdown: a. 1.!. Use the AMS emergency kill system for killing each reactor. Each reactor has a pot located at grade beside each reactor, containing AMS. The AMS is injected into the head space of the reactor with nirtogen by opening the appropriate control valves, from the control room. The hand switch for the control valves for each reactor is located next to the agitator start-stop handswitch on each reactors control station. Refer to the operating manual for the AMS Emergency Kill System. 2. If the AMS does not stop the reaction, use the nitric oxide (NO) short stop system for killing each reactor. There are six cylinders of NO that can be released for each reactor D-741, 742, 743 and 744. D-745 has twelve cylinders of NO which can be released. The NO system can be activated at the reactors by manually opening the correct valves.
DTH 000096719
Operating Manual D-745 PVC Reactors Page 38
III. OPERATING PROCEDURES (Cont.) D. Polymerization (Cont.) 3. Emergency Shutdown (Cont.) b. Use nitrogen to pressurize the Dura-Seal* unit emergency seal oil drum and the mechanical seal purge water surge drum. The valves connecting the emergency seal oil and seal water drums with their respective systems must be opened manually. c. There will be sufficeint air in the air system surge tank to operate valves for approximately fifteen minutes. It will be necessary to use the nitrogen backup system to operate valves after fifteen minutes. The surge tank should be valved off before the backup nitrogen system is activated. d. Monitor each reactor for pressure rise. If the pressure con tinues to rise, the following steps are to be taken: (1) Equalize the reactor with any other empty or killed reactor of the same type product. (2) If the pressure still continues to rise, vent through the main condenser valve to the recovery system and the re covery system to the recovered VCM receiver. (3) If this willinot relieve the pressure buildup, then equal ize the reactor with a reactor of different type resin.
* Registered Trademark
DTH 000096720
Operating Manual D-745 PVC Reactors Page 39
III. OPERATING PROCEDURES (CONTINUED)
D. Polymerization (Cont.)
3. Emergency Shutdown (Cont.)
d. (4) When 1, 2, and 3 alone fail to relieve the reactor
pressure, the relief valve vent system will allow
the reactor to vent off and on thru the relief valves
to control the pressure.
NOTE: Step (4) is to be the last resort. Under the new EPA
law, any venting must be reported and could result in a
fine.
The foilwing guidelines, when followed, will control a runaway reactor
and prevent a VCM release. The NO system is to be activated if either
one of the parameters is exceeded.
Resin Type
Maximum Temperature
Maximum Pressure
5385, 5425, 5465
142F
145 psig
5305 (CTA)
152F
155 psig
5305 (Normal)
162F
165 psig
NO is high poisonous orange-brown colored gas. A Scott Air Pak must
be worn while killing a reactor with the NO short stop system.
E. Recovery and Steam Stripping
The reactor is ready for recovery when certain conditions are reached
in the reaction process. The conditions under which recovery will start are:
Pressure Drop -- There is not enough unreacted VCM left in the reactor to
maintain run pressure. A pressure drop is accompanied by a drop in the
cooling water flow to the reactor jacket and condenser. __TI DTH 000096721
Runaway --Reaction has increase to the point that it has outrun the
capabilities of the cooling water to control.Temperature and pressure will
Operating Manual
Dr^745 pvc Reactors
Page 40
III. OPERATING PROCEDURES (CONTINUED)
E. Recovery and Steam Stripping (Cont.)
Runaway (Cont.)
both rise when this occurs. Follow instructions on each product
formula as to the exact conditions at which the reaction is
killed.
Temperature Rise-Pressure Drop-- This is the ideal recovery situation
and indicated proper initiator loading. The reaction will peak and
slightly out: run the capabilities of the cooling water. This situation
gives the best recovery conditions since there is less VCM to be
recovered and more converted to resin.
Quick-Kill-- A reactor is sometimes killed on specific products
to meet certain customer specifications--lower dry time (higher
plasticizer absorbtion ). The reactor is killed with a specified
amount of the short stop solution at a specified set of conditions.
The short stop solution mixture stops the reaction chain.
On a quick-kill batch, it is very important to guard against resin
carryover to the recovery system. An injection of defoamer will
help to control foaming. A fast recovery is also important and will
affect the dry time.
1. "A" Operator Duties
When notified by the lead operator that the recovery conditions
specified in the formula are met, the "A" operator will take the
following steps:
'
DTH 000096722
a. Check the hydroquinone injection sytem to make sure that the
proper valves are open and hydroquinone level is adequate. b. Check the blowdown tank level and pressure. Level and pressure
must be low to allow the automatic drain on the water recirculation Plimp to operate.
Operating Manual D-745 PVC Reactors Page 41
III. OPERATING PROCEDURES (Cont.) E. Recovery and Steam Stripping (Cont.) 1. "A" Operator Duties (Cont.) c. Check the water levels in the seal water separators and knockout drums. These levels are controlled automatically but should be checked before startup. Knockout drum level should be at or below the mid-point of the inlet to the vessel. The seal water separator level should be at or below the mid-point of the inlet of the vessel. d. Check the backflow pressure controller. It should be set at twenty-five inches Hg vacuum. e. Check to see that the flush to the knockout drum and seal water separator level gauges are on set at 1 gpm. These are FI-726, FI-727, FI-741, and FI-742. f. Notify the lead operator that the recovery system is ready to startup. g. Steam header pressure should be greater than 100 psig. h. Reactor steam line should be checked and reactor steam valves should be checked to make sure they are opening correctly. 2. Lead Operator Duties a. When the "A" operator has checked the recovery system, the lead operator can change reactor interlock mode to "recovery. b. Start the water recirculation pump, 72-889 and 72-890.
DTH 000096723
Operating Manual D-745 PVC Reactors Page 42
III. OPERATING PROCEDURES (Cont.) E. Recovery and Steam Stripping (Cont.) 2. Lead Operator Duties (Cont.) c. Start the seal water pumps, 72-891 and 72-892. This auto matically starts hydroquinone injection pump 72-895. d. Two recovery compressors, 72-903, 72-904, or 72-905, are started from handswitches located on the recovery control panel. This starts two compressors and opens! the valves associated with compressor startup. e. The vacuum pumps will atuomatically come on when the suction pressure of the compressor is 7 psig. The necessary valve changes are also automatically made. f. When:the reactor reaches the pressure specified in the product formula, the lead operator will move the reactor temperature set point to the specified stripping temperature, set the steam stripping flow controller on 23,000 lbs/hour, and begin steam stripping. g. Watch the temperature of the reactor condenser. h. When stripping conditions specified in the formula are met, steam stripping is complete. i. When steam stripping and recovery is complete, the recovery system is shut down as follows:
DTH 000096724
Operating Manual D-745 PVC Reactors Page 42
III. OPERATING PROCEDURES (Cont.) E. Recovery and Steam Stripping (Cont.) 2. Lead Operator Duties (Cont.) c. Start the seal water pumps, 72-891 and 72-892. This auto matically starts hydroquinone injection pump 72-895. d. Two recovery compressors, 72-903, 72-904, or 72-905, are started from handswitches located on the recovery control panel. This starts two compressors and opens! the valves associated with compressor startup. e. The vacuum pumps will atuomatically come on when the suction pressure of the compressor is 7 psig. The necessary valve changes are also automatically made. f. When:the reactor reaches the pressure specified in the product formula, the lead operator will move the reactor temperature set point to the specified stripping temperature, set the steam stripping flow controller on 23,000 lbs/hour, and begin steam stripping. g. Watch the temperature of the reactor condenser. h. When stripping conditions specified in the formula are met, steam stripping is complete. i. When steam stripping and recovery is complete, the recovery system is shut down as follows:
DTH 000096724
Operating Manual iD-745 PVC Reactors Page 43
m. OPERATING PROCEDURES (Cont.)
E. Recovery and Steam Stripping (Cont.)
2. Lead Operator Duties (Cont.)
i. (1) Push stop buttons for the recovery compressor 72-903,
72-904, 72-905. This also stops the vacuum pumps.
(2) Push stop buttons for seal water pumps 72-891 and 72-892.
This also stops hydroquinone injection pump.
(3) Push stop buttons for the water recirculation pumps,
72-889-72-890.
3. Recovery System Troubleshooting
a. High Compressor Outlet Temperature
Probable cause is poor or no water recirculation in the
recovery knockout drum, 45-760. Check VCM feedback controller
setting. Controller setting should be at 25 inches Hg.
b. High Compressor Discharge Pressure
High pressure can be caused by:
(1) Plugged Condenser-- Have -lead operator report problem
to the shift supervisor.
(2) Plug in the Line from the Condenser to the VCM Collect
Tank--Line will have to be pulled and cleaned.
(3) High Level in the VCM Collect Tank
(a) Switch transfer pump to manual.
(b) Check level of the recovered VCM receiver--east or west. (4) High RVCM Receiver Pressure
(a) Switch receivers
DTH 000096725
(b) Check line pressure to V-ll RVCM receivers to be sure
line is not plugged.
Operating Manual
D-745 pvc Reactors
Page 44
III. OPERATING PROCEDURES (Cont.)
E. Recovery and Compressor Stripping (Cont.)
b. High Compressor Discharge Pressure (Cont.)
(5) No Cooling Water to Condenser--Check inlet and outlet
water valves.
(6) High Seal Water Temperature--This temperature should be
110 +_ 10. Check seal water pump for flow and pressure
and check filter pack.
c. If the compressor is not compressing the VCM vapor and does
not have a 50 to 70 psi discharge pressure:
(1) Check seal water flow.
(2) Check seal water separator water level and adjust as neces
sary.
(3) Check seal water temperature--b61ow 80F water will condense
the VCM vapor and cause displacement of the water seal around
the compressor cone.
d. Recirculation water pump 72-889 goes out (mechanical-electrical).
(1) Under normal operation, recirculation water pump 72-889 circu
lates water through the water recirculation cooler and into
recovery knockout drum 45-760. Crossover piping is provided
so that, if recirculation water pump 72-889 fails, recircu
lation water cooler and into recovery knockout drum 45-761.
NOTE: Normal operating temperatures for the recovery system
during stripping are:
DTH 000096726
Operating Manual D-745 PVC Reactors Page 45
III. OPERATING PROCEDURES (Cont.) E. Recovery and Steam Stripping (Cont.) 3. Recovery Troubleshooting (Cont.) d. (1) Continued (a) Reactor Condenser - 215-225F (Peak Temperature) (b) 45-760 Knockout Drum Outlet - 122-128F (c) 45-761 Knockout Drum Outlet - 90-115F (d) Compressor Outlet - 130-140F The lead operator must monitor these temperatures on the multipoint recorder and have the "A" operator check out and correct deviations. e. Reactor Foaming (carryover)--When foaming is detected, the "A" operator will: (1) Inject defoamer into the reactor to reduce slurry surface tension and lower the reactor slurry level. It may become necessary for the lead operator to shut down one compressor to slow the recovery. If excessive foaming occurs, shut down recovery and thoroughly flush the entire system with water until clear. All flushing must be done to the blowdown tank.
000096727 DTH
Operating Manual D-745 PVC Reactors Page 46
III. OPERATING PROCEDURES (CONTINUED) F. Reactor Dump and Rinse When the recovery of the reactor has been completed, the slurry is ready to be dumped to the slurry blend tank(s) that has been designated by the shift supervisor. 1. "A" Operator Duties a. Check the selected blend tank or tanks to make sure it will hold the batch. b. If transferring to small blend tank, set up piping to go to appropriate tank. Check to see that the blend tank sewer valve is closed and the aeration is flowing in the tank. c. Check the slurry transfer pump valving to make sure the flow will be going to the correct line. d. Place the coarse overflow collector into position. Inform the lead operator that the dump can begin. e. Monitor the dump tank level until the flow to the pump and discharge from the reactor have leveled out to a steady rate. f. Add the formula amount f calcium stearate to the dump tank as directed by the shift supervisor.
*Registered Trademark
DTH 000096728
Operating Manual D-745 PVC Reactors Page 47
III. OPERATING PROCEDURES (Cont.)
F. Reactor Dump and Rinse (Cont.)
2. Lead Operator Duties
a. Select the blend tank to be used by opening the appropriate
control valves in the slurry transfer lines. The valves are
operated by handswitches located on the recovery section of the
control panel, as follows:
CV-1521 CV-1522 CV-1506 CV-1523 CV-1524
To T-501 To T-407 To T-747 To T-502 To small blend tank manifold
b. Check the sewer valve on the reactor to be sure it is closed.
c. Turn on the Sweco* strainer.
d. Check the Sweco* exhauster to be sure it is running. It should
be running continuously.
e. Turn the interlock mode selector switch to the "dump" position.
f. After the "A" operator informs lead operator that dump can
begin, place the slurry transfer pumps, 72-896 and/or 72-897,
in the "run" position. This opens the slurry transfer pumps'
seal water supply valves, CV-864 and/or CV-866, before the
pumps start. The level in slurry dump tank 45-766 is auto
matically controlled.
g. Five minutes after the start of dump, open the reactor vent
to go the atmosphere.
*Registered Trademark
DTH 000096729
Operating Manual D-745 PVC Reactor t'age 49 III. OPERATING PROCEDURES (Cont.)
G. Chem Wash and Rinse (Cont.) the body, immediately get under a safety shower and remove your clothing. If any should,get in the eyes, flush eyes for at least' fifteen minutes until all burning stops and report to your supervisor. Procedure 1. The lead operator will check and make sure the reactor sewer valve is closed. 2. The lead operator will then place the interlock mode selector switch to "clean and rinse." 3. The lead operator then checks to see that the cleaning solution tank, 45-767, is at least 85 percent full. 4. The lead operator then opens the valves from;the cleaning solution pumps, 72-989 or 72-899, to the reactor condenser cleaning nozzle. The atmospheric vent on the reactor should be closed. 1 All other reactor valves are closed. 5. The lead operator then opens the suction valves, CV-873, for the cleaning solution pumps, 72-898 or 72-899. 6. The lead operator will then turn on one cleaning solution heater temperature controller is set at 190F. 7. The lead operator will then turn on one cleaning solution pump 72-898 or 72-899.
DTH 000096731
Operating Manual D-745 pvc Reactor Page 50 III. OPERATING PROCEDURES (Cont.)
G. Chem Wash and Rinse (Cont.) Procedure 8. When the chem wash solution has been flushed through the reactor condenser, the lead operator will: CAUTION: The atmospheric vent valve must remain closed.
. .1 .
k. Stop the cleaning solution pump. b. Close pump suction valve CV-873 from the cleaning solution ' tank. c. Open chem wash return valve on reactor. d. Open cleaning solution pump suction valve CV-874 from the
reactor. e. Close valves to the reactor cleaning nozzle. f. Open valves to the reactor cleaning nozzle. g. Restart the cleaning solution pump. The chem wash solution
should now be circulating from the bottom of the reactor back to the reactor cleaning nozzle. h. The reactor agitator remains on. 9. The lead operator will recirculate the chem wash solution through the reactor for five minutes and will then pump the chem wash solution back to the cleaning solution tank by: a. Opening CV-872 b. Closing CV-871. This sends the cleaning solution pump dis charge to the cleaning solution tank.
DTH 000096732
Operating Manual D-745 PVC Reactor Page 51
III. OPERATING PROCEDURES (Cont.)
G. Chem Wash and Rinse (Cont.)
Procedure (Cont.)
10. The "A" operator should monitor the cleaning solution pump and
notify the lead operator when it loses suction (check pressure gauge on pump discharge).
11. The lead operator will now shut off the cleaning solution pump.
12. The lead operator will then check the cleaning solution tank level
indicator to see if all the chem wash solution has returned. If
any solution is lost or accidentally dumped to the sewer, notify
the utilities operator. The spilled solution must be neutral
ized to avoid upsetting the chemical balance in the lagoons.
13. The lead operator will now close the reactor cleaning valves and
open the condenser cleaning valve and the reactor sewer valve.
14. The lead operator will cut on both hot water charge pumps and
flush through the condenser to the sewer for ten minutes.
15. The lead operator will then close the condenser cleaning valve,
open the reactor cleaning valve, and flush the reactor to the
sewer for ten minutes. Reactor is empty when agitator shows no ldad amps and sewer bullseye is empty.
16. The lead operator will now close the reactor sewer valve and open the atmospheric vent.
17. Because of the water dilution and resin accumulation, chem wash
solution must be disposed of and fresh caustic pumped to the
cleaning solution tank once per week. Follow the procedure out
lined under "Used Chem Wash Solution Disposal".
DTH 000096733
Opeating Manual D-745 PVC Reactors Page 52 III. OPERATING PROCEDURES (Cont.)
H. Full and Partial Swirl To assist in the production of quality resin, particularly low gel, it has been found that, by filling the reactor with water and agitating, the gel count is markedly lower. 1. Full Swirl In this swirl, the reactor is almost completely filled with water.
Lead Operator Duties
a. Turn the interlock mode selector switch to the "swirl" position.
b. Opens the reactor main charge valve and water charge valve. c. Starts both hot water charge pumps. d. (1) D-741, 742, 743, and 744--Adds 1500 counts of water to
reactor (15,000 gallons). (2) D-745--Adds 2000 counts of water to reactor (20,000 gallons). e. Cuts off pumps and closes valves. Agitates for ten minutes. g. Opens sewer valve and dumps. 2. Partial Swirl This swirl procedure is the same as the full swirl except for the amount of water used. Charge 750 counts (7500 gallons) for D-741 D-742, D-743, and D-744 and 1000 counts (10000 gallons) for D-745 Then follow the same procedure as the full swirl.
DTH 000096734
Operating Manual D-745 PVC Reactors Page 53
III. OPERATING PROCEDURES (Cont.)
I. Colloid Solution Makeup
A-Operator
The properties of polyvinyl chloride (PVC) are strongly dependent
upon the type and quality of the colloid solution used. The colloid
solution must be made very accurately and consistently every time
it is prepared. The colloid solution is a
percent solution of
Dow F-50 Methocel* powder in water.
There is a local instrument panel located near the colloid makeup
tank on the second floor of the recovery building. These instruments
are to aid the operator in making the colloid solution in a consis
tent manner.
1. Lead Operator Duties
As soon as the lead operator is notified by the "A" operator that
the colloid storage tank level is below the straight wall, he will
schedule the "A" operator to make up colloid solution as follows:
a. With the "A" operator at the colloid tanks, open the makeup
tank outlet valve (CV-857) and start the colloid transfer pump
to the transfer the colloid solution to the storage tank.
b. To mix any remaining heel in the storage tank with the new
colloid solution, open the storage tank inlet valve (CV-858).
* Registered Trademark
DTH 000096735
Operating Manual D-745 PVC Reactors Page 54
III. OPERATING PROCEDURES (CONTINUED) I. Colloid Solution Makeup (Continued) 1. Lead Operator Duties (Continued) and circulation pump inlet valve (CV-859) and start the colloid circulation pump. The charge tank inlet valve (CV-861) must be closed. c. When the "A" operator indicates that the makeup tank is empty, close the makeup tank outlet valve (CV-857) and turn off the transfer pump. d. With the circulation pump still running, notify the "A" operator to catch a colloid solution sample and take it to the laboratory for analysis. e. Close the storage tank inlet valve (CV-858) and circulation pump inlet valve (CV-859) and turn off the circulation pump. f. Schedule the "A" operator to makeup a new batch of colloid solution as soon as possible. g. During the first part of the colloid makeup procedure when notified by the "A" operator, the lead operator will open the hot water charge valve (CV-706) and will start one hot water charge pump and the discharge valve associated with the charge pump to transfer hot water to the colloid makeup tank. The colloid makeup tank water meter will close the valves and shut down the hot water pump automatically when it reaches its set point.
DTH 000096736
Operating Manual D-7,45 PVC Reactors Page 55
III. OPERATING PROCEDURES (CONTINUED) I. Colloid Solution Makeup (Continued) 2. "A" Operator Duties The "A" operator aids in colloid solution transfer by notifying the lead operator when the colloid storage tank heeds to be refilled. After transfer, the "A" operator notifies the lead operator that the makeup tank is empty.
laboratory.
When notified by the lead operator, the "A" operator makes up a new batch of colloid solution by the following procedure: a. Bring eight bags of Dow F-50 Methocel* powder (50 pounds
per bag) to the top of the colloid makeup tank. b. Rinse the colloid makeup tank with water to the sewer
until it is clean. c. Reset the colloid makeup water meter to 538 gallons, open
the colloid tank inlet valve (CV-856), and notify the lead operator to open the hot water charge valve (CV-706), start a hot water charge pump, and open the discharge valve associ ated with the pump selected. The water meter will stop the pump and close the actuated valves that were opened when the set point is reached. Check to see that the agitator blades are covered.
Registered Trademark
DTH 000096737
Operating Manual D-745PVC Reactors Page S6
III. OPERATING PROCEDURES (CONTINUED) *
I. Colloid Solution Makeup (Continued) 2. "A" Operator Duties (Continued) d. Start the colloid tank heater and the tank agitator. The temperature controller will close the steam valve when the water in the tank reaches 200F. e. When the heater is off, add the methocel powder very slowly with the agitator still on. Each bag should take about one minute to add. If the powder is added too quickly, it will form lumps and not dissolve properly. Carry the empty bags to a trash container. f. Allow about thirty minutes to let the agitator thoroughly mix the powder into the hot water. Check the mixture for 'lumps and continue to mix if lumps are present. g. When the mixture contains no lumps, reset the colloid makeup water meter to 2,623 gallons and open the colloid tank inlet valve (CV-856) and the colloid tank water valve (CV-828) to add cold water. The water meter will close the actuated valves that were opened when the set point is reached. Measure the outage on the colloid makeup tank to check the accuracy of the water meter. The straight wall por tion of the tank contains 14.8 gallons per inch.
000096738
dth
Operating Manual D-745 PVC Reactors Page 57
III. OPERATING PROCEDURES (CONTINUED) I. Colloid Solution Makeup (Continued) 2. "A" Operator Duties (Continued) h. Start the colloid tank cooler. The temperature controller will close the cooling jacket valve when the colloid solu tion reaches 85F. Check the cooling water temperature. If it is 80#F or above, the solution will cool very slowly; so close the manual cooling water valves and open the process Water valves to the jacket. i. Check the temperature after four hours of cooling. If the temperature is 85F and the temperature controller has closed the cooling jacket valve, turn off the agitator. If the tank is still cooling, leave the agitator on until the tank has reached 85F. It is very important to cool the colloid solution completely each time to produce a good quality colloid solution. j. Caution: Spills of colloid solution are slick and present a dangerous slipping hazard.
DTH 000096739
Operating Manual D-745 PVC Reactors Page 58
III. OPERATING PROCEDURES (CONTINUED) J. Hydroquinone Solution Makeup Hydroquinone is injected into the recovery system to short stop the chain reaction and polymerization of vinyl chloride. If the hot VCM gases are allowed to flow through the recovery lines with out any inhibitor, they continue the reaction that was started in the reactor and rapidly fill and plug the recovery lines. Plugged lines in the recovery system are very time consuming to pull and clean and cause considerable amounts of downtime.
Adequate and accurate injection of hydroquinone eliminates this problem. Hydroquinone (commercial name Tecquinol*) comes in a powder form and must be put into a solution with water for our use.
When the hydroquinone solution level is low, as determined by the low level alarm LA-733 in the control room and/or by the hydro quinone storage tank sight glass, a new batch is to be made. Each batch should last approximately one month.
1. Lead Operator Duties As soon as it is determined that the hydroquinone storage tank is low, the lead operator should schedule hydro quinone makeup between reactor recoveries.
Registered Trademark
DTH 000096740
Operating Manual
D-745 pvc Reactors
Page 59
III. OPERATING PROCEDURES (CONTINUED) J. Hydroqulnone Solution Makeup (Continued) 2. "A" Operator Duties When notified by the lead operator to make up a new batch of hydroquinone solution, the "A" operator does the following: a. Weight up twenty pounds of hydroquinone powder. b. Turn off hydroquinone metering pump suction valve and, with the nitrogen turned on and the vent closed, drain the remaining heel to the sewer and rinse with water to the sewer. c. Open the vent and add water until the tank is about half full. d. Turn off the nitrogen temporarily and add the hydroquinone powder through the funnel. e. Turn on the agitator and open the nitrogen line. f. Fill with water to the full mark on the sight glass (fifty gallons). g. Close the vent and mix until the powder is dissolved. h. Make sure the valves are lined up to the hydroquinone metering pump. 3. Safety Precautions Rubber gloves and full face shield must be worn while handling and transferring hydroquinone dust and liquid. Hydroquinone dust can irritate and seriously damage the eyes.
DTH 000096741
Operating Manual D-745PVC Reactors Page 60
III. OPERATING PROCEDURES (CONTINUED) J. Hydroquinone Solution Makeup (Continued) 3. Safety Precautions (Continued) First Aid--In case of contact, immediately flush eyes with water for fifteen (15) minutes. Notify the plant nurse. Flush skin with water and wash clothing before reuse. K. Used Chem Wash Solution Disposal Procedure 1. The shift supervisor must have given instructions to dump the used chem wash solution and make up a fresh batch. 2. The lead operator will instruct the "A" operator to open the tank's drain valve. The valve is opening using the gear operator on the valve. 3. As soon as the tank is empty of solution as indicated by the level indicator in the control room, the "A" operator will open the three inch process water valve to the tank to flush out the tank. Then the "A" operator will close the process water valve and the drain valve. 4. Make up a new batch of cleaning solution. Notify the P-1 operator to transfer new caustic to the tank.
NOTE: Notify the utility operator that the cleaning soution has been dumped to the sewer.
DTH 000096742
Operating Manual B-745 PVC Reactors Page 61
III. OPERATING PROCEDURES (CONTINUED) L. Initiator Handling and Storage In the conversion of vinyl chloride monomer to polyvinyl chloride resin, an initiator is needed to start and help sustain the reac tion process. The Aberdeen plant uses peroxide-type initiators. The physical properties of the type resin needed determines the type of initiator to be used. All of these products must be kept in cold storage because of rapid dangerous decomposition rates Tat room temperatures. The initiator is a skin and eye irritant and must be handled accordingly.
Safety precautions for all types of initiator are basically the same, with some differences in handling temperatures and explosive limits. 1. Safety Precautions in Handling Initiator
a. Wear full face shield when handling an open container.
1). Avoid contact with skin or clothing (will bleach out clothes).
c. Do not leave initiator unattended when not under refriger
ation.
d. If initiator is spilled, soak up with absorbent material,
such as vermiculite, and spread thinly in an isolated area.
e. Dispose of empty containers immediately. Leave cap off and
split the side of this container and store away from the
unit in an open area.
dth 000096743
Operating Manual D-745 pvc Reactors Page 62
III. OPERATING PROCEDURES (CONTINUED) L. Initiator Handling and Storage (Continued) 1. Safety Precautions in Handling Initiator (Continued) f. Bring only what is necessary to the production area. Do not allow the amount in the reactor area freezers to exceed one shift's comsumption. g. If a partial or full jug of initiator is found sitting out, it may be water, but always handle and dispose of just as if it were initiator. h. If spilled on skin area, wash with large amounts of water. i. If splashed in the eyes, flush with water for fifteen (15) minutes and notify your supervisor. Do not use oils or salves on the eyes. j. Should any initiator catch on fire, use water to cool the surrounding area. However, if the fire is spread ing and likely to ignite other initiator set the portable fire monitor and get out of the area, since an explosion is very likely. 2. Physical Characteristics These Lucidol 223M75 , Trigonox EHP-C75 and Witco 939M75 must be stores at a safe temperature below 20F to prevent rapid decom position of the material which occurs at approximately 50F.
DTH 000096744
Operating Manual D-745 PVC Reactors Page 63
III. OPERATING PROCEDURES (CONTINUED) L. Initiator Handling and Storage (Continued) 2. Physical Characteristics (Continued) Lupersol L-ll catalyst must be stored at a temperature not oo below 15 F because it freezes if stored below 15 F for extended periods of time. These types of catalyst are not self ignitied because they contain 75% product and 25% OMS, odorless mineral spirits. 3. Initiator Storage Freezers Three walk-in freezers and one chest freezer have been installed o for initiator storage at temperatures down to -30 F. Each freezer has two independent refrigeration compressors with one to be held in reserve. This is to insure continuous operation at the temperature set point. High temperature in any freezer will activate the air horn and a beacon flasher alarms. An automatic defrost system controlled by time clocks will provide frost-free operation, a. Operating Conditions (1) Temperature The temperatures are adjustable. They can be set from -30F to +30F. (2) Alarms The chest and the walk-in freezers on high temperature
DTH 000096745
Operating Manual D-745 PVC Reactors Page 64 III. OPERATING PROCEDURES (Cont.)
L. Initiator Handling and Storage (Cont.) 3. Initiator Storage Freezers (Cont.) a. Operating Conditions (Cont.) (2) Alarms (Cont.) setting with actuate the red beacon light and air freezer. This is the same for all freezers in the plant. The alarm's present setpoint is 17F (+2). (3) Compressors The compressors for the freezers are located in two inter connected sheds 50 feet north of the freezers. The com pressors for the chest freezer and the west and middle walk-in freezers are located in the west shed. The compressors for the east walk-in freezer is in the east shed. The compressors in the west shed are numbered 1 thru 6. (a) No. 1 and No. 2 compressors serve the middle walkin freezer. (b) No.3 and No. 4 compressors serve the west walk-in freezer. (c) No.5 and No. 6 compressor serve the chest freezer on the west end. The compressors in the east shed are numbered 7 and 8. They serve the east walk-in freezer.
DTH 000096746
Operating Manual D-745 PVC Reactors Page 65
III. OPERATING PROCEDURES (Cont.)
L. Initiator Handling and Storage (Cont.) a. Operating Conditions (Cont.)
(4) Compressor Shutdown Conditions (Automatic)
(a) Freezer temperature (b) Compressor low oil level (c) High or low compressor pressure (5) Circuit Breakers
(a) West Compressor Shed - Located on north wall.
(1) Compressor Panel--The compressor circuit breakers
are numbered in sequence 1 thru 6.
(2) Fan Panel - The fans are numbered 2, 3, 5, and 6.
(3) Auxiliary Panel - Contains lights, defrost controls,
alarms, fans, and defrost time clocks.
(b) East Compressor Shed - Located on north wall.
(1) Compressor Panel - The compressor circuit breakers
are numbered 1 and 2. The fans are numbered 7 and 8.
(2) Auxiliary Panel - Contains lights, defrost controls, alarms, and defrost time clocks.
(6) Defrost Cycles - Adjustable
In the walk-in freezers, each compressor switches to hot gas
bypass every six hours to provide a defrost cycle. This is
controlled by a time clock.
(7) Freezer Capacity
(a) East walk-in freezer - 600 gallons (b) Middle and West walk-in freezers - 550 gallons (c) Chest freezer - 100 gallons
DTH 000096747
Operating Manual D-745 PVC Reactors Page 66 III. OPERATING PROCEDURES (Cont.)
L. Initiator Handling and Storage (Cont.) 4. Design and Operational Functions Each freezer is provided with two refrigeration units each which are capable of maintaining the desired freezer temperature. Both units can be run simultaneously to allow a check on com pressor operation. The temperature element in each freezer is connected to a mer cury switch which starts and stops the compressor. These are adjustable and can be set for different temperatures. Each compressor has a timer which activates a solenoid valve in the hot gas line to send hot gas directly to the evaporator to allow for the defrost cycle. The fan normally runs with the compressor but is off during the defrost cycle. The east, middle, and west walk-in freezers defrost every six hours, and the chest freezer defrosts every eight hours. The water-cooled condensers on each compressor in the west compressor shed have water bypass to allow continuous flow and prevent freezeup during cold weather. The condensers also have inlet and outlet valves to allow for acid cleaning. Condenser cooling water is normally supplied by and returned to the cooling tower. During shutdowns and power outages, a bypass valve from the well to city water can be opened to supply water pressure. If the condensers are put on the well water, open the block valve in the manhole at the west end of the cooling tower to divert the water to the sewer.
DTH 000096748
Operating Manual D-745 PVC Reactors Page 6? III. OPERATING PROCEDURES (Cont.)
L. Initiator Handling and Storage (Cont.) 4. Design and Operational Functions (Cont.) The condensers for the east walk-in freezers are air-cooled and are not tied into the cooling water system. 5. Daily Operational Checks a. Each compressor oil level by maintenance. b. Temperature recorders by Chief Operator. c. Frost buildup on freezer coils by Chief Operator. NOTE: Manual defrost instructions are on the inside front of each time clock. NOTE: Due to the explosive nature of this initiator, formal approval must be obtained from the operations super intendent and the mechanical superintendent before any changes are made to this operation.
DTH 000096749
Operating Manual D-745 PVC Reactors Page 68
III. OPERATING PROCEDURES (CONTINUED) L. Initiator Handling and Storage (Continued) 6. Emergency Procedure for Initiator Freezers If the power should go off, do not open the freezers btjit do the following: a. Notify the shift supervisor to find out the reason for the power failure. (1) If trouble is inside the plant, the supervisor will survey the situation and estimate how long the outage will be. Freezers should hold temperature from 3-4 hours, depending on what is in them, the outside temperature, and how may times the door is opened. (2) If trouble is dtermined to be outside the plant, the shift supervisor will notify the proper people on the call list. (a) The duration of the outages will be determined. (b) If outage is expected to be over three (3) hours, Joan Pope will arrange for purchase of dry ice. b. If a compressor should 1 fail and it is not an electrical problem, get in touch with maintenance as soon as possible.
DTH 000096750
Operating Manual D*+745 PVC Reactors Page 69 III. OPERATING PROCEDURES (Cont.)
L. Initiator Handling and Storage (Cont.) 6. Emergency Procedure for Initiator Freezers (Cont.) (2) If the problem cannot be fixed, try to move all initiator to other freezer. If not possible, get dry ice.
NOTE: If compressors should go out on a freezer, make sure fans are turned off to that freezer. Middle walk-in freezer 1 and 2 fans, west walk-in freezer 3 and 4 fans, and chest freezer 5 and 6 fans in the west compressor shed. The east walk-in freezer 7 and 8 fans located in the east compressor shed.
c. Notify the following if an emergency should arise with the initiator freezers: Jim Barton - 369-4755 Pete Markey - 369- 6019
7. Circle Chart Responsibility and Change Schedule a. The '.Chief Operator on each shift will check the charts to be sure they have ink and are rotating.
b. The Chief Operator on the 7 P.M. - 7 A.M. shift will place new charts- in the recorder andi turn in the previous day's chart,3to the shift supervisor.
DTH 000096751
Operating Manual 0*745 PVC Reactors Page 70
III. OPERATING PROCEDURES (CONTINUED) M. Reactor Pressure Check Prior to the startup of a reactor after an extended outage or following a maintenance outage such as replacing a main dump valve or rodding out the condenser tubes, the reactor must be hydrostatically pressure checked. This is to insure that no leakage occurs at the reactor, either inward or outward. Procedure 1. The lead operator sets up the pressure check as follows: a. Place the reactor mode in "emergency" to gain use of both the charge water valve and the rinse valves. b. Open both hot water charge pump discharge valves CV-849 and CV-829. c. 0)en the reactor charge water valve. d. Open the main dump valve. e. Open the emergency vent valve. 2. The lead operator then turns on both hot water charge pumps and fills the reactor. 3. The "A" operator stands by to notify the lead operator when water comes out the atmospheric vent, showing that the reactor is full. 4. The lead operator then shuts down the hot water charge pumps and closes all valves. This must be done immediately to avoid overpressuring the reactor and blowing the rupture discs.
DTH 000096752
Operating Manual D-745 PVC Reactors Page 71
III. OPERATING PROCEDURES (CONTINUED) M. Reactor Pressure Check (Continued) Procedure (Continued) 5. The "A" operator then increases the reactor pressure by charging water into the reactor through the initiator injec tion system. 6. The lead operator monitors the reactor pressure from the control room and instructs the "A" operator to shut off water addition when the pressure reaches 130 psig. 7. The "A" operator then checks the reactor for leaks at the reactor bottom and top side. If a flange or gasket has been changed, check these very closely. 8. The lead operator then monitors the reactor pressure. If the reactor holds 130 psig for ten minutes, the pressure check is terminated. If the reactor loses pressure, instruct the "A" operator to bring the pressure back up to 130 psig with the high pressure service water and reinspect the reactor for leaks. NOTE: Do not charge a reactor that will not hold pressure. 9. When the pressure check is completed, the lead operator dumps the water in the reactor to the sewer. The reactor is now ready to start evacuation procedure.
000096'753
dth
Operating Manual D-745 PVC Reactors Page 7 2
III. OPERATING PROCEDURES (CONTINUED) N. Reactor Cleaning and Entry 1. Reactor Manhead Opening Procedures One of the most critical parts of the operator's job is the opening of the reactor Lenape* manhead. Following is a list of procedures that must be followed by the "A" operator or anyone else when opening a reactor manhead. Procedure a. Check the pressure gauge and/or bleed valve for pressure or vacuum. b. Put on continuous flow fresh air mask. c. Unlatch Lenape* lock on Lenape* manhead roll-bar and drop down. NOTE: If the reactor has pressure when the roll-bar arm is lifted, the pressure will start escaping. If this should happen, notify the lead operator.
d. Slowly raise manhead four to six inches and hold in that position.
e. Call lead operator and have him cut on the reactor evacu ation ejector to pull air inward through the manhead.
f. Finish raising the manhead. g. The continuous flow fresh air mash may be removed
at this time. h. Change "0" ring on manhead.
*Registered Trademark
DTH 000096754
Operating Manual D-745 PVC Reactors Page 73
III. OPERATING PROCEDURES (CONTINUED) N. Reactor Cleaning and Entry (Continued) 1. Reactor Manhead Opening Procedures (Continued) i. If the bottom manhead is to be opened, inspect the bottom of the reactor through the open manhead. The reactor should contain no liquids. j. Go to the bottom of the reactor and make sure that the safety chain and jacking bolts are in proper position on the bottom manhead. k. Maintenance will remove the bolts and open the manhead. 2. Reactor Cleaning and Entry This section will cover precaustions taken prior to entry and during entry and cleaning of the reactor. The following is a check list stating conditions which must be met by anyone entering the reactor. The equipment entry sheet is to be filled out and placed at the reactor. Procedure a. The reactor must be empty/steam stripped, recovered and flushed with water. b. The 0^ content must be greater than 20 percent. c. The VCM content myst be less than 10 ppm. d. The top and bottom manways myst be open. e. The nitric oxide (NO) piping myst be disconnected at the bottles.
DTH 000096755
Operating Manual D-745 PVC Reactors Page 74
III. OPERATING PROCEDURES (CONTINUED) N. Reactor Cleaning and Entry (Continued) 2. Reactor Cleaning and Entry (Continued) Procedure (Continued) f. The following lines must be blanked or disconnected. (1) Main eight-inch dump line. (2) Four-inch steam stripping lines. (3) Six-inch condenser lines. (4) Four-inch chem wash and rinse line to condenser* (5) Four-inch chem wash andirinse line to reactor* (6) One-inch initiator injection line. (7) One-inch inerts vent. (8) Three-inch colloid charge line. (9) One-inch sample line. (10) Six-inch VCM charge line - D-745 only.
g. Lock out and tag agitator breaker.
h. Test agiator switch
i. Special precautions and safety equipment that may be needed are:
(1) Impervious suit (2) Plastic mats on the bottom dish to prevent slipping. (3) Continuous flow fresh air mask
DTH 000096756
*When preparing to blank or remove blank in chem wash line, lock out cleaning solution pump, open chem wash line to reactor, and bleed line at discharge of pump before breaking chem wash flange.
Operating Manual D-745 pvc Reactors Page 75 III. OPERATING PROCEDURES (CONTINUED)
2. Reactor Cleaning and Entry (Continued) Procedure (Continued) (4) Rubber gloves (5) Scaffolding for work above bottom level. (6) Two-way radio communication plus manway watch. (7) Safety harness and rope. (8) 12 volt explosion proof lights.
DTH 000096757
Operating Manual
D-745 PVC Reactors Page 76
III. OPERATING PROCEDURES (CONTINUED)
N. Reactor Cleaning and Entry (Continued)
2. Reactor Cleaning and Entry (Continued)
j. While cleaning the buildups from the baffles and blade,
take extreme care not to scratch the reactor walls. These
walls have been polished to eliminate giving the resin
being formed during reaction a place to create a buildup.
NEVER SCRAPE THE WALLS.
k. Around the shaft at the bottom of each reactor is a carbon
throttle bushing. The purpose of the throttle bushing is
to protect the reactor seal from resin. The seal water
flush will not be effective if the throttle bushing or
holder is damaged. If there is any buildup in this area,
it is the Maintenance Department's responsibility to remove
it. Operators are NOT to clean the throttle bushing.
Damage to the throttle bushing may cause seal failure.
l. If hammer and chisel are required to clean the reactor, be
careful of chisel placement to avoid it kicking back out
of the buildup and causing personal injury.
m. While in the reactor, check the safety discs for buildups,
nozzles for plugs, and the bottom of the condenser for
plugging.
n. When internal job is completed, remove scaffolding from
the reactor and store neatly. Remove any loose buildup
on the reactor bottom and close the bottom manhead.
o. Clean up any debris, rags, etc. The job is never complete
until the area is clean.
000096758
Operating Manual D-745 PVC Reactor Page 77 III. OPERATING PROCEDURES (CONTINUED)
0. Housekeeping Guidelines Good housekeeping is a major portion of any task to be under taken, and no task can be called complete until the work area has been cleaned. Return all tools and materials used to their proper place and do not leave lying around to create a safety hazard. The housekeeping of the reactor area is the responsibility of all people working there.
DTH 000096759
Operating Manual D-745 PVC Reactors Page 78
'
IV. EQUIPMENT INDEX
A. Reactors
1. Polymerization Reactors 45-741, 45-742, 45-743, and 45-744
a. Purpose
Vessel used to react VCM to PVC in a water suspension.
b. Description
Vertical-mounted, bottom-agitated vessel, 12-foot diameter
by 22-foot straight wall height (28 feet overall height),
jacketed, and with top-mounted condenser. The reactor is
stainless steel, and the cooling water and steam jacket
is carbon $teel. Approximate capacity is 22,<500 gallons. c. Normal Operating Conditions
The reactor produces various resin types, operating in a
pressure rsnge of 28.5 inches Hg vacuum to 150 psig and a
temperature range of 80-225F.
d. Design Conditions
Shell
Temperature, F
250
Pressure, psig
200 (and full
vacuum)
2. Polymerization Reactors 45-781
Jacket
200 30
a. Purpose
Vessel uspd to react VCM to PVC in water suspension.
b. Description
Vertical-mounted, bottom-agitated vessel, diameter by 28-foot
straight wall height (35 feet overall height), jacketed and
DTH 000096760
Operating Manual D-745 PVC Reactors Page 79
IV. EQUIPMENT INDEX (Cont.)
A. Reactors (Cont.)
2. Polymerization Reactors 45-781 (Cont.)
b. Description (Cont.)
with top-mounted condenser. The reactor is stainless steel,
and the cooling water and steam jacket is carbon steel
Approximate capacity is 30,000 gallons.
c. Normal Operating Conditions
The reactor produces various resin types, operating in a pres
sure range of 28.5 inches Hg vacuum to 150 psig and a temper
ature range of 80 - 225F.
d. Design Conditions
Shell
Jacket
Temperature, F Pressure, psig
250 FV-225
200 45
B. Heat Exchangers
1. Reactor Condensers 55-328, 55-329, 55-330, and 55-331 a. Purpose
To remove the heat of reaction from the polymerization reac
tor by condensing VCM vapor.
b. Description
Each of the reactor condensers are vertical, mounted on top
of the polymerization reactors. Cooling water (shell side)
is used to condenser VCM (tube side). Each condenser has
2,100 square foot surface area provided by 999 tubes which are
eight feet long by one-inch diameter. Materials of construction
DTH 000096761
Operating Manual D-745 pvc Reactors
Page 80
IV. EQUIPMENT INDEX (Cont.)
B. Heat Exchangers (Cont.)
b. Description (Cont.)
are stainless steel or stainless steel clad for all surfaces
in contact with VCM.
c. Normal Operating Conditions
Condensers operate in a temperature range of 80-225F and pres
sure range of 28.5 inches Hg vacuum to 150 psig during the
reactor cycle.
d. Design Conditions
Shell
Tubes
Temperature, F Pressure, psig
200 250 120 200 (and full
vacuum)
2. Reactor Condenser 55-558
a. Purpose
To remove the heat of reaction from the polymerization
by condensing VCM vapor.
b. Description
Condenser is vertical, mounted on top of the polymerization
reactors. Cooling water (shell side) is used to condense VCM
(tube Side). Each condenser is provided with 2700 tubes which
are ten-feet long by One-inch diameter. Materials of con
struction are stainless steel and stainless steel clad for
all surfaces in contact with VCM.
DTH 000096762
Operating Manual D-745 pvc Reactors
Page 82
IV. EQUIPMENT INDEX (Cont.)
B. Heat Exchangers (Cont.)
3. Hot Water Preheater 55-332 (Cont.)
d. Design Conditions
Shell
Tube
Temperature, F Pressure, psig
400 400 175 200
4. Hot Water Tank Heater 55-333
a. Purpose
To maintain water temperature in hot water tank 45-748.
b. Description
External plate coil type heat exchanger that will be clamped outside the hot water tank; stainless steel construction. c. Normal operating Conditions
Steam in the coil should be around 341F and 150 psig. Water
in the hot water tank should be near 160F.
d. Design Conditions
400F and 175 psig.
5. Water Recirculation Cooler 55-334
a. Purpose
To cool the recirculation water in recovery knockout drum 45-760.
b. Description
DTH 000096763
Horizontal mounted, shell and tube type heat exchanger.
Cooling water is on the shell side and recirculating water is
on the tube side. Surface area of 1,441 square feet is pro
vided by 466 tubes, 16 feet long by 3/4-inch diameter. The
tubes are stainless steel and the shell is carbon steel.
Operating Manual D-745 pvc Reactors Page 8-5
IV. EQUIPMENT INDEX (Cont.)
B. Heat Exchangers (Cont.)
4. Water Recirculation Cooler 55-334 (Cont.)
c. Normal Operating Conditions
d. Design Conditions
Shell
Tube
Temperature, F Pressure, psig
450 400 150 150
5. Seal Water Coolers 55-335 and 55-556
a. Purpose
To cool the circulating vacuum pump and compressor seal water.
b. Description
Horizontal-mounted shell and tube type heat exchanger. Cooling
water is on the shell side and recirculating seal water is on
the tube side. Surface area of 339 square feet is provided by
182 tubes 10 feet long by 3/4-inch diameter. The tubes are
stainless steel and theshell is carbon steel.
c. Normal Operating Conditions
d. Design Conditions
Shell
Tube
Temperature, F Pressure, psig
200 380 150 150
6. Recovered VCM Condensers 55-337 and 55-338
a. Purpose
To condense VCM vapor during recovery as it is removed from the
polymerization reactors.
DTH 000096764
Operating Manual D-745 PVC Reactors Page 84
IV. EQUIPMENT INDEX (CONTINUED) B. Heat Exchangers (Continued) c. Normal Operating Conditions
Steam temperature and pressure on the shell side will vary. Cleaning solution on the tube side is estimated to enter at 175F and leave at 190F with a pressure of 125 psig.
d. Design Conditions
Temperatue, F Pressure, psig
Shell
175 400
Tube
200 400
C. Tanks and Vessels 1. Instrument Air Capacity Tank 45-301 a. Purpose To provide adequate instrument air during periods of high demand and temporarily supply air during Instrument air failure. b. Description Vertical-mounted, five-foot nine-inch straight wall height, four-foot diameter, carbon steel construction. c. Normal Operating Conditions 100 psig and 80F d. Design Conditions
DTH 000096765
Operating Manual
D-745 PVC Reactors Page 85
IV. EQUIPMENT INDEX (CONTINPED)
C. Tanks and Vessels (Continued)
2. Recovered VCM Storage Tanks 45-317 and 89-520
a. Purpose
Storage of recovered VCM and charge tank for recovered
VCM.
b. Description
Vertical-mounted, 18-foot straight wall height, 22-foot
overall height, eight-foot diameter with an approximate capacity of 7,200' gallons, carbon steel construction
c. Normal Operating Conditions
Ambient temperature and 20-70 psig.
3. Water Stripper 45-519 a. Purpose
To provide for collection and recovery of various VCM con
taining vapor vents and waste waters. b. Description
Horizontal-mounted, 26-foot straight wall length, six-foot diameter, approximate capacity 5,500 gallons, carbon steel construction.
c. Normal Operating Conditions
Ambient temperature to 150F and pressure from 10 inches
Hg vacuum to 10 psig.
d. Design Conditions
350F and full vacuum to 150 psig.
DTH 000096766
Operating Manual D-7A5 pvc Reactors
Page 816
IV. EQUIPMENT INDEX (CONTINUED)
C. Tanks and Vessels (Continued)
4. Fresh VCM Storage Tank 45-745
a. Purpose
VCM storage tank which holds fresh VCM used in reactor
charge.
b. Description
Vertical-mounted, 22-foot straight wall height, 26-foot
overall height, eight-foot diameter with an approximate
capacity of 8,700 gallons, carbon steel construction.
c. Normal Operating Conditions
Ambient temperature and 20-70 psig.
d. Design Conditions
150F and full vacuum to 150 psig.
5. Hot Water Tank 45-748
a. Purpose
To supply a large volume of hot water for reactor charge
and rinse.
b. Description
Vertical, cone roof, 42-foot straight wall height, 12-foot
diameter with an approximate capacity of 35,000 gallons,
aluminum construction.
c. Normal Operating Conditions
Atmospheric pressure and 160F.
d. Design Conditions
212F and 1.5 Inches of water.
DTH 000096767
Operating Manual D-745 pvc Reactors
Page 87
IV. EQUIPMENT INDEX (Cont.) C. Tanks and Vessels (Cont.) 6. 1. Initiator Injection Pot 45-75Q a. Purpose To inject initiator into the reactor during charge. b. Description Vertical-mounted, two-foot straight wall height with onefoot diameter, approximate capacity 12 gallons, stainless steel construction. c. Normal Operating Conditions Temperature near 70F and 180-260 psig. d. Design Conditions 150F and 300 psig. 2. Initiator Injection Pot 45-784 a. Purpose To inject initiator into the reactor during charge. b. Description Vertical-mounted, two foot straight wall height with one and one-half foot diameter, approximate capacity 30 gallons, stainless steel construction.
c. Normal Operating Conditions Temperature near 70F and 180-260 psig.
d. Design Conditions 300 0 F and 450 psig
DTH 000096768
Operating Manual D-745 PVC Reactors Page 8$'
IV. EQUIPMENT INDEX (CONTINUED)
C. Tanks and Vessels (Continued)
8. Colloid Storage Tank 45-752
a. Purpose To provide colloid solution storage.
b. Description
Vertical-mounted, flat top, cone bottom, 12-foot straight
wall height, seven-foot diameter, approximate capacity
3,400 gallons, stainless steel construction.
c. Normal Operating Conditions
Atmospheric pressure and 70-85F.
d. Design Conditions
150F and 0 psig
9. Colloid Charge Tank 45-753
a. Purpose
To provide a sufficient quantity of quality colloid solution
for charge.
b. Description
Vertical-mounted, flat top, cone bottom, 14-foot straight
wall height, 5 1/2-foot diameter, capacity approximately 2,400
gallons, stainless steel construction.
c. Normal Operating Conditions
Atmospheric pressure and 70-85F.
d. Design Conditions
150F and 0 psig
DTH 000096770
Operating Manual
D-745PVC Reactors Page 90
IV. EQUIPMENT INDEX (CONTINUED)
C. Tanks and Vessels (Continued)
10. Seal Oil Storage Drum 45-754
a. Purpose
To provide seal oil storage.
b. Description
Horizontal-mounted, five-foot straight wall length by
three-foot diameter, carbon steel construction, approxi
mate capacity 270 gallons.
c. Normal Operating Conditions
Atmospheric pressure, ambient temperature.
d. Design Conditions
150F and 0 psig
11. AMS Short Stop Charge Pots 45-735, 45-756, 45-757, and 45-758
a. Purpose
To provide a means for Injecting short stop solution into
any or all of the reactors to stop the reaction.
b. Description
Vertical-mounted, two-foot straight wall height, six-inch
diameter, capacity approximately three gallons, stainless
steel construction.
c. Normal Operating Conditions
Approximately 70F and 180-260 psig.
d. Design Conditions
150F and 300 psig
DTH 000096771
Operating Manual D-745pvc Reactors Page 91
IV. EQUIPMENT INDEX (CONTINUED) C. Tanks and Vessels (Continued) 12. Mechanical Seal Purge Water Surge Drum 45-759 a. Purpose To provide seal purge water in the event of electrical power failure. b. Description Vertical-mounted, seven-foot straight wall height, 3 1/2-foot diameter, capacity approximately 500 gallons, stainless steel construction. c. Normal Operating Conditions Approximately 70F and 200 pslg. d. Design Conditions 150F and 300 psig 13. Recovery Knockout Drums 45-760 and 45-761 a. Purpose To prevent liquid and solids carryover to the recovery vacuum pumps and compressors during reactor recovery. b. Description Vertical-mounted; bottom section has five-foot straight wall height; five-foot diameter; top section has ten-foot straight wall height; three-foot diameter; top section has water spray to help remove carryover; carbon steel construc tion.
DTH 000096772
Operating Manual D-745 PVC Reactors Page 92
IV. EQUIPMENT INDEX (CONTINUED) C. Tanks and Vessels (Continued) c. Normal Operating Conditions 100-200F and 0-35 psig d. Design Conditions 300F and full vacuum to 150 psig 14. Seal Water Separators 45-762 and 45-763 a. Purpose To separate the circulating vacuum pump and compressor seal water from the recovered VCM vapor. b. Description Vertical-mounted, seven-foot straight wall height, fourfoot diameter, approximate capacity 650 gallons, carbon steel construction. c. Normal Operating Conditions 100-150F and 40-80 psig d. Design Conditions 300F and full vacuum to 150 psig 15. Recovered VCM Collect Tank 45-764 a. Purpose To collect recovered VCM and provide liquid head for VCM transfer pump to allow pumping of recovered VCM to recovered VCM storage tank.
dth 000096773
Operating Manual D-745 PVC Reactors Page 93
IV. EQUIPMENT INDEX (CONTINUED) C. Tanks and Vessels (Continued) b. Description Horizontal-mounted, ten-foot straight wall length, threefoot diameter, approximate capacity 520 gallons, carbon steel construction. c. Normal Operating Conditions 70-100F and 35-75 psig d. Design Conditions 160F and full vacuum to 150 psig 16. Hydroquinone Storage Tank 45-765 a. Purpose Provide for hydroquinone storage and makeup. b. Description Top-agitated, vertical-mounted, 2'6" straight wall height, two-foot diameter, approximate capacity 60 gallons, carbon steel construction. c. Normal Operating Conditions Temperature near ambient; pressure about 1 psig. d. Design Conditions 150F and 16 psig
DTH 000096774
Operating Manual
D-745 pvc Reactors
Page 94
IV. EQUIPMENT INDEX (CONTINUED)
C. Tanks and Vessels (Continued)
17. Slurry Dump Tank 45-766
a. Purpose
To provide sufficient head for the slurry transfer pumps
to operate correctly.
b. Description Vertical-mounted, flat top, cone bottom, three-foot
straight wall height, five-foot diameter, approximate
capacity 440 gallons, stainless steel construction.
c. Normal Operating Conditions
One-inch water vacuum and 150-200F.
d. Design Conditions
250F and two-inch water pressure. 18.` Cleaning Solution Tank 45-767
a. Purpose
To provide an adequate amount of chem wash solution during
reactor chem wash.
b. Description
Vertical-mounted, flat top, cone bottom, ten-foot straight
wall height, ten-foot diameter, approximate capacity 5,800
gallons, carbon steel construction.
c. Normal Operating Conditions
Atmospheric pressure and 60-190F
d. Design Conditions
250F and + five--inch water pressure.
DTH 000096775
Operating Manual
D-745 pvc Reactors Page 95
IV. EQUIPMENT INDEX (CONTINUED) C. Tanks and Vessels (Continued) 19. Reactor Evacuation Ejector Cyclone Separator 45-768 a. Purpose To remove any condensate present In the motive steam to the reactor evacuation steam ejector. b. Description High efficiency horizontal separator, Anderson type L5-4-175, 10 3/4-inch outside diameter, 26 inches long, carbon steel construction with stainless steel internal baffles. c. Normal Operating Conditions Steam in is 125 psig and 353F. d. Design Conditions 400F and 175 psig 20. Reactor Sampling Bomb 45-770 a. Purpose To safely obtain a resin sample from the reactor. b. Description 3/4-inch stainless steel pipe, three inches long. One end is capped, and the other is fitted with a coupling. A basket strainer fits inside the sampler for onsy resin removal. c. Normal Operating Conditions Slight vacuum to 60 psig and 70-140F.
DTH 000096776
Operating Manual D-745 PVC Reactors Page 96 IV. EQUIPMENT INDEX (Cont.)
C. Tanks and Vessels (Cont.) 21. AMS Emergency Kill Pots 45-786 a. Purpose To inject AMS into the reactor during power failure or upon loss of agitation. b. Description Vertical-mounted, three-foot straight wall height, two feet in diameter, capacity approximately 60 gallons, car bon steel construction. c. Normal Operating Conditions Approximately 70F and 300 psig. d. Design Conditions 150F and 400 psig.
DTH 000096777
Operating Manual B-745PVC Reactors Page 97
IV. EQUIPMENT INDEX (CONTINUED) D. Filters 1. Process Water Charge Filter 64-716 a. Purpose To remove dirt and scale from the charge water. b. Description Filterite Model 88MS04--316-4FD-C300, cartridge type, stainless steel. c. Normal Operating Conditions 40 psig and 70F d. Design Conditions 300 psig and 200F. Particle retention size is ten microns. 2. VCM Charge Filters 64-718 and 64-742 a. Purpose To remove any PVC particles from the VCM charge to the reactor. b. Description Filterite model 906415-001, cartridge type, stainless steel filter with polypropylene filtering element. c. Normal Operating Conditions 150-200 psig and ambient temperature. d. Design Conditions 150F, 300 psig, 1,000 gpm, particle retention size is ten microns.
DTH 000096778
Operating Manual D-745 PVC Reactors Page 98
IV. EQUIPMENT INDEX (CONTINUED) D. Filters (Continued) 3. Recovered VCM Filter 64-719 a. Purpose To remove PVC particles from the recovered VCM charge to the reactor. b. Description Filterite Model 909596, cartridge type, stainless steel filter with polypropylene filtering element. c. Normal Operating Conditions 40-130 psig and ambient temperature. d. Design Conditions 150F, 190 psig, 250 gpm, particle retention size ten microns. 4. Process Water Filter 64-720 a. Purpose To remove dirt and scale from process water to the hot water tank. b. Description Dollinger Model LL-122-280, cartridge type, carbon steel filter with polypropylene filtering element. c. Normal Operating Conditions 40 psig and 70F d. Design Conditions 100F, 100 psig, 200 gpm, particle retention size ten microns.
dTH 000096779
Operating Manual D-745?VC Reactors Page 99
IV. EQUIPMENT INDEX (CONTINUED') D. Filters (Continued) 5. Colloid Makeup Water Filter 64-721 a. Purpose To remove dirt and scale from water used in colloid makeup. b.* Description Dollinger Model LL-222-180, Series 150, cartridge type, stainless steel filter, cotton filtering element. c. Normal Operating Conditions 40 psig and 70F d. Design Conditions 250F, 250 psig, 125 gpm, particle retention size ten microns. 6. Service Water Filter 64-724 a. Purpose To remove dirt and scale from service water. b. Description Dollinger Model LL-222-280, cartridge type, stainless steel filter with cotton filtering element. c. Normal Operating Conditions 40 psig and 70F d. Design Conditions 100F, 100 psig, 190 gpm, particle retention size ten microns
OTH 000096^80
Operating Manual 0-745 PVC Reactors Page 100
IV. EQUIPMENT INDEX (CONTINUED) D. Filters (Continued) 7. Seal Oil Supply Filters 64-725 and 64-726 a. Purpose Removes dirt and scale from seal oil. b. ` Description Dollinger Model LL-222-39, Series 150, cartridge type, stainless steel filter with cotton filtering element. c. Normal Operating Conditions 245 psig and 100F d. Design Conditions 150F, 275 psig, 4 gpra, particle retention size one micron.
8. Seal Oil Return Filters 64-727 and 64-728 a. Purpose Removes dirt and scale from seal oil. b. Description Dollinger Model LL-222-39, Series 150, cartridge type, stainless steel filter with cotton filtering elements. c` Normal Operating Conditions 220 psig and 100F d. Design Conditions 150F, 275 psig, 4 gpm, particle retention size one micron.
DTH 000096781
Operating Manual D-745 PVC Reactors Page 101
IV. EQUIPMENT INDEX (CONTINUED) D. Filters (Continued) 9. Seal Water Filters 64-731 and 64-732 a. Purpose To remove PVC resin from the circulating seal water for ;the recovery vacuum pumps and compressors. b. Description Dollinger Model LL-122-140, cartridge type, carbon steel filter with polypropylene filtering element. c. Normal Operating Conditions 90-130 psig and 100-150F d. Design Conditions 300F, 150 psig, 160 gpm, particle retention size 100 microns.
10. Slurry Strainer 64-733 a. Purpose To remove large resin particles from the slurry. b. Description Sweco Model LS605 1210, vibrating screen, stainless steel filter and filtering element. c. Normal Operating Conditions One-inch water vacuum and 150-200F d. Design Conditions 250F, two-inch water pressure, 1,000 gpm, particle reten tion on four-mesh screen.
DTH 000096782
c Operating Manual D-745PVC Reactors Page 102
IV. EQUIPMENT INDEX (CONTINUED) D. Filters (Continued)
11. Cleaning Solution Strainer 64-734 a. Purpose To remove PVC particles from the cleaning solution. b. Description Ten-inch Elco line strainer, carbon steel construction. c. Normal Operating Conditions 2 psig and 180F d. Design Conditions 200F, 20 psig, 500 gpm, particle retention on four-mesh screen.
12. Breathing Air Filters 64-735, 64-736, 64-737, 64-738, 64-739, 64-740_____________________________ _________________________________
Purpose
-r-'
To remove dirt and scale from the breathing air.
Description
Dollinger Model GP-246-15, cartridge type, stainless steel
filter. Nylon 147 filtering element.
Normal Operating Conditions
70-90 psig and 60-70F
Design Conditions
100F, 125 psig, 6,000 standard cubic feet per hour (SCFH),
particle retention size five microns.
^000096783
Operating Manual D-745 PVC Reactors Page 103 IV. EQUIPMENT INDEX (Cont.)
D. Filters (Cont.) 13. Blowdown Tank Drain Strainer 64-741 a. Purpose To remove PVC particles in water dumped to the sewer from the blowdown tank. b. Description Andale type 105 simplex strainer, basket strainer, cast iron with stainless steel filtering element. c. Normal Operating Conditions 8-9 psig and 100 150F d. Design Conditions 200F, 125 psig, 200 gpm, particle retention size 3/8 inch.
DTH 000096784
Operating Manual D-7A5PVC Reactors Page A04
IV. EQUIPMENT INDEX (CONTINUED) E. Pumps 1. VCM Charge Pumps 72-875 and 72-876 a. Purpose To supply reactors with VCM during charge. b. Description Centrifugal type, Goulds Model 3736, 3X6-13DV, Group L, 150-HP, 3,560 RPM. The casing Is carbon steel and the impeller is cast iron. c. Normal Operating Conditions Rated for 800 gpm at 450 feet of differential head. 2. Recovered VCM Charge Pumps 72-877 and 72-878 a. Purpose To supplv recovered VCM to the suction of the VCM charge pumps during charge. b. Description Centrifugal type, Goulds Model 3196 MT, 2X3-13, 25 hp 1,750 rpm. The casing is stainless steel and the impeller is cast iron. c. Normal Operating Conditions Rated for 450 gpm at 82 feet of differential head.
DTH 000096785
Operating Manual
D-745 PVC Reactors Page 105
IV. EQUIPMENT INDEX (CONTINUED)
E. Pumps (Continued)
3. Hot Water Charge Pumps 72-879 and 72-880
a. Purpose
To supply the reactor with hot water during charge.
b. Description
Centrifugal type, Goulds Model 3196 LTC, 2X3-13, 100-HP,
3,550 rpm. The casing is stainless steel and the impeller
is cast iron.
c. Normal Operating Conditions
Rated for 450 gpm at 410 feet of differential head.
4. Colloid Batch Transfer Pump 72-881 and Colloid Circulation Pump 72-882
a. Purpose
The batch transfer pump is used primarily to transfer
colloid from the colloid makeup tank to the colloid storage
tank. The colloid circulation pump is used primarily to
circulate colloid in the storage tank and to transfer col
loid from the storage tank to the colloid charge tank.
These pumps are piped so they can be used to spare each
other.
b. Description
Centrifugal type, Goulds Model 3196 MT, 1X2-10, 3-HP,
1,750 rpm. The casing and impeller are stainless steel.
c. Normal Operating Conditions
Rated for 50 gpm at 69 feet differential head.
DTH 000096786
Operating Manual D-745 PVC Reactors Page 106
IV. EQUIPMENT INDEX (CONTINUED) E. Pumps (Continued) 5. Colloid Charge Pumps 72-883 and 72-884 a. Purpose Used to charge colloid to the reactor. b. Description Centrifugal type, Goulds Model 3736, 1X2-11B, 50-HP, 3,550 rpm. The casing and impeller are stainless steel. c. Normal Operating Conditions Rated for 100 gpm at 470 feet differential head. 6. High Pressure Service Water Pumps 72-885 and 72-886 a. Purpose To provide high pressure water for a variety of uses. b. Description Centrifugal type, Goulds Model 3196 LTC, 2X3-13, 60-HP, 3,550 rpm. The casing and impeller are stainless steel. c. Normal Operating Conditions Rated for 150 gpm at 415 feet of differential head. 7. Mechanical Seal Purge Water Pumps 72-887 and 72-888 a. Purpose To supply high pressure water to the reactor agitator seals and the reactor cleaning nozzle flush. b. Description Centrifugal type, Goulds 3196 MT, 1X2-10, 30-HP, 3,500 rpm. The casing and the impeller are stainless steel.
DTH 000096787
Operating Manual D-745j?VC Reactors Page 107
IV. EQUIPMENT INDEX (CONTINUED) E. Pumps (Continued) c. Normal Operating Conditions Rated for 40 gpm at 415 feet of differential head. 8. Water Recirculation Pumps 72-889 and 72-890 a. Purpose To circulate water in the recovery knockout drums. b. Description Centrifugal type, Goulds Model 3196 MT, 2X3-10, 7 1/2 HP, 1,750 rpm. The casing is stainless steel and the impeller is cast iron. c. Normal Operating Conditions Rated for 200 gpm at 68 feet differential head. 9. Seal Water Pumps 72-891 and 72-892 a. Purpose To circulate the seal water used by the recovery vacuum pumps and compressors. b. Description Centrifugal type, Goulds Model 3196 MT, 2X3-10, 10-HP, 1,750 rpm. The casing is stainless steel and the impeller is cast iron. c. Normal Operating Conditions Rated for 160 gpm at 94 feet of differential head.
DTH 000096788
Operating Manual D-745 PVC- Reactors Page
IV. EQUIPMENT INDEX (CONTINUED) E. Pumps (Continued) 10. Recovered VCM Transfer Pumps 72-893 and 72-894 a. Purpose To transfer recovered VCM from the recovered VCM collect tank to a recovered VCM storage tank. b. Description Centrifugal type, Goulds Model 3196 MT, 1X2-10, 3-HP, 1,750 rpm. The casing is stainless steel and the impeller is cast iron. c. Normal Operating Conditions Rated for 50 gpm at 75 feet of differential head. 11. Hydroquinone Injection Pump 72-895 a. Purpose To supply hydroquinone solution for injection into recovery system seal water during reactor recovery. b. Description Reciprocating type, Milton-Roy Model DB-1-30R, 1/4 HP, 1,750 rpm, carbon steel construction. c. Normal Operating Conditions 0.081 gph at approximately 282 feet of differential head. 12. Slurry Transfer Pumps 72-896 and 72-897 a. Purpose To transfer slurry from the reactor to the slurry blend tanks.
DTH 000096789
Operating Manual D-745pvC Reactors Page 109
IV. EQUIPMENT INDEX (CONTINUED) E. Pumps (Continued) b. Description Centrifugal type, Goulds Model 3196 MT, 4X6-13, 40-HP, 1,770 rpm. The casing and impeller are stainless steel. c. Normal Operating Conditions Rated for 600 gpm at 126 feet of differential head. 13. Cleaning Solution Pumps 72-898 and 72-899 a. Purpose To supply chem wash solution to the reactors during chem wash. b. Description Centrifugal type, Durco Model Mark II, Group II, 4X3-10/80, 75-HP, 3,550 rpm. stainless steel casing and impeller. c. Normal Operating Conditions Rated for 500 gpm at 165 feet of differential head. 14. Blowdown Tank Pump 72-900 a. Purpose To pump water which has been stripped of VCM from the blowdown tank to the sewer. b. Description Centrifugal type, Durco Model Mark II, Group II, 4X3-10/84, 7 1/2 HP, 1,750 rpm. The casing is stainless steel and the impeller is cast iron. c. Normal Operating Conditions Rated for 200 gpm at 63 feet of differential head.
DTH 000096790
Operating Manual B-743PVC Reactors Page HO
IV. EQUIPMENT INDEX (CONTINUED) F. Compressors and Fans 1. Recovery Vacuum Pumps 72-901 and 72-902 a. Purpose To recover unreacted VCM from the polymerization reactors. b. Description Bingham Model 4G-M, 75-HP, 1,200 rpm. Constant volume liquid ring with a water seal. The liquid ring is driven by a multivaned impeller in a circular pumpcase. Construc tion is cast iron casing and ductile iron impeller. c. Normal Operating Conditions 24 inches Hg vacuum to 7 psig inlet, 0-10 psig dishcarge, and 100-150F. 2. Recovery Compressors 72-903, 72-904, and 72-905 a. Purpose To recover unreacted VCM from the polymerization reactors. b. Description Nash Model 1256, 150-HP, constant volume liquid ring with water seal. The liquid ring is driven by a multivaned impeller in a circular pumpcase. Construction is cast iron casing and stainless steel impeller. c. Normal Operating Conditions 0-35 psig inlet, 40-80 psig outlet, and 100-150F.
DTH 000096791
Operating Manual D-745 PVC Reactors Page 111
IV. EQUIPMENT INDEX (CONTINUED) F. Compressors and Fans (Continued) 3. Slurry Strainer Exhauster 49-368 a. Purpose To keep personnel exposure to VCM vapors to a minimum. b. Description Centrifugal fan, Buffalo Forge Model 365 DL, 3-RP, 1,800 rpm, stainless steel construction. c. Normal Operating Conditions Near atmospheric pressure and 150-200F. G. Agitators 1. Reactor Agitators 51-101, 51-102, 51-103, and 51-104 a. Purpose To keep the colloid, VCM, and water in the reactor well mixed. b. Description Bottom entering, single speed, four blades at 45 angle, 200-HP, 125 rpm, stainless steel construction. c. Normal Operating Conditions 15,000 gallons of liquid or slurry in vertical vessel, 22-foot straight wall by 12-foot diameter, at about 120F and 130 psig.
DTH 000096792
Operating Manual D*-745 pvc Reactors Page 1.12
IV. EQUIPMENT INDEX (CONTINUED) G. Agitators (Continued) 2. Colloid Makeup Tank Agitator 51-105 a. Purpose To provide agitation needed to dissolve F-50 methocel in water. b. Description Top entering, single speed, "Lightnin" Model 73-Q-5, 5-HP, 1,750 rpm. Wetted parts are stainless steel. c. Normal Operating Conditions 3,000 gallons of colloid solution; tank is vertical; sevenfoot diameter by 11'6" tall; temperature ranges from 70-250F and atmospheric pressure. 3. Hydroquinone Storage Tank Agitator 51-106 a. Purpose To provide agitation needed to dissolve hydroquinone powder in water. b. Description Top entering, single speed, "Lightnin" Model N33-33, 1/3-HP, 1,750 rpm. c. Normal Operating Conditions Approximately fifty gallons hydroquinone solution in vertical tank 2'6" high by two-foot diameter, 1 psig, and 70F.
DTH 000096793
Operating Manual D-745 PVC Reactors Page 113 IV. EQUIPMENT INDEX (CONTINUED)
H. Package Units 1. Seal Oil Pressure Units 95-299 and 95-300 a. Purpose To supply seal oil to the reactor agitator seals at the required temperature and pressure. b. Description Dura circulator Model SWAR-40-25. c. Normal Operating Conditions 245-250 psig, 100-150F. The seal oil is Di(2-Ethylhexy) phthalate (DOP) which has a viscosity of 35 cp.
DTH 000096794
c Operating Manual D-745 PVC Reactors Page 114
V. INSTRUMENT INDEX
A. Flow Controllers
Item No.
Service
IZRi
Set Point
FIRC-710 FIRC-711 FIRC-712 FIRC-713 FRC-201 '
Reactor Cooling Water Flow Controllers
Meter run with orifice plate, board-mounted indicators and recorders.
Cascade control; the temperature controller of each reactor sets the set point.
NOTE: FIRC-710 controls thecooling water to reactor 45-741.
FIRC-711 controls the cooling water to reactor 45-742.
FIRC-712 controls thecooling water to reactor 45-743-
FIRC-713 controls thecooling water to reactor 45-744.
FRC-201 controls the cooling water to teactor 45-781.
FIC-738 Recovery Vacuum Pump Brooks Model 3611
50 gpm
FIC-739 FIC-740
and Compressor Seal Water Flow Control
lers
Rotameter with trans mitter and a local Foxboro flow con
c troller NOTE: FIC-738 controls the seal water to vacuum pump 72-901 and
compressor 72-903.
FIC-739 controls the seal water to vacuum pump 72-902 and
compressor 72-904.
FIC-740 controls the seal water to compressor 72-905.
FCi-749 FCi-750 FCi-751 FCi-752
Reactor Agitator Mechanical Seal Oil Supply Flow Regulators
Kates Model MFA1-1 Flow Regulator
1.0 gpm
NOTE: FCi-749 controls the seal oil flow to reactor 45-741 double mechanical seal.
FCi-750 controls the seal oil flow to reactor 45-742 double mechanical seal.
FCi-751 controls the seal oil flow to reactor 45-743 double mechanical seal.
FCi-752 controls the seal oil flow to reactor 45-744 double mechanical seal.
DTH 000096795
Operating Manual D-745 PVC Reactors Page 115
V. INSTRUMENT INDEX (Cont.)
B. Flow Totalizers
Item No.
FQIC-701A FQIC-701B
Service VCM Charge Totalizers
IXP
Foxboro Turbine Meter, Board-Mounted Read out
Set Point
Determined by specific batch recipe.
FQIC-702
Recovered VCM Charge Totalizer
Fischer/Porter Vortex Determined by
Shedding Meter, Board specific batch
Mounted Readout
recipe.
FQIC-704
Hot Water Charge Totalizer
Foxboro Turbine Meter, Board-Mounted Read out .
Determined by specific batch recipe.
FQIC-705
Colloid Charge Totalizer
Brooks Oval Meter, Board-Mounted Read out .
Determined by specific batch recipe.
FQIC-706
Colloid Makeup Water Flow Totalizer
Brooks Oval Meter, Local Colloid Board Readout
Hot Water, 538 Gallons
Cold Water, 2,6: Gallons
FQI-798
Reactor Steam Stripping Flow Totalizer
Flow Nozzle with D/P Cell, Board-Mounted Readout.
None; totalizes only.
FQI-757
Hot Water Charge Totalizer Orifice Plate with D/P None; totalizes Cell, Board-Mounted only. Readout.
FQI-811
Steam to Reactor Module Flow Totalizer
Orifice Plate with D/P Cell, Board-Mounted Readout
None; Totalizes only.
FIC-708
Reactor Steam Stripping Flow Control
Flow Nozzle with D/P Cell, Board-Mounted Controller
23,000 lbs/hr.
FQI-203
Initiator Injection Pot
Neptune Displacement
Service Water Flow
Meter, Local Read
Totalizer--D-745 Reactor out only
Determined in Field
DTH 000096796
Operating Manual B-745 PVC Reactors Page 116
V. INSTRUMENT INDEX (CONTINUED)
C. Level Controllers
Item No.
Service
Type
Set Point
LC-720 LC-722
Seal Water Separator Displacer, Fisher
Level Controllers
Model 2500T
16 Inches from Bottom of Dis placer Float
NOTE: LC-720 controls the water level in seal water separator 45-762. LC-722 controls the water level in seal water separator 45-763.
LIC-725
Slurry Dump Tank 45-766 Level Controller
Displacer, Fisher Model 2500T
To be determined in field.
D. Pressure Controllers
Item No.
Service
Type
Set Point
PCi-704
Recovered VCM Storage Tanks 89-520 and 45317 Inert Vent Back pressure Regulator
Self-Contained Pressure Regulator
60 psig
PCi-706
Steam Stripping Header Steam Supply Backpressure Regu lator
Self-Contained Pressure Regulator
100 psig
PIC-725
Recovery Knockout Drum 45-760 Inlet Pressure Controller
Diaphragm with Foxboro Controller
35 psig
PIC-726 PCi-729
VCM Bleed Stream to Recovery System Pressure Controller
Vacuum D/P Transmit ter with a Local Foxboro Controller
3" Hg Vacuum
Hydroquinone Storage Self-Contained Pres Tank 45-765 Nitrogen sure Regulator Pressure Regulator
1 psig
PCi-731
Mechanical Seal Purge Water Surge Drum 45-759 Nitrogen Supply Pressure Regulator
Self-Contained Pres sure Regulator
180 psig
dih ooooae^'7
Operating Manual D-745PVC Reactors Page 117
V. INSTRUMENT INDEX (CONTINUED)
D. Pressure Controllers (Continued)
Item No.
Service
Type
Set Point
PCi-739
Seal Oil Pressure Unit Self-Contained Pres95-299 Nitrogen Supply sure Regulator Pressure Regulator
200 psig
PCi-741
Seal Oil Pressure Unit Self-Contained Pres95-300 Nitrogen Supply sure Regulator Pressure Regulator
200 psig
PCi-743 PCi-744 PCi-745 PCi-746 PCi-747 PCi-752
Breathing Air Station Supply Pressure Regulator
Self-Contained Pressure Regulator
20 psig
NOTE:
PCi-743 regulates breathing air to the reactor area, ground level, PCi-744 regulates breathing air to the reactor area, second level, PCi-745 regulates breathing air to the recovery building, first
floor. PCi-746 regulates breathing air to the recovery building, second
floor. PCi-747 regulates breathing air to the charge area. PCi-752 regulates breathing air to the reactor area, third level.
PCi-754 PCi-755 PCi-756 PCi-757
NO Short Stop Supply Pressure Regulator
Self-Contained Pressure Regulator
200 psig
NOTE:
PCi-754 regulates PCi-755 regulates PCi-756 regulates PCi-757 regulates
NO supply pressure NO supply pressure NO supply pressure NO supply pressure
to reactor 45-741. to reactor 45-742. to reactor 45-743. to reactor 45-744.
PIC-759 Blowdown Tank 45-319 Pressure Controller
Vacuum D/P Transmitter To be Determined
with Local Foxboro
in Field
Controller
OTH 000096793
Operating Manual D-745 PVC Reactors Page H8
V. INSTRUMENT INDEX (CONTINUED)
E. Temperature Controllers
Item No.
Service
Type
Set Point
TIC-701
Hot Water Tank 45-748 Temperature Control ler
Resistance Bulb with Board-Mounted Foxboro Controller
140F
TIC-702
Hot Water Preheater 55-332 Discharge Temperature Con troller
Filled System with Local Foxboro Con troller
145F
TRC-703 Charge Water Temper ature Controller
Resistance Bulb with Board-Mounted Fox boro Controller
Determined by Specific Batch Recipe
TIRC-706 Reactor Polymerization Resistance Bulb with Determined by
TIRC-707 Temperature Control
Foxboro Controller
Specific Batch
TIRC-708 lers
Recipe
TIRC-709
TIRC-201
NOTE: TIRC-706 controls reactor 45-741 polymerization temperature.
TIRC-707 controls reactor 45-742 polymerization temperature.
TIRC-708 controls reactor 45-743 polymerization temperature.
TIRC-709 controls reactor 45-744 polymerization temperature,
TIRC-201 controls reactors 45-781 polymeriz&ion temperature.
TIRC-710 Reactor Steam Strip-
Resistance Bulb with
225*F
TIRC-711 ping Temperature
Board-Mounted
TIRC-712 Controller
Foxboro Controller
TIRC-713 TIRC-202
NOTE: TIRC-710 controls reactor 45-741 steam stripping temperature.
TIRC-711 controls reactor 45-742 steam stripping temperature.
TIRC-712 controls reactor 45-743 steam stripping temperature.
TIRC-713 controls reactor 45-744 steam stripping temperature.
TIRC-202 controls r**ctor 45-781 steam stripping temperature.
TIC-716 Seal Water Temperature Filled System with
i`o be Determined
TIC-717 Controller
Local Foxboro
inField
Controller
NOTE: TIC-716 controls seal water cooler 55-335 outlet temperature. TIC-717 controls seal water cooler 55-336 outlet temperature.
DTH 000096799
Operating Manual
B-745 pvc Reactors
Page 119
V. INSTRUMENT INDEX (CONTINUED)
E. Temperature Controllers (Continued)
Item No.
Service
Type
TIC-718
Cleaning Solution Heater Filled System with
55-339 Outlet Temper-
Local Foxboro
ature Controller
Controller
TIC-730
Water Stripper 45-319 Temperature Controller
Filled System with Local Foxboro
Controller
Set Point L90F
.L75F
DTH 000096800
Operating Manual D-745 PVC Reactors Page 120
VI. ALARMS AND SAFETY EQUIPMENT A. Continuous Flow Fresh Air System In order to provide personnel protection, a continuous flow fresh air system has been installed. This system consists of personnel fresh air masks and a constant flow breathing air supply. The supply lines are piped to all affected areas of the plant. The individual hookup stations consist of quick connect/disconnocttype fittings.
The individual lines to the designated areas are designed to allow a minimum flow of 6 SCFM to each mask at approximately 10-15 psig. An air pressure regulator, shutoff valve, and an air filter are provided at the piping header to each individual area.
The air supply system utilizes two Nash compressors supplying 100 SCFM each at a maximum pressure of 80 psig. Each compressor will supply about fifteen masks with air at one time. The com pressors normally are both in operation at the same time, except in cases of mechanical failure.
The system is equipped with both visable and audible low pressure alarms which are activated at 50 psig. The revolving be,iron light is mounted on a pole to give wider visibility, and the lion is mounted at the compressor. An on-off switch is provided at each compressor.
DTH 000096801
Operating Manual D-745 PVC Reactors Page 121
VI. ALARMS AND SAFETY EQUIPMENT (Cont.)
A. Continuous Flow Fresh Air System (Cont.)
The following job operations will REQUIRE the wearing of a continuous
flow fresh air mask supplied through the fresh air lines or a Scott
Air Pak:
1. Opening any piece of process equipment in vinyl chloride service including:
a. Pumps b. Compressors c. Filters d. Vessels e. Piping
2. Opening a Lenape manway on a reactor without using steam jet evacuation.
3. Entering vessels or may confined area that have contained vinyl chloride.
4. While on top of the large blend tanks which are regulated areas.
5. When using the portable vinyl chloride detector to pinpoint a vinyl chloride leak detected by the continuous monitoring system when the VCM conentration is expected to exceed 10 ppm.
6. Reactor dumping normally does not require the use of a fresh air respirator. Abnormal conditions which would require a fresh air mask are:
a. When working on a plugged reactor dump valve or line. b. Dumping a coarse batch. c. Inoperative Sweco exhauster.
7. Sampling of reactors, VCM railcars, or storage tanks.
8. The heated water vapor coming from vents in the old unit sewer during pump-out of the blowdown tank contain concentrations of VCM above 1 ppm. If an employee must perform work in an area where these vapors exist, an air mask must be worn.
000096802 dth
Operating Manual D-745 PVC Reactors Page 122 VI. ALARMS AND SAFETY EQUIPMENT (Cont.)
A. Continuous Flow Fresh Air System (Cont.) 9. Any other operation which has the possibility of resulting in exposure greater than the permissible exposure limit. The per missible exposure limit is defined as: a. No employee may be exposed to vinyl chloride at concentra tions greater than 1 ppm averaged over any 8-hour period, and b. No emplyee may be exposed to vinyl chloride at concentrations greater than 5 ppm averaged over any period exceeding 15 minutes. c. No empoyee may be exposed to vinyl chloride by direct contact with liquid vinyl chloride.
DTH 000096803
Operating Manual D--745 PVC Reactors Page 123
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches
1. Amperage Alarms
Item No.
Service
Type
Set Point
AAHL-701 AAHL-702
AAHL-703 AAHL-704
Low or High Amperage to the Reactor Agi tator Motor
Board-Mounted Alarm
To be deter mined in the field.
IAHL-200 NOTE: AAHL-701 indicates abnormal amperage to reactor 45-741
agitator motor. AAHL-702 indicates abnormal amperage to reactor 45-742
agitator motor. AAHL-703 indicates abnormal amperage to reactor 45-743
agitator motor.
AAHL-704 indicates abnormal amperage to reactor 45-744 agitator motor.
IAHL-200 indicates abnormal amperage to reactor 45-78.1 agitator motor. 2. Flow Alarms and Switches
Item No.
Service
Type
Set Point
FSL-701A Low VCM Flow during
and B
Charge
Switch that /Acti vates Alarm (FAL-701) on Board
400 gpm
FAL-701 Low VCM Flow during Board-Mounted
Charge
Alarm
400 gpm
FAL-714 FAL-715 FAL-716 FAL-717
Low Seal Water Flow to the Reactor Agitators
Board-Mounted Alarm
2 gpm
NOTE:
FAL-714 indicates low flow to reactor 45-741. FAL-715 indicates low flow to reactor 45-742. FAL-716 indicates low flow to reactor 45-743. FAL-717 indicates low flow to reactor 45-744.
DTH 000096804
Operating Manual D-745PVC Reactors
Page 124
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches (Continued)
3. Level Alarms and Switches
Item No.
Service
LAH-701
High VGM Level in Fresh VCM Storage Tank 45-745
TyPe
Board-Mounted Alarm
Set Point
252 Inches above Bottom Tangent
LSH-701A High VCM Level in Fresh VCM Storage Tank 45-745
Switch Activates LAH-701
252 Inches above Bottom Tangent
LSH-701B High VCM Level in Fresh VCM Storage Tank 45-745
Switch that Serves 252 Inches above . as Charge Permis Bottom Tangent
sive
LSH-701C Level Control of Fresh VCM Receiver 45-745
Switch which Stops 225 Inches Above
VCM Transfer
Discharge Nozzle
LSL-701D Level Control of Fresh VCM Receiver 45-745
Switch which Starts Transfer
219 Inches Above D1 .charge Nozzle
LAH-710
High Level in Col loid Makeup Tank 45-751
Alarm on Colloid Local Board
8 Inches from Top of Tank
LSH-711B High Water Level in Hot Water Tank 45-748
Switch that Serves 129 Inches above as Charge Permis Discharge Nozzle sive
LSH-711C Hot Water Tank 45-758 Level Control
Switch which Stops 360 Inches above Water Transfer on Bottom Tangent High Level
LSL-711D Hot Water Tank 45-748 Level Control
Switch which Starts Water Transfer
350 Inches above Discharge Nozzle
LAH-713
High Level in Col loid Storage Tank 45-752
Board-Mounted Alarm
6 Inches from Top of Tank
DTH 000096805
Operating Manual D-745PVC Reactors Page 125
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches (Continued)
3. Level Alarms and Switches (Continued)
Item No.
Service
LAH-714
High Level in Colloid Charge Tank 45-753
IZP-e
Board-Mounted Alarm
Set Point
8 Inches from Top of Tank
LSL-715
Low Level in Col loid Charge Tank 45-753
Switch Serves as Charge Permis sive
24 Inches above Bottom Tangent
LSH-716
Level Control of Recovery Knockout Drum 45-760
Switch Opens Valve 28 Inches above
to Blowdown Tank
Bottom Tangent
on High Level
LSL-717
Level Control of Recovery Knockout Drum 45-760
Switch Closes Valve to Blow down Tank on Low Level
18 Inches above Bottom Tangent
LSH-718
Level Control of Recovery Knockout Drum 45-761
Switch Opens Valve to Blowdown Tank on High Level
28 Inches above Bottom Tangent
LSH-719
Level Control of Recovery Knockout Drum 45-761
Switch Closes Valve to Blow down Tank on Low Level
18 Inches Above Bottom Tangent
LAH-720
High Level in Seal
Water Separator 45-762
Local Alarm
44 Inches above Bottom Tangent
LAL-720
Low Level in Seal Water Separator 45-762
Local Alarm
16 Inches above Bottom Tangent
LAH-722
High Level in Seal Water Separator 45-763
Local Alarm
44 Inches above Bottom Tangent
LAL-722
Low Level in Seal Water Separator 45-763
Local Alarm
16 Inches above Bottom Tangent
000096806
Operating Manual D-745 PVC Reactors Page 126
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches (Continued)
3. Level Alarms and Switches (Continued)
Item No.
Service
Type
Set Point
LAH-725
High Level in Slurry Dump Tank 45-766
Board-Mounted Alarm
6 Inches from Top of Tank
LAH-727
High Level in Cleaning Solution Tank 45-767
Board-Mounted Alarm
6 Inches from Top of Tank
LAL-729
Low Level In Cleaning Solution Tank 45-767
Board-Mounted Alarm
6 Inches from Bottom of Tank
LSL-730
Low Level in Seal Oil Reservoir 95-299
Switch Activates LAL-730, Starts Spare Seal Oil Unit 95-300, and Turns Off 95-299
To be Defined by Vendor
LAL-730
Low Level in Seal Oil Reservoir 95-299
Board-Mounted Alarm
To be Defined by
LSL-731
LAL-731 LAL-733
Low Level in Seal Oil Reservoir 95-300
Low Level in Seal Oil Reservoir 95-300
Low Level in Hydroquinone Storage Tank 45-765
Switch Activates LAL-731, Starts Spare Seal Oil Unit 95-299, and Turns Off 95-300
Board-Mounted Alarm
Board-Mounted Alarm
To be Defined by Vendor
To be Defined by Vendor
6 Inches above Bottom Tangent
LAH-734
High Level in Cleaning Solution Tank 45-767
Switch Shuts Down 6 Inches from Cleaning Solution Top of Tank Pumps 72-898 and 72-899 and Caustic Transfer Pumps
LAL-739
Low Level in Colloid Makeup Tank 45-751
Board-Mounted Alarm
One Inch above Bottom Tangent
DTH 000096807
Operating Manual D-745 PVC Reactors Pagel27
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches (Continued)
3. Level Alarms and Switches (Continued)
Item No.
Service
Type
Set Point
LAH-740
High Level in Blow down Tank 45-319
Board-Mounted Alarm
22 Inches from Top of Tank
LSL-741
Low Level in Blow down Tank 45-319
Switch will Shut Off Blowdown Tank Pump 72-900 and Close Valves CV-880 and CV-891
12 Inches from Bottom of Tank
4. Pressure Alarms and Switches
Item No.
Service
Type
Set Point
PSH-703
High Pressure in Initiator Injec tion Pot 45-750
Switch turns on high pressure light on the board and is a precharge condition.
180 psig
PSL-707
Low Pressure in Steam Stripping Header
Switch closes control valve that supplies steam to the reactor during steam strip ping.
100 psig
PSL-712 PSL-713 PSL-714 PSL-715 PSL-205
Low Pressure in Reactor during Recovery
Switch prevents opening of reactor dump valve unless pres sure during recovery has been at least as low as set point.
8 psig
NOTE:
PSL-712 senses pressure in reactor 45-741. PSL-713 senses pressure in reactor 45-742. PSL-714 senses pressure in reactor 45-743. PSL-715 senses pressure in reactor 45-744. PSL-205 senses pressure in reactor 45-781
DTH 000096808
Operating Manual D-745 PVC Reactors Page 128
VI. ALARMS AND SAFETY EQUIPMENT (Cont.)
B. Alarms and Switches (Cont.)
4. Pressure Alarms and Switches (Cont.)
Item No.
Service
PSL-716 PSL-717 PSL-718 PSL-719
Low Pressure in Reactors during Evacuation
1ZE
Sv/itch keeps charge from starting by preventing main reactor charge valve from opening unless pres sure is at low set point/ or above.
Set Point
25" Hg Vacuum
NOTE:
PSL-716 senses pressure in reactor 45-741. PSL-717 senses pressure in reactor 45-742. PSL-718 senses pressure in reactor 45-743. PSL-719 senses pressure in reactor 45-744.
PAH-720 PAH-721 PAH-722 PAH-723 PAH-206
High Pressure in Reactors
Board-Mounted Alarm
160 psig
NOTE:
PAH-720 indicates high pressure in reactor 45-741. PAH-721 indicates high pressure in reactor 45-742. PAH-722 indicates high pressure in reactor 45-743. PAH-723 indicates high pressure in reactor 45-744. PAH-206 indicates high pressure in reactor 45-781
PSL-727
Low Recovery Com pressor Suction Pressure
Switch will start recovery vacuum pumps 72-901 and 72-902 and activate proper valving sequence during recovery
7 psig
PDS-728
High Differential Pressure Between Recovery Vacuum Pump Suction and Recovery Compres sor Discharge
Switch shuts off recovery compressors 72-903, 72-904, and 72905 and vacuum pumps 72-901 and 72-902.
80 psig
PSL-732
Low Pressure on High Pressure Service Water System
Switch prevents automatic matic charge sequence from beginning and activates PAL-732
150 psig
PAL-212 Low Pressure on AMS kill Pot
Switch alerts operator to low
275 psig
nitrogen pressure on Emer
gency AMS Kill pot.
DTH 000096809
Operating Manual
D-74.5PVC Reactors Page 129
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches (Continued)
4. Pressure Alarms and Switches (Continued)
Item No.
Service
Type
PAL-732
Low Pressure on High Board-Mounted Alarm Pressure Service Water System
PSL-737
Low Pressure on Mechanical Seal Purge Water System (MSPW)
Switch activates PAL-737 and turns on spare (MSPW) pump 72-887 or 72-888.
PAL-737
Low Pressure on Mechanical Seal Purge Water System
Board-Mounted Alarm
PSL-738
Low Pressure from Seal Oil Unit 95-299
Switch activates spare seal oil unit 95-300, turns off 95-299, acti vates the necessary valves, and acti vates PAL-738.
PAL-738
Low Pressure from Seal Oil Unit 95-299
Board-Mounted Alarm
PSL-740
Low Pressure from Seal Oil Unit 95-300
Switch activates spare seal oil unit 95-299, turns off 95-300, activates the necessary valves, and acti vates PAL-740.
PAL-740
Low Pressure from Seal Oil Unit 95-300
Board-Mounted Alarm
PAH-750
High Pressure on Initiator Injec tion Pot 45-750
Board-Mounted Alarm
Set Point 150 pslg 180 psig
180 psig 205 psig
205 psig 205 psig
205 psig 225 psig
DTH 000096810
Operating Manual D-745PVC Reactors Page 130
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
B. Alarms and Switches (Continued)
4. Pressure Alarms and Switches (Continued)
Item No.
Service
TyPe
PAH-751
High Seal Oil System Board-Mounted Alarm Pressure
Set Point 255 psig
PAL-753
Low Pressure on NO Short Stop Bottles
Board-Mounted Alarm
350 psig
PSL-758
Low Pressure on High Pressure Service Water System (HPSW)
Switch turns on spare HPSW pump 72-885 or 72-886.
180 psig
PAH-760 High Pressure in
Board-Mounted Alarm
10 psig
Blowdown Tank
c 45-319
PSL-762 Low Steam Pressure
Switch closes TCV-730 40 psig
to Blowdown Tank
and PCV-759 and re
45-319
sets on rising steam
pressure of 50 psig.
PAL-763
Low Instrument Air Pressure
Board-Mounted Alarm
85 psig
TAH-706 High Temperature
Board-Mounted Alarm
160F
TAH-707
in the Reactors
TAH-708
TAH-709
TAH-201
NOTE: TAH-706 indicates high temperature in reactor 45-741.
TAH-707 indicates high temperature in reactor 45-742.
TAH-708 indicates high temperature in reactor 45-743.
TAH-709 indicates high temperature in reactor 45-744.
TAH-201 indicates high temperature in reactor 45-781.
TAH-715 High Discharge
Board-Mounted Alarm
150F
Temperature on
the Recovery
Compressors
TAH-719 High Seal Oil
Board-Mounted Alarm
125F
Temperature
c TAH-720 High Temperature in Board-Mounted Alarm
75 F
Initiator Injec
tion Pot 45-750
dTH 000096811
A
Operating Manual D-745 PVC Reactors Page 131
VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED) C. Firewater System The firewater system consists of a deluge system, combustible hydrocarbon analyzer, and fire monitors with hose connections. 1. Fire Monitors The fire monitors are normally supplied from the city water system. A tie-in with the firewater system allows the fire monitors to operate off either water system. There are six fire monitors located around the perimeter of the recovery building and reactor area. 2. Hydrocarbon Analyzer A continuous combustible hydrocarbon analyzer is used to detect major VCM leaks. When the VCM level at any sample point reaches the set point, the deluge system is activated automatically. 3. Deluge System The deluge system is normally supplied from the firewater system. It can be operated on process water. The deluge system is a sprinkler system which will cover the reactors, dump system, fresh and recovered VCM storage tanks, and both floors of the recovery building with a water spray. The deluge system is designed to lower VCM concentrations in the reactor and recovery building area in the event of a VCM leak and as a sprinkler system to help put out fires. The deluge system can be acti
vated manually, by the combustible hydrocarbon analyzer, or by thermal sensors.
DTH 000096812
Operating Manual D-745PVC Reactors Page 132 VI. ALARMS AND SAFETY EQUIPMENT (CONTINUED)
C. Firewater System (Continued) 3. Deluge System (Continued) The revised firewater system contains three new post indicator valves (PIV) and one PIV was relocated. These are valves which have indicators on them to show whether the valve Ls open or closed. These valves are used to direct water to either the D-700 reactor area or the V-ll area. The valves are located at: 1. The southwest corner of the new cooling water tower. 2. East wall of the V-ll building. 3. Two are located at the northwest corner of the intersec tion of the entrance road and second street.
D. Fixed Point VCM Monitor A fixed point VCM monitor is used to detect VCM and record the VCM concentration at various locations in the reactor and recovery building. The readout is on a chart in the control room.
DTH 000096813
Operating Manual D-745PVC Reactors Page 133 VII. EQUIPMENT ENTRY PROCEDURE
EPA standards for VCM emissions and OSHA regulations on personnel exposure to VCM require that certain operating procedures be followed when there is the possibility of VCM emission to the atmosphere or personnel exposure to VCM. For this reason and to ensure safe working conditions at all times, the "Engineering and Work Practice Control Program for the Reduction of Employee Exposure to Vinyl Chloride" manual should be consulted whenever equipment in the reactor area is opened for any reason. This manual contains a list of detailed procedures as well as safety precautions for equipment opening. Every vessel has an entry check list that must be filled out by the Shift Supervior. The entry check list contains a building list for opening a vessel.
D1H 000096814
Tanks and Vessels (Contim ted)
45-759 45-760 45-761 45-762 45-765 45-764 45-765 45-766 45-767 45-768 45-770 45-778 45-786
Filters
64-716 64-718 64-719 64-720 64-721 64-722 64-723 64-724 64-725
64-726
64-727
64-728
64-731 64-732 64-733 64-734 64-735 64-736 64-737
64-738
64-739 64-740 64-741 64-742
APPENDIX A
EQUIPMENT LIST - CONTINUED
Service
Mechanical Seal Purge Water Surge Drum South Recovery Knockout Drum North Recovery Knockout Drum South Seal Water Separator North Seal "Water Separator Recovered VCM Collect Tank" Hydroquinone Storage Tank Slurry Dump Tank Cleaning Solution Tank Reactor Evacuation Ejector Cyclone Separator Reactor Sampling Bofc-.. Initiator Charge Pot for Reactor 45-781 AMS Emergency Kill Pot for Reactor 45-781
Process Water Charge Filter North VCM Charge Filter Recovered VCM Filter Process Water Filter Colloid Makeup Water Filter North Colloid Transfer Filter South Colloid Transfer Filter Service Water Filter Seal Oil Supply Filter for Seal Oil Pressure
Unit 95-299 Seal Oil Supply Filter for Seal Oil Pressure
Unit 95-300 Seal Oil Return Filter for Seal Oil Pressure
Unit 95-299 Seal Oil Return Filter for Seal Oil Pressure
Unit 95-300 South Seal Water Filter North Seal Water Filter Slurry Strainer Cleaning Solution Strainer Breathing Air Filter (Reactors, First Level) Breathing Air Filter (Reactors, Second Level) Breathing Air Filter (Recovery Building
First Floor) Breathing Air Filter (Recovery Building,
Second Floor) Breathing Air Filter (Charge Area) Breathing Air Filter (Reactors, Third Level) Blowdown Tank Drain Strainer South VCM Charge Filter
DTH 000096815
Reactors
45-741 45-742 45-743 45-744 45-781
Heat Exchangers
55-328 55-329 55-330 55-331 55-358 55-332 55-333 55-334 55-335 55-336 55-337 55-338 55-339
Eductors and Ejectors
EE-701 EE-702 EE-703 EE-704 EE-705 EE-201 A, B, 8 C EE-200
Tanks and Vessels
45-301 45-317 89-520 45-319 45-745 45-748 45-750 45-751 45-752 45-753 45-754 45-755 45-756 45-757 45-758
APPENDIX A EQUIPMENT LIST
Polymerization Reactor Polymerization Reactor Polymerization Reactor Polymerization Reactor Polymerization Reactor
Reactor 45-741 Condenser Reactor 45-742 Condenser Reactor 45-743 Condenser Reactor 45^744'Condenser Reactor 45-781 Condenser Hot Water Preheater Hot Water Tank Heater Water Recirculation Cooler West Seal Water Cooler East Seal Water Cooler West Recovered VCM Condenser East Recovered VCM Condenser Cleaning Solution Heater
Reactor 45-741 Jacket Eductor Reactor 45-742 Jacket Eductor Reactor 45-743 Jacket Eductor Reactor 45-744 Jacket Eductor Reactor Evacuation Ejector Reactor 45-781 Jacket Eductor Reactor Evacuation Ejector
Instrument air Capacity Tank
East Recovered VCM Storage Tank
West Recovered VCM Storage Tank
Blowdown Tank
Fresh VCM Storage Tank
Hot Water Tank
Initiator Injection Pot
Colloid Makeup Tank
Colloid Storage Tank Colloid Charge Tank
DTH 000096816
Seal Oil Storage Drum
AMS Short Stop ChargePot for Reactor 45-741
AMS Short Stop ChargePot for Reactor 45-742
AMS Short Stop ChargePot for Reacto-r 45-743
AMS Short Stop ChargePot for Reactor 45-744
APPENDIX A EQUIPMENT LIST - CONTINUED
Pumps
Motor
72-875 72-876 72-877 72-878 72-879 72-880 72-881 72-882 72-883 72-884 72-885 72-886 72-887 72-888 72-889 72-890 72-891 72-892 72-893 72-884 72-895 72-896 72-897 72-898 72-899 72-900
70-875 70-876 70-877 70-878 70-879 70-880 70-881 70-882 70-883 70-884 70-885 70-886 70-887 70-888 70-889 70-890 70-891 70-892 70-893 70-894 70-895 70-896 70-897 70-898 70-899 70-900
Compressors and Fans
Motor
72-901 72-902 72-903 72-904 72-905 49-368
70-901 70-902 70-903 70-904 70-905 70-864
Agitators
Motor
51-101 51-102 51-103 51-104 51-105 51-106 51-110
70-814
70-815 70-816 70-817 70-818 70-819 70-971
Service
VCM Charge Pump VCM Charge Pump Recovered VCM Charge Pump Recovered VCM Charge Pump Hot Water Charge Pump Hot Water Charge Pump Colloid Batch Transfer Pump Colloid Circulation Pump Colloid Charge Pump Colloid Charge Pump High Pressure Service Water Pump High Pressure Service Water Pump Mechanical Seal Purge Water Pump Mechanical Seal Purge Water Pump Water Recirculation Pump Water Recirculation Pump Seal Water Pump Seal Water Pump Recovered VCM Transfer Pump Recovered VCM Transfer Pump Hydroquinone Injection Pump Slurry Transfer Pump Slurry Transfer Pump Cleaning Solution Pump Cleaning Solution Pump Blowdown Tank Pump
Recovery Vacuum Pump Recovery Vacuum Pump Recovery Compressor Recovery Compressor Recovery Compressor Slurry Strainer Exhauster
Reactor 45-741 Agitator
Reactor 45-742 Agitator Reactor 45-743 Agitator Reactor 45-744 Agitator Colloid Makeup Tank Agitator Hydroquinone Storage Tank Agitator Reactor 45-781 Agitator
X)TH 000096817
Package Units
95-299 95-300 PA-703 PA-704 PA-705 PA-706 PA-707 PA-708 PA-709 PA-710 PA-711 PA-712 PA-713 PA-714 PA-715 PA-716 PA-717
PA-200 PA-201
APPENDIX A
EQUIPMENT LIST - CONTINUED
Service
Seal Oil Pressure Unit Seal Oil Pressure Unit Deluge System Deluge System Combustible Hydrocarbon Analyzer Fire Monitor Fire Monitor Fire Monitor Fire Monitor Fire Monitor Fire Monitor Deleted Fixed Point VCM Monitor Emergency NO Short Stop Bottles Emergency NO Short Stop Bottles Emergency NO Short Stop Bottles Emergency NO Short Stop Bottles Programmable Logic Controller Emergency NO Short Stop Bottles Nitrogen Supply bottle to AMS Emergency Kill Pot
DTH 000096818
APPENDIX B INSTRUMENT LIST
Item No.
Service
Amperage Instruments
AI-701 AAHL-701 AI-702 AAHL-702 AI-703 AAHL-703 AI-704 AAHL-704 AI-705 AI-706 AI-707 AI-708 AI-709
Reactor Agitator 51-101 Motor Amperage Indicator Reactor Agitator 51-101 Motor High or Low Amperage Alarm Reactor Agitator 51-102 Motor Amperage Indicator Reactor Agitator 51-102 Motor High or Low Amperage Alarm Reactor Agitator 51-103 Motor Amperage Indicator Reactor Agitator 51-103 Motor High or Low Amperage Alarm Reactor Agitator 51-104 Motor Amperage Indicator Reactor Agitator 51-104 Motor High or Low Amperage Alarm Recovery Vacuum Pump 72-901 Motor Amperage Recovery Vacuum Pump 72-902 Motor Amperage Recovery Compressor 72-903 Motor Amperage Recovery Compressor 72-904 Motor Amperage Recovery Compressor 72-905 Motor Amperage
Control Valves
CV-701 CV-702 CV-703 CV-704 CV-705 CV-706 CV-707 CV-708 CV-709 CV-710 CV-711 CV-712 CV-713 CV-714 CV-715 CV-716 CV-717 CV-718 CV-719 CV-720 CV-721 CV-722 CV-723 CV-724 CV-725 CV-726 CV-727 CV-728
Fresh VCM Storage Tank 45-745 Outlet Valve Deleted
Recovered VCM Valve to VCM Charge Pumps 72-875 and 72-876 VCM Charge Pump 72-875 Discharge Valve VCM Charge Pusq> 72-876 Discharge Valve Hot Water Tank 45-748 Outlet Valve Colloid Charge Pump 72-885 Discharge Valve Deleted Hot Water Valve to Colloid Makeup Tank 45-751 Reactor 45-741 Main Charge Valve Reactor 45-741 Colloid Charge Valve Reactor 45-741 Steam Stripping Valve Reactor Condenser 55-328 Cleaning and Rinse Valve Reactor 45-741 Vent Valve Reactor 45-741 Inert Vent Valve Reactor 45-741 Recovery and Evacuation Valve Reactor 45-741 Cleaning and Rinse Valve Deleted Deleted Reactor 45-742 Main Charge Valve Reactor 45-742 Colloid Charge Valve Reactor 45-742 Steam Stripping Valve Reactor Condenser 55-329 Cleaning and Rinse Valve Reactor 45-742 Vent Valve Reactor 45-742 Inert Vent Valve Reactor 45-742 Recovery and Evacuation Valve Reactor 45-742 Cleaning and Rinse Valve Deleted
DTH 000096819
c c
c
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No
Service
Control Valves (Continued)
CV-729 CV-730 CV-731 CV-732
CV-733 CV-734 CV-735 CV-736 CV-737 CV-738 CV-739 CV-740 CV-741 CV-742 CV-743 CV-744 CV-745 CV-746 CV-747 CV-748 CV-749 CV-750 CV-751 CV-752 CV-753 CV-754 CV-755 CV-756 CV-757 CV-758 CV-759 CV-760 CV-761 CV-762 CV-763 CV-764 CV-765 CV-766 CV-767 CV-768 CV-769 CV-770 CV-771 CV-772
Deleted Reactor 45-743 Main Charge Valve Reactor 45-743 Colloid Charge Valve Reactor 45-743 Steam Stripping Valve Reactor Condenser 55-330 Cleaning and Rinse Valve Reactor 45-743 Vent Valve Reactor 45-743 Inert Vent Valve Reactor 45-743 Recovery and Evacuation Valve Reactor 45-743 Cleaning and Rinse Valve Deleted Deleted Reactor 45-744 Main Charge Valve Reactor 45-744 Colloid Charge Valve Reactor 45-744 Steam Stripping Valve Reactor Condenser 55-331 Cleaning and Rinse Valve Reactor 45-744 Vent Valve Reactor 45-744 Inert Vent Valve Reactor 45-744 Recovery and Evacuation Valve Reactor 45-744 Cleaning and Rinse Valve Deleted Deleted Reactor 45-741 Hot Water Rinse Supply Valve Reactor Condenser 45-741 Chem Wash Solution Supply Valve Reactor 45-741 Recovery Valve Reactor 45-741 Initiator Charge Valve Reactor 45-741 VCM Charge Valve Reactor 45-741 Water Charge Valve Deleted
Reactor 45-741 Initiator Charge.Line Sewer Valve Reactor 45-741 Slurry Dump Valve Reactor 45-741 Sewer Drain Valve Reactor 45-741 Chem Wash Solution Return Valve Deleted Reactor 45-741 Evacuation Valve Reactor 45-741 Initiator Charge Valve Reactor 45-742 Hot Water Rinse Supply Valve Reactor 45-742 Evacuation Valve Reactor 45-742 Chem Wash Solution Supply Valve Reactor 45-742 Recovery Valve Reactor 45-742 Initiator Charge Valve Reactor 45-742 VCM Charge Valve
Reactor 45-742 Water Charge Valve Deleted Reactor 45-742 Slurry Dump Valve
ATH 000096820
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Control Valves (Continued)
CV-773 CV-774 CV-775 CV-776 CV-777 CV-778 CV-779 CV-780 CV-781 CV-782 CV-783 CV-784 CV-785 CV-786 CV-787 CV-788 CV-789 CV-790 CV-791 CV-792 CV-793 CV-794 CV-795 CV-796 CV-797 CV-798 CV-799 CV-800 CV-801 CV-802 CV-803 CV-804 CV-805 CV-806 CV-807 CV-808 CV-809 CV-810 CV-811 CV-812 CV-813
CV-814
Reactor 45-742 Chem Wash Solution Return Valve Reactor 45-742 Sewer Drain V^lveDeleted Reactor 45-742 Initiator Charge Valve Reactor 45-742 Initiator Charge Line Sewer Valve Reactor 45-743 Hot Water Rinse Supply Valve Reactor 45-743 Evacuation Valve Reactor 45-743 Chem Wash Solution Supply Valve
Reactor 45-743 Recovery Valve Reactor 45-743 Initiator Charge Valve Reactor 45-743 VCM Charge Valve Reactor 45-743 Water Charge Valve Deleted Reactor 45-743 Slurry Dump Valve Reactor 45-743 Chem Wash Solution Return Valve Reactor 45-743 Sewer Drain Valve Deleted Reactor 45-743 Initiator Charge Valve Reactor 45-743 Initiator Charge Line Sewer Valve Reactor 45-744 Hot Water Rinse Supply Valve Reactor 45-744 Evacuatiov Valve Reactor 45-744 Chem Wash Solution Supply Valve Reactor 45-744 Initiator Charge Valve Reactor 45-744 VCM Charge Valve Reactor 45-744 Water Charge Valve Deleted Reactor 45-744 Slurry Dump Valve Reactor 45-744 Chem Wash Solution Return Valve Reactor 45-744 Sewer Drain Vlave Deleted Reactor 45-744 Initiator Charge Valve Reactor 45-744 Initiator Charge Line Sewer Valve Reactor 45-744 Recovery Valve Colloid Charge Pump 72-884 Discharge Valve Deleted Cold Water Addition Valve for Swirl Cold Water Addition Valve for Charge Recovery Vacuum Pusq> 72-901 Suction V*lve Recovery Vacuum Puiq> 72-901 Discharge Valve Recovery Vacuum Pump 72-901 Seal Water Supply Valve Recovery Vacuum Pump 72-901 Mechanical Seal Water
Supply Valve Reactor Jacket Eductor EE-701 Steam Valve
DTH 000096821
\
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Control Valves (Continued)
CV-815 CV-816 CV-817 CV-818 CV-819 CV-820 CV-821 CV-822 CV-823
CV-824 CV-825 CV-826 CV-827 CV-828 CV-829 CV-830 CV-831 CV-832 CV-833
CV-834 CV-835
CV-836
CV-837 CV-838
CV-839 CV-840 CV-841 CV-842 CV-843
CV-844
CV-845 CV-846 CV-847 CV-848 CV-849 CV-850 CV-851
Reactor Jacket Eductor EE-702 Steam Valve Reactor Jacket Eductor EE-703 Steam Valve Reactor Jacket Eductor EE-704 Steam Valve Fresh VCM Storage Tank 45-745 Inlet Valve. Hot Water Preheater 55-332 Water Inlet Valve Recovery Vacuum Pump 72-902 Suction Valve Recovery Vacuum Pump 72-902 Discharge Valve Recovery Vacuum Pump 72-902 Seal Water Supply Valve Recovery Vacuum Pump 72-902 Mechanical Seal Water
Supply Valve Deleted Deleted Deleted Deleted Colloid Makeup Tank 45-751 Process Water Valve Hot Water Charge Pump 72-880 Discharge Valve Recovery Compressor 72-903 Suction Valve Recovery Compressor 72-903 Discharge Valve Recovery Compressor 72-903 Seal Water Supply Valve Recovery Compressor 72-903 Mechanical Seal Water
Supply Valve Deleted
Water Recirculation Cooler 55-334 Cooling Water Return Valve
Recovery Knockout Drum 45-760 Water Recirculation Inlet Valve
Recovery Knockout Drum 45-760 Water Blowdown Valve
Recovery Knockout Drum 45-761 Water Recirculation Inlet Valve
Recovery Knockout Drum 45-761 Water Blowdown Valve Recovery Compressor 72-904 Suction Valve Recovery Compressor 72-904 Discharge Valve Recovery Compressor 72-904 Seal Water Supply Valve Recovery Compressor 72-904 Mechanical Seal Water
Supply Valve Recovered VCM Condensers 55-337 and 55-338 Cooling
Water Return Valve Deleted Deleted Reactor Evacuation Ejector EE-706 First Stage Steam Valve Reactor Evacuation Ejector EE-706 Second Stage Steam Valve Hot Water Charge Pump 72-879 Discharge Valve Recovery Compressor 72-905 Suction Valve Recovery Compressor 72-905 Discharge Valve
DTH 000096822
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Control Valves (Continued)
CV-852 CV-853
CV-854 CV-855
CV-856 CV-857 CV-858
CV-859 CV-860 CV-861 CV-862 CV-863 CV-864 CV-865 CV-866 CV-867 CV-868 CV-869 CV-870 CV-.J71 CV-872 CV-873 CV-874
CV-875 CV-876 CV-877 CV-878 CV-879
CV-880 CV-881 CV-882 CV-883 CV-884 CV-885 CV-886 CV-887 CV-888 CV-889 CV-890
Recovery Compressor 72-905 Seal Water Supply Valve Recovery Compressor 72-905 Mechanical Seal Water
Supply Valve Recovery Vacuum Pumps 72-901 and 72-902 Bypass Valve Recovery Compressors 72-903, 72-904, and 72-905
Bypass Valve Colloid Makeup Tank 45-751 Water Inlet Valve Colloid Makeup Tank 45-751 Colloid Outlet Valve Colloid Recirculation Valve to Colloid Storage Tank
45-752 Colloid Circulation Pump 72-882 Inlet Valve Deleted Colloid Charge Tank 45-753 Inlet Valve Deleted Dump System Water Rinse Valve Slurry Transfer Punqp 72-896 Mechanical Seal Water Valve Deleted Slurry Transfer Punqs 72-897 Mechanical Seal Water Valve Deleted Deleted Deleted Deleted Cleaning Solution Heater 55-339 Inlet Valve Cleaning Solution Storage Tank 45-767 Top Inlet Valve Cleaning Solution Pumps 72-898 and 72-899 Suction Valve Reactor Cleaning Solution Return Valve to Cleaning
Solution Tank 45-767 Seal Oil Pressure Unit 95-300 Seal Oil Return Valve Seal Oil PressureUnit 95-299 Seal Oil Return Valve Seal Oil PressureUnit 95-300 Seal Oil Supply Valve Seal Oil PressureUnit 95-299 Seal Oil Supply Valve Initiator Injection Pot 45-750 Service Water Inlet
Valve Blowdown Tank Pump 72-900 Discharge Valve 45-741 Emergency NO Short Stop Three-Way Valve 45-742 Emergency NO Short Stop Three-Way Valve 45-743 Emergency NO Short Stop Three-Way Valve 45-744 Emergency NO Short Stop Three-Way Valve 45-741 Emergency NO Short Stop Valve 45-742 Emergency NO Short Stop Valve 45-743 Emergency NO Short Stop Valve 45-744 Emergency NO Short Stop Valve Recovery Seal Water and VCM Diverter Valve Recovery Seal Water and VCM Diverter Valve
EftH 000096823
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Level Instruments (Continued)
LIC-726 LA-726 LAH-727 LI-728 LAL-729 LSL-730
LAL-730
LSL-731
LAL-731
LC-732 LAL-733 LSH-734 LA-735 LA-736 LA-737 LA-738 LAL-739 LAH-740 LSL-741
Deleted Deleted Cleaning Solution Tank 45-767 High Level Alarm Cleaning Solution Tank 45-767 Level Indicator Cleaning Solution Tank 45-767 Low Level Alarm Seal Oil Pressure Unit 95-299 Reservoir Low Level
Switch Seal Oil Pressure Unit 95-299 Reservoir Low Level
Alarm Seal Oil Pressure Unit 95-300 Reservoir Low Level
Switch Seal Oil Pressure Unit 95-300 Reservoir Low Level
Alarm Deleted Hydroquinone Storage Tank 45-765 Low Level Alarm Cleaning Solution Tank 45-767 High Level Switch Deleted Deleted Deleted
Deleted Colloid Makeup Tank 45-751 Low Level Alarm Blowdown Tank 45-319 High Level Alarm Blowdown Tank 45-319 Low Level Switch
Pressure Gauges
PG-701 PG-702 PG-703 PG-704 PG-705 PG-706 PG-707 PG-708 PG-709 PG-710 PG-711 PG-712 PG-713 PG-714 PA-715 PG-716 PG-717 PG-718
VCM Charge Pump 72-875 Discharge Pressure Gauge VCM Charge Pump 72-876 Discharge Pressure Gauge Recovered VCM Charge Pump 72-877 Discharge Pressure Gauge Recovered VCM Charge Pump 72-878 Discharge Pressure Gauge Fresh VCM Storage Tank 45-745 Pressure Gauge Recovered VCM Storage Tank 89-520 Pressure Gauge Recovered VCM Storage Tank 45-317 Pressure Gauge Deleted Deleted Deleted Deleted Process Water Filter 64-720 Inlet Pressure Gauge Process Water Filter 64-720 Outlet Pressure Gauge Hot Water Charge Pump 72-879 Discharge Pressure Gauge Hot Water Charge Pump 72-880 Discharge Pressure Gauge Deleted Deleted Deleted
DTH 000096824
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Pressure Gauges (Continued)
PG-719 PG-720 PG-721
PG-722 PG-723 PG-724 PG-725 PG-726 PG-727 PG-728 PG-729 PG-730 PG-731 PG-732 PG-733 PG-734 PG-735 PG-736 PG-737 PG-738 PG-739 PG-740 PG-741 PG-742 PG-743 PG-744 PG-745 PG-746 PG-747 PG-748 PG-749 PG-750 PG-751 PG-752
PG-753
PG-754 PG-755 PG-756 PG-757 PG-758 PG-759
Colloid Makeup Water Filter 64-721 Inlet Pressure Gauge Colloid Makeup Water Filter 64-721 Outlet Pressure Gauge Colloid Batch Transfer Pump 72-881 Discharge Pressure
Gauge Colloid Transfer Filter 64-722 Outlet Pressure Gauge Colloid Circulation Pump 72-882 Discharge Pressure Gauge Colloid Transfer Filter 64-723 Outlet Pressure Gauge Colloid Charge Pump 72-883 Discharge Pressure Gauge Colloid Charge Pump 72-884 Discharge Pressure Gauge Steam Stripping Header Pressure Gauge Reactor 45-741 Steam Stripping Line Pressure Gauge Deleted Reactor Condenser 55-328 Pressure Gauge Reactor Agitator 51-101 Seal Oil Return Pressure Gauge Reactor 45-742 Steam Stripping Line Pressure Gauge Reactor Condenser 55-329 Pressure Gauge
Deleted Reactor Agitator 51-102 Seal Oil Return Pressure Gauge Reactor 45-743 Steam Stripping Line Pressure Gauge Reactor Condenser 55-330 Pressure Gauge Deleted Reactor Agitator 51-103 Seal Oil Return Pressure Gauge Reactor 45-744 Steam Stripping Line Pressure Gauge Reactor Condenser 55-331 Pressure Gauge Deleted Reactor Agitator 51-104 Seal Oil Return Pressure Gauge Recovery Knockout Drum 45-760 Pressure Gauge Water Recirculation Pump 72-889 Discharge Pressure Gauge Deleted Recovered VCM Bleed Back Line Pressure Gauge Recovery Knockout Drum 45-761 Pressure Gauge Water Recirculation Pump 72-890 Discharge Pressure Gauge Deleted Recovery Vacuum Pump 72-901 Inlet Pressure Gauge
Recovery Compressors 72-904 or 72-905 Suction Pressure Gauge
Recovery Compressors 72-903, 72-904, and 72-905 Discharge Pressure Gauge
Seal Water Separator 45-762 Pressure Gauge Seal Water Separator 45-763 Pressure Gauge Seal Water Pump 72-891 Discharge Pressure Gauge Seal Water Filter 64-731 Outlet Pressure Gauge Seal Water Pump 72-892 Discharge Pressure Gauge Seal Water Filter 64-732 Outlet Pressure Gauge
DTH 000096825
c
L
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Pressure Gauges (Continued)
PG-760 PG-761
PG-762
PG-763 PG-764
PG-765 PG-766 PG-767 PG-768 PG-769 PG-770 PG-771 PG-772 PG-773 PG-774
PG-775
PG-776 PG-777 PG-778 PG-779 PG-780 PG-781 PG-782 PG-783 PG-784 PG-785 PG-786 PG-787 PG-788 PG-789 PG-790 PG-791
PG-792 PG-793 PG-794 PG-795 PG-796 PG-797
Recovered VCM Collect Tank 45-764 Pressure Gauge Recovered VCM Transfer Pumps 72-893 and 72-894
Discharge Pressure Gauge Recovery Knockout Drum 45-760 VCM Inlet Line Pressure
Gauge Hydroquinone Storage Tank 45-765 Pressure Gauge Hydroquinone Injection Pump 72-895 Discharge Pressure
Gauge Slurry Transfer Pump 72-896 Discharge Pressure Gauge Deleted Slurry Transfer Pump 72-897 Discharge Pressure Gauge Deleted Caustic Solution Pump 72-898 Discharge Pressure Gauge Caustic Solution Pump 72-899 Discharge Pressure Gauge Cleaning Solution Heater 55-339 Outletr Pressure Gauge Service Water Filter 64-724 Inlet Pressure Gauge Service Water Filter 64-724 Outlet Pressure Gauge Service Water Pumps 72-885 and 72-886 Discharge
Pressure Gauge Mechanical Seal Purge Water Pumps 72-887 and 72-888
Discharge Pressure Gauge AMS ShortStop Charge Pot 45-755 Outlet Pressure Gauge AMS ShortStop Charge Pot 45-756 Outlet Pressure Gauge AMS ShortStop Charge Pot 45-757 Outlet Pressure Gauge AMS ShortStop Charge Pot 45-758 Outlet Pressure Gauge Deleted Blowdown Tank Pump 72-900 Discharge Pressure Gauge Blowdown Tank 45-319 Pressure Gauge Seal Oil Return Header Pressure Gauge Seal Oil Pressure Unit 95-299 Pressure Gauge Seal Oil Pressure Unit 95-300 Pressure Gauge Seal Oil Supply Header Pressure Gauge Deleted Deleted Deleted Deleted Reactor Ejector Cyclone Separator 45-768 Outlet
Pressure Gauge Breathing Air Header Pressure Gauge Recovery Vacuum Pump 72-902 Suction Pressure Gauge Deleted Initiator Injection Pot 45-750 Pressure Gauge Seal Oil Return Filter 64-727 Outlet Pressure Gauge Seal Oil Return Filter 64-728 Outlet Pressure Gauge
000096826 DTH
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Pressure Gauges (Continued)
PG-798 PG-799 PG-800 PG-801 PG-802
PG-803
PG-804 PG-805 PG-806 PG-807 PG-808 PG-809
PG-810
PG-811
Emergency NO Short Stop Bottle PA-713 Pressure Gauge Emergency No Short Stop Bottle PA-714 Pressure Gauge Emergency NO Short Stop Bottle PA-715 Pressure Gauge Emergency NO Short Stop Bottle PA-716 Pressure Gauge VCM Charge Filter 64-718 and 64-742 Discharge
Pressure Gauge Recovered VCM Charge Filter 64-719 Discharge
Pressure Gauge Reactor 45-741 Resin Sampling System Pressure Gauge Reactor 45-742 Resin Sampling System Pressure Gauge Reactor 45-743 Resin Sampling System Pressure Gauge Reactor 45-744 Resin Sampling System Pressure Gauge Instrument Air Capacity Tank 45-301 Pressure Gauge Mechanical Seal Purge Water Surge Drum 45-759
Pressure Gauge High Pressure Service Water Header Pressure Gauge
(Downstream of PCi-817) Mechanical Seal Purge Water Header Pressure Gauge
(Downstream of PCi-818)
Pressure Instruments
PA-701 PCi-702 PSH-703 PCi-704
PI-705 PCi-706
PSL-707 PCi-708 PCi-709 PCi-710 PCi-711 PSL-712
PSL-713
PSL-714
PSL-715
PSL-716
PSL-717
Deleted Deleted Initiator Injection Pot 45-750 High Pressure Switch Recovered VCM Storage Tanks 89-520 and 45-317 Inert
Vent Back Pressure Regulator Reactor Evacuation Header Pressure Indicator Steam Stripping Header Steam Supply Back Pressure
Regulator Steam Stripping Header Low Pressure Switch Deleted Deleted Deleted Deleted
Reactor 45-741 Pressure Switch (Prevents dump before recovery)
Reactor 45-742 Pressure Switch (Prevents dump before recovery)
Reactor 45-743 Pressure Switch (Prevents dump before recovery)
Reactor 45-744 Pressure Switch (Prevents dump before recovery)
Reactor 45-741 Pressure Switch (Prevents charge before evacuation)
Reactor 45-742 Pressure Switch (Prevents charge before
evacuation)
DTH 000096827
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Pressure Instruments (Continued)
PSL-718
PSL-719
PR-720 PAH-720 PR-721 PAH-721 PR-722 PAH-722 PR-723 PAH-723 PI-724 PIC-725 PIC-726 PSL-727
PDS-728
PCi-729
PCi-730 PCI-731
PSL-732 PAL-732 PCi-733 PCi-734 PCi-735 PSL-737A and B PAL-737 PSL-738
PAL-738
PCi-739
PSL-740
PAL-740
PCI-741
PA-742
Reactor 45-743 Pressure Switch (Prevents charge before evacuation)
Reactor 45-744 Pressure Switch (Prevents charge before evacuation)
Reactor 45-741 Pressure Recorder Reactor 45-741 High Pressure Alarm Reactor 45-742 Pressure Recorder Reactor 45-742 High Pressure Alarm Reactor 45-743 Pressure Recorder Reactor 45-743 High Pressure Alarm Reactor 45-744 Pressure Recorder Reactor 45-744 High Pressure Alarm Reactor Recovery Pressure Indicator Recovery Knockout Drum 45-760 Inlet Pressure Controller VCM Bleed Stream to Recovery System Pressure Controller Recovery Compressors 72-903, 72-904, and 72-905 Suction
Low Pressure Switch Recovery Vacuum Pumps 72-901 and 72-902 Suction and Re
covery Compressors 72-903, 72-904, and 72-905 Discharge Differential Pressure Switch Hydroquinone Storage Tank 45-765 Nitrogen Pressure Regulator Deleted Mechanical Seal Purge Water Surge Drum 45-759 Nitrogen Supply Pressure Regulator High Pressure Service Water System Low Pressure Switch High Pressure Service Water System Low Pressure Alarm Deleted Deleted Deleted Mechanical Seal Water System Low Pressure Switches Mechanical Seal Water System Low Pressure Alarm Seal Oil Pressure Unit 95-299 Discharge Low Pressure Switch Seal Oil Pressure Unit 95-299 Discharge Low Pressure Alarm Seal Oil Pressure Unit 95-299 Nitrogen Supply Pressure Regulator Seal Oil Pressure Unit 95-300 Discharge Low Pressure Switch
Seal Oil Pressure Unit 95-300 Discharge Low Pressure Alarm
Seal Oil Pressure Unit 95-300 Nitrogen Supply Pressure Regulator
Deleted
X)TH 000096828
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Preaaure Instruments (Continued)
PCI-743
PC1-744
PCI-745
PCI-746
PCI-747
PCi-748 PC1-749 PAH-750 PAH-751 PCi-752 PAL-753 PCI-754 PCI-755 PCI-756 PCi-757 PSL-758 PIC-759 PAH-760 PI-760 PS-761 PSL-762 PAL-763
Breathing Air Station Supply Pressure Regulator (Reactors, Ground Level)
Breathing Air Station Supply Pressure Regulator (Reactors, Second Level)
Breathing Air Station Supply Pressure Regulator (Recovery Building, First Floor)
Breathing Air Station Supply Pressure Regulator (Recovery Building, Second Floor)
Breathing Air Station Supply Pressure Regulator (Charge Area)
Deleted Deleted Initiator Injection Pot 45-750 High Pressure Alarm Seal Oil Supply High Pressure Alarm Breathing Air Station Supply (Reactors, Third Level) Emergency NO Short Stop Bottles Low Pressure Alarm PA-713 NO Supply Pressure Regulator to Reactor 45-741 PA-714 NO Supply Pressure Regulator to Reactor 45-742 PA-715 NO Supply Pressure Regulator to Reactor 45-743 PA-716 NO Supply Pressure Regulator to Reactor 45-744 High Pressure Service Water Low Pressure Switch Blowdown Tank 45-319 Pressure Controller Blowdown Tank 45-319 High Pressure Alarm Blowdown Tank 45-319 Pressure Indicator Deleted
Blowdown Tank 45-319 Stripping Steam Low Pressure Switch Reactor Area Instrument Air Low Pressure Alarm
Rupture Discs
RD-701 RD-702 RD-703 RD-704 RD-705 RD-706 RD-707 RD-708 RD-709 RD-710 RD-711 RD-712 RD-713 RD-714
Reactor 45-741 Rupture Disc Reactor 45-742 Rupture Disc Reactor 45-743 Rupture Disc Reactor 45-744 Rupture Disc Reactor Condenser 55-328 Rupture Disc Reactor Condenser 55-329 Rupture Disc Reactor Condenser 55-330 Rupture Disc Reactor Cotiddhser 55-331 Rupture Disc Reactor 45-741 First of Double Rupture Discs Reactor 45-742 First of Double Rupture Discs Reactor 45-743 First of Double Rupture Discs Reactor 45-744 First of Double Rupture Discs Reactor 45-741 Second of Double Rupture Discs Reactor 45-742 Second of Double Rupture Discs
DTH 000096829
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Rupture Discs (Continued)
RD-715 RD-716 RD-717 RD-718 RD-719 RD-720 RD-721 RD-722 RD-723 RD-724 RD-725 RD-726 RD-727 RD-728 RD-729 RD-730 RD-731 RD-732 RD-733 RD-734 RD-735 RD-736 RD-737 RD-738 RD-739 RD-740 RD-741 RD-742 RD-743 RD-744 RD-745 to
RD-759 RD-760 RD-761 RD-762 RD-763 RD-764 RD-765 RD-766
RD-767
Reactor 45-743 Second of Double Rupture Discs Reactor 45-744 Second of Double Rupture Discs Fresh VCM Storage Tank 45-745 Rupture Disc Recovered VCM Storage Tank 89-520 Rupture Disc Recovered VCM Storage Tank 45-317 Rupture Disc Deleted Deleted Deleted Deleted Deleted Deleted Recovery Knockout Drum 45-760 Rupture Disc Recovery Knockout Drum 45-761 Rupture Disc Initiator Injection Pot 45-750 Rupture Disc Deleted Deleted Recovery Vacuum Pump 72-901 Inlet Rupture Disc Recovery Vacuum Pump 72-902 Inlet Rupture Disc Deleted Deleted Seal Water Separator 45-762 Rupture Disc Seal Water Separator 45-763 Rupture Disc Deleted Deleted Recovered VCM Condenser 55-337 VCM Outlet Rupture Disc Recovered VCM Condenser 55-338 VCM Outlet Rupture Disc Recovered VCM Collect Tank 45-764 Rupture Disc Deleted Deleted Blovdown Tank 45-319 Rupture Disc Deleted
Recovered VCM Collect Tank 45-764 Inlet Line Rupture Disc
Deleted Deleted Deleted Deleted Slurry Dump Line Rupture Disc Cleaning Solution Strainer 64-734 Inlet Piping Rupture
Disc Deleted
Safety-Relief Valves
SV-701 SV-702
SV-703
Reactor 45-741 Relief Valve Reactor 45-742 Relief Valve
Reactor 45-743 Relief Valve
000096830 I)TH
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Safety-Relief Valves (Continued)
SV-704 SV-705 SV-706 SV-707 SV-708 SV-709 SV-710 SV-711 SV-712 SV-713 SV-714 SV-715 SV-716 SV-717 SV-718 SV-719 SV-720
SV-721
SV-722 SV-723
SV-724 SV-725
SV-726 SV-727 SV-728 SV-729 SV-730 SV-731 SV-732 SV-733 SV-734 SV-735 SV-736 SV-737 SV-738 SV-739 SV-740 SV-741 SV-742 SV-743
Reactor 45-744 Relief Valve Reactor Condenser 55-328 Relief Valve Reactor Condenser 55-329 Relief Valve Reactor Condenser 55-330 Relief Valve Reactor Condenser 55-331 Relief Valve Reactor 45-741 Jacket Relief Valve Reactor 45-742 Jacket Relief Valve Reactor 45-743 Jacket Relief Valve Reactor 45-744 Jacket Relief Valve Hot Water Preheater 55-332 Relief Valve Deleted Deleted Deleted Fresh VCM Storage Tank 45-745 Relief Valve Recovered VCM Storage Tank 89-520 Relief Valve Recovered VCM Storage Tank 45-317 Relief Valve VCM Charge Pumps 72-875 and 72-876 Suction Piping
Relief Valve Recovered VCM Charge Pumps 72-877 and 72-878 Suction
Piping Relief Valve Recovered VCM Charge Filter 64-719 Relief Valve Recovered VCM Charge Pumps 72-877 and 72-878 Discharge
Piping Relief Valve VCM Charge Filter 64-718 Relief Valve VCM Charge Line Relief Valve (Down Stream of VCM Charge
Totalizers FQIC-701A and B) Recovery Knockout Drum 45-760 Relief Valve Recovery Knockout Drum 45-761 Relief Valve Deleted Water Recirculation Cooler 55-334 Relief Valve Deleted Recovery Vacuum Pump 72-901 Inlet Relief Valve Recovery Vacuum Pump 72-902 Inlet Relief Valve Hydroquinone Storage Tank 45-765 Relief Valve Hydroquinone Injection Pump 72-895 Discharge Relief Valve Seal Water Separator 45-762 Relief Valve Seal Water Separator 45-763 Relief Valve Seal Water Filter 64-731 Relief Valve Seal Water Filter 64-732 Relief Valve Recovered VCM Condenser 55-337 VCM Outlet Relief Valve Recovered VCM Condenser 55-338 VCM Outlet Relief Valve Recovered VCM Collect Tank 45-764 Relief Valve Cleaning Solution Heater (Tubes) 55-339 Relief Valve Mechanical Seal Purge Water Surge Drum 45-759
Relief Valve
DTH 000096831
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Safety-Relief Valves (Continued)
SV-744 SV-745
SV-746
SV-747
SV-748
SV-749
SV-750 SV-751 SV-752 SV-753 SV-754 SV-755 SV-756 SV-757 SV-758 SV-759 SV-760 SV-761
SV-762
SV-763 SV-764
SV-765 SV-766 SV-767 SV-768
Blowdown Tank 45-319 Relief Valve Breathing Air Station Supply Piping Relief Valve
(Reactors, Ground Level) Breathing Air Station Supply Piping Relief Valve
(Reactors, Ground Level) Breathing Air Station Supply Piping Relief Valve
(Recovery Building First Floor) Breathing Air Station Supply Piping Relief Valve
(Recovery Building Second Floor) Breathing Air Station Supply Piping Relief Valve
(Charge Area) AMS Short Stop Charge Pot 45-755 Relief Valve AMS Short Stop Charge Pot 45-756 Relief Valve AMS Short Stop Charge Pot 45-757 Relief Valve AMS Short Stop Charge Pot 45-758 Relief Valve Reactor 45-741 Steam Stripping Line Relief Valve Reactor 45-742 Steam Stripping Line Relief Valve Reactor 45-743 Steam Stripping Line Relief Valve Reactor 45-744 Steam Stripping Line Relief Valve Deleted Deleted Recovered VCM Collect Tank 45 764 Inlet Line Relief Valve Recovered VCM Transfer Pumps 72-893 and 72-894
Discharge Relief Valve Recovered VCM Storage Tanks 89-520 and 45-317 Inlet
Line Relief Valve
VCM Charge Pumps 72-875 and 72-876 Discharge Relief Valve Breathing Air Station Supply Piping Relief Valve
(Reactors, Third Level) Cleaning Solution Filter 64-734 Relief Valve Deleted VCM Charge Filter 64-742 Relief Valve Instrument Air Capacity Tank 45-301 Relief Valve
Temperature G
TG-701 TG-702 TG-703 TG-704 TG-705 TG-706 TG-707
TG-708
Hot Water Preheater 55-332 Outlet Temperature Gauge Recovered VCM Storage Tank 89-520 Tenperature Gauge Recovered VCM Storage Tank 45-317 Temperature Gauge Colloid Makeup Tank 45-751 Tenperature Gauge Colloid Storage Tank 45-752 Tenperature Gauge Colloid Charge Tank 45-753 Temperature Gauge Reactor Jacket 45-741 Cooling Water Return Temperature
Gauge
Reactor Condenser 55-328 Cooling Water Return Tempera ture Gauge
000096832
APPENDIX B INSTURMENT LIST - CONTINUED
Item No.
Service
Temperature Gauges (Continued)
TG-709
TG-710
TG-711
TG-712
TG-713
TG-714
TG-715
TG-716 TG-717
TG-718
TG-719
TG-720
TG-721 TG-722
TG-723
TG-724
TG-725
TG-726 TG-727
TG-728
TG-729 TG-730 TG-731 TG-732
TG-733
Reactor Jacket 45-742 Cooling Water Return Temperature Gauge
Reactor Condenser 55-329 Cooling Water Return Tempera ture Gauge
Reactor Jacket 45-743 Cooling Water Return Temperature Gauge
Reactor Condenser 55-330 Cooling Water Return Temperature Gauge
Reactor Jacket 45-744 Cooling Water Return Temperature Gauge
Reactor Condenser 55-331 Cooling Water Return Temperature Gauge
Water Recirculation Cooler 55-334 Outlet Temperature Gauge
Deleted
Water Recirculation Cooler 55-334 Cooling Water Return Temperature Gauge
Water Recirculation Cooler 55-334 Inlet Temperature Gauge
Seal Water Cooler 55-335 Cooling Water Return Temperature Gauge
Seal Water Separator 45-762 Seal Water Cutlet Temperature Gauge
Deleted Seal Water Cooler 55-336 Cooling Water Return
Temperature Gauge Seal Water Separator 45-763 Seal Water Outlet
Temperature Gauge Recovered VCM Condenser 55-337 Cooling Water
Return Temperature Gauge Recovered VCM Condenser 55-337 VCM Outlet
Temperature Gauge Deleted Recovered VCM Condenser 55-338 Cooling Water Return
Temperature Gauge Recovered VCM Condenser 55-338 VCM Outlet
Temperature Gauge Deleted
Cleaning Solution Tank 45-767 Temperature Gauge Seal Oil Return Temperature Gauge
Seal Oil Pressure Unit 95-299 Cooling Water Return Temperature Gauge
Seal Oil Pressure Unit 95-300 Cooling Water Return Tenq>erature Gauge
dTH 000096833
c APPENDIX B INSTRUMENT LIST - CONTINUED
Item No r
Service
Temperature Gauges (Continued)
TG-734 TG-735
TG-736 TG-737 TG-738 TG-739 TG-740
Seal Oil Supply Temperature Gauge Colloid Makeup Tank Jacket 45-751 Cooling Water
Return Temperature Gauge Fresh VCM Storage Tank 45-745 Temperature Gauge Process Water Temperature Gauge Hot Water Tank 45-748 Temperature Gauge Initiator Charge Pot 45-750 Temperature Gauge Blowdown Tank 45-319 Temperature Gauge
Temperature Instruments
TIC-701
Hot Water Tank 45-748 Temperature Controller
TIC-702
Hot Water Preheater 55-332 Discharge Temperature
Controller
TRC-703 '
Charge Water Temperature Controller
TR-704
Colloid Makeup Tank 45-751 Temperature Recorder
TSH-704
Colloid Makeup Tank 45-751 High Temperature Switch
TSL-704
Colloid Makeup Tank 45-751 Low Temperature Switch
c TI-705 TIRC-706
VCM Charge Temperature Indicator Reactor 45-741 Polymerization Temperature Controller
TAH-706
Reactor 45-741 High Temperature Alarm
TIRC-707
Reactor 45-742 Polymerization Temperature Controller
TAR-707
Reactor 45-742 High Temperature Alarm
TIRC-/08
Reactor 45-743 Polymerization Temperature Controller
TAH-708
Reactor 45-743 High Temperature Alarm
TIRC-709
Reactor 45-744 Polymerization Temperature Controller
TAH-709
Reactor 45-744 High Temperature Alarm
TIRC-710 TIRC-711
Reactor 45-741 Steam Stripping Temperature Controller Reactor 45-742 Steam Stripping Temperature Controller
TLRC-712
Reactor 45-743 Steam Stripping Temperature Controller
TlRC-713
Reactor 45-744 Steam Stripping Temperature Controller
TR-714
Reactor Multipoint Temperature Recorder (For all
Four Reactors)
TAH-715
Recovery Compressors 72-903, 72-904, and 72-905
Discharge High Temperature Alarm
TIC-716
Seal Water Cooler 55-335 Outlet Temperature
Controller
TIC-717
Seal Water Cooler 55-336 Outlet Temperature
Controller
TIC-718
Cleaning Solution Heater 55-339 Outlet Temperature
Controller
TAH-719 *
Seal Oil Pressure Units 95-299 or 95-300 Discharge
High Temperature Alarm
TAH-720
Initiator Injection Pot 45-750 High Temperature Alarm
TV-721
Cleaning Solution Heater 55-339 Steam Inlet Thermowell
TV-722
Cleaning Solution Heater 55-339 Solution Inlet Thermowell
DTH 000096834
t
APPENDIX B
J
INSTRUMENT LIST - CONTINUED
Item No.
Service
Temperature Instruments (Continued)
TW-723 TW-724
TW-725
TR-726 TW-727
TW-728 TW-729
TIC-730 TW-731 TW-732 TW-733 TW-734
Deleted Cleaning Solution Heater 55-339 Solution Outlet
Thermowell
VCM Charge Filters 64-718 and 64-742 Outlet Piping Thermowell
Recovery System Multipoint Temperature Recorder Water Recirculation Cooler 55-334 Cooling Water
Supply Thermowell
Seal Water Cooler 55-335 Cooling Water Supply Thermowell Recovered VCM Condenser 55-337 Cooling Water
Supply Thermowell
Blowdown Tank 45-319 Temperature Controller Reactor 45-741 Cooling Water Return Thermowell Reactor 45-742 Cooling Water Return Thermowell Reactor 45-743 Cooling Water Return Thermowell Reactor 45-744 Cooling Water Return Thermowell
c Amperage Instruments
11-200 IR-200 IAH-200 IAL-200
Reactor Agitator 51-110 Motor Amperage Indicator Reactor Agitator 51-110 Motor Amperage Recorder
Reactor Agitator 51-110 Motor Amperage High Alarm Reactor Agitator 51-110 Motor Amerpage Low Alarm
V DTH 000096835
Item No.
Control Valves
CV-200 CV-201 CV-202 CV-203 CV-204 CV-205 CV-206 CV-207 CV-208 CV-209 CV-210 CV-211 CV-213 CV-214 CV-215 CV-216 CV-217 CV-218 CV-219 CV-220 CV-221 CV-222 CV-223 CV-224 CV-225 CV-226 CV-227 CV-228 CV-891 CV-892
CV-893
CV-894 CV-895
CV-896
CV-897
Flow Instruments
FQIC- 701A and B FSL-701A and B
APPENDIX B INSTRUMENT LIST - CONTINUED
Service
Reactor 45-781 Main Dump Valve Reactor 45-781 VCM Charge Valve Reactor 45-781 Slurry Dump Valve Reactor 45-781 Chem Wash Return Valve Reactor 45-781 Hot Water Charge Valve Reactor 45-781 Sewer drain Valve Reactor 45-781 Steam Stripping Valve Reactor 45-781 Steam Stripping Valve Reactor 45-781 Colloid Charge Valve Reactor 45-781 Initiator Charge Valve Reactor 45-781 Resin Sampling Valve Reactor Jacket Educator EE-201 Steam Valve Reactor 45-781 Chem Wash Supply Valve Reactor 45-781 Rinse Supply Valve Reactor Condenser 55-358 Cleaning and Rinse Valve Reactor 45-781 Cleaning and Rinse Valve Reactor 45-781 Evacuation Valve Reactor 45-781 Recovery Valve Reactor 45-781 Recovery and Evacuation Valve Reactor Condenser 55-358 Inert Vent Valve Reactor 45-781 Vent Valve Evacuation Ejector First Stage Steam Valve Evacuation Ejector. Second.-Stage Steam Valve Evacuation Header Valve to EE-200 Reactor 45-781 VCM Charge Valve Evacuation Header Valve to EE-705 Reactor 45-781 AMS Emergency Kill Valve Reactor 45-781 AMS Emergency Kill Valve Steam Valve for Blowdown Tank 45-319 Pressure Regulation Water Drain Valve from Recovered VCM Storage Tank 89-520
to the Blowdown Tank 45-319 Water Drain Valve from Recovered VCM Storage Tank 45-317
to the Blowdown Tank 45-319 VCM Recovery Valve for Blowdown Tank 45-319 VCM Recovery Valve for VCM Storage Tank 45-745, 89-520,
and 45-317 Instrument Air Supply Valve to Reactors 45-741, 45-742,
45-743, 45-744, and 45-781 Hot Water Rinse Header Valve to Reactors 45-741, 45-742,
45-743, 45-744, and 45-781
VCM Charge Totalizers VCM Charge Low Flow Switches
DTH 000096836
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No. Flow Instruments (Cont.)
Service
FAL-701 FQIC-702 FQIC-704 FQIC-705 FQIC-706 FI-707 FR-708 FQI-708 FIC-708 FIRC-710 FIRC-711 FIRC-7I2 FIRC-713 FI-714
FAL-714 FI-715
FAL-715 FI-716
FAL-716 FI-717
FAL-717 FI-718
FQI-203
FIRC-201 FI-200 FI-202 FI-205
OF-206 RO-207
VCM Charge Low Flow Alarm Recovered VCM Charge Totalizer Hot Water Charge Totalizer Colloid Charge Totalizer Colloid Makeup Tank 45-751 Makeup Water Flow Totalizer Deleted Reactor Steam Stripping Flow Recorder Reactors Steam Stripping Flow Totalizer Reactor Steam Stripping Flow Controller Reactor 45-741 Cooling Water Flow Controller Reactor 45-742 Cooling Water Flow Controller Reactor 45-743 Cooling Water Flow Controller Reactor 45-744 Cooling Water Flow Controller Reactor Agitator 51-101 Inboard Seal Water Flush
Rotameter Reactor Agitator 51-101 Seal Water Low Flow Alarm Reactor Agitator 51-102 Inboard Seal Water Flush
Rotameter Reactor Agitator 51-101 Seal Water Low Flow Alarm Reactor Agitator 51-103 Inboard Seal Water Flush
Rotameter Reactor Agitator 51-103 Seal Water Low Flow Alarm Reactor Agitator 51-104 Inboard Seal Water Flush
Rotameter Reactor Agitator 51-104 Seal Water Low Flow Alarm Reactor 45-741 Spray Nozzle Flush Rotameter
Reactor 45-781 Initiator Injection Pot 45-778 Flow Totalizer
Reactor 45-781 Cooling Water Flow Controller Reactor Agitator 51-110 Lip Seal Flush Rotameter Reactor 45-781 Spray Nozzle Flush Rotameter Reactor Agitator 51-110 Mechanical Seal Oil Supply
Rotameter Reactor Condenser 55-358 Cooling Water Supply Orifice Reactor 45-781 Inert Vent Restriction Orifice
00009683^ DTH
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Flow Instruments (Continued)
FI-719 FI-720 FI-721 FI-722 -FI-723 FI-724 FI-725 FI-726
FI-727
FI-728
FI-729 FI-730
FI-731
FI-732
FI-733 FI-734
FI-735 FI-736
FI-737 FIC-738
FIC-739
FIG-740 FI-741
FI-742
FIC-743 FI-744 FI-745 FI-746 FI-747 FI-748 FCi-749
Reactor 45-742 Spray Nozzle Flush Rotameter Reactor 45-743 Spray Nozzle Flush Rotameter Reactor 45-744 Spray Nozzle Flush Rotameter Deleted Deleted Deleted Deleted Recovery Knockout Drum Level Controller LC-716
Water Flush Rotameter Recovery Knockout Drum Level Controller LC-718
Water Flush Rotameter Recovery Vacuum Pump 72-901 Double Mechanical Seal
Water Rotameter Recovery Vacuum Pump 72-901 Inboard Flush Water Rotameter Recovery Vacuum Pump 72-902 Double Mechanical Seal
Water Rotameter Recovery Vacuum Pump 72-902 Inboard Flush Water
Rotameter Rocovery Compressor 72-903 Double Mechanical Seal
Water Rotameter Deleted Recovery Compressor 72-904 Double Mechanical Seal
Water Rotameter Deleted
Recovery Compressor 72-905 Double Mechanical Seal Water Rotameter
Deleted Recovery Vacuum Pump 72-901 and Recovery Compressor
72-903 Seal Water Flow Controller Recovery Vacuum Pump 72-902 and Recovery Compressor
72-904 Seal Water Flow Controller Recovery Compressor 72-905 Seal Water Flow Controller Seal Water Separator Level Controller LC-720
Flush Water Rotameter Seal Water Separator Level Controller LC-722
Flush Water Rotameter Deleted
Recovered VCM to Recovery Knockout Drum 45-760 Bullseye Deleted Deleted
Slurry Dump to Slurry Strainer FD-717 Bullseye Deleted Reactor Agitator 51-101 Mechanical Seal Oil Supply
Flow Regulator
6638 009
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Flow Instruments (Continued)
FCi-750
FCi-751
FCi-752
FI-753
FI-754
FI-755
FI-756
FQI-757 RO-758 OF-759 OF-760 OF-761 OF-762 FI-763
FI-764
FI-765 FI-766 FI-767
FI-768
FI-769
FI-770
RO-771
RO-772
RO-773
RO-774
Reactor Agitator 51-102 Mechanical Seal Oil Supply Flow Regulator
Reactor Agitator 51-103 Mechanical Seal Oil Supply Flow Regulator
Reactor Agitator 51-104 Mechanical Seal Oil Supply Flow Regulator
Reactor Agitator 51-101 Mechanical Seal Oil Supply Rotameter
Reactor Agitator 51-102 Mechanical Seal Oil Supply Rotameter
Reactor Agitator 51-103 Mechanical Seal Oil Supply Rotameter
Reactor Agitator 51-104 Mechanical Seal Oil Supply Rotameter
Hot Water Charge Totalizer Colloid Makeup Water Supply Restriction Orifice Reactor 45-741 Cooling Water System Orifice Flanges Reactor 45-742 Cooling Water System Orifice Flanges Reactor 45-743 Cooling Water System Orifice Flanges Reactor 45-744 Cooling Water System Orifice Flanges Slurry Transfer Pump 72-896 Inboard Seal Flush Water
Rotameter Slurry Transfer Pump 72-897 Inboard Seal Flush Water
Rotameter Deleted Deleted VCM Charge Punqp 72-875 Double Mechanical Seal Water
Rotameter VCM Charge Pump 72-876 Double Mechanical Seal Water
Rotameter Recovered VCM Charge Pump 72-877 Double Mechanical
Seal Rotameter Recovered VCM Charge Pump 72-878 Double Mechanical
Seal Rotameter VCM Charge Pump 72-875 Double Mechanical Seal Water
Back Pressure Restriction Orifice VCM Charge Pump 72-876 Double Mechanical Seal Water
Back Pressure Restriction Orifice Recovered VCM Charge Punp 72-877 Mechanical Seal
Water Back Pressure Restriction Orifice Recovered VCM Charge Pump 72-878 Mechanical Seal
Water Back Pressure Restriction Orifice
DTH 000096839
APPENDIX B
INSTRUMENT LIST - CONTINUED
Item No.
Service
Flow Instruments (Continued)
FI-775 FI-776 FI-777 FI-778 FI-779 RO-780 RO-781 RO-782 RO-783 RO-784 RO-785 RO-786 FI-787 FI-788 FI-789
Water Recirculation Pump 72-889 Inboard Seal Flush Water Rotameter
Deleted Water Recirculation Pump 72-890 Inboard Seal Flush
Water Rotameter
Seal Water Pump 72-891 Inboard Seal Flush Water Rotameter
Seal Water Pump 72-892 Inboard Seal Flush Water Rotameter
Recovery Vacuum Pump 72-901 Double Mechanical Seal Water Back Pressure Restriction Orifice
Recovery Vacuum Pump 72-902 Double Mechanical Seal Water Back Pressure Restriction Orifice
Recovery Compressor 72-903 Double Mechanical Seal Water Back Pressure Restriction Orifice
Recovery Compressor 72-904 Double Mechanical Seal Water Back Pressure Restriction Orifice
Recovery Compressor 72-905 Double Mechanical Seal Water Back Pressure Restriction Orifice
Recovered VCM Transfer Pump 72-893 Mechanical Seal Water Back Pressure Restriction Orifice
Recovered VCM Transfer Pump 72-894 Mechanical Seal Wster Back Pressure Restriction Orifice
Recovered VCM Transfer Pump 72-893 Mechanical Seal Water Rotameter
Recovered VCM Transfer Pump 72-894 Mechanical Seal Water Rotameter
Recovery Vacuum Pump 72-901 Inboard Flush Water Rotameter
FI-790
FI-791
FI-792
FI-793 FI-794
FI-795 FI-796
FI-797 FI-798
Recovery Vacuum Pump 72-901 Double Mechanical Seal Water Rotameter
Recovery Vacuum Pump 72-902 Inboard Flush Water Rotameter
Recovery Vacuum Pump 72-902 Double Mechanical Seal Water Rotameter
Deleted Recovery Compressor 72-903 Double Mechanical Seal
Water Rotameter Deleted Recovery Compressor 72-904 Double Mechanical Seal
Water Rotameter Deleted Recovery Compressor 72-905 Double Mechanical Seal
Water Rotameter
DTH 0096840
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Flov Instruments (Continued)
RO-799
RO-800
RO-801
RO-802
RO-803
FI-804 FI-805 FI-806 FI-807 FI-808 FI-809 FI-810 FQI-811 RO-812 RO-813 FI-814
FI-815
RO-816
Recovery Vacuum Pump 72-901 Double Mechanical Seal
Water Back Pressure Restriction Orifice
Recovery Vacuum Pump 72-902 Double Mechanical Seal
Water Back Pressure Restriction Orifice
Recovery Compressor 72-903 Double Mechanical Seal
Water Back Pressure Restriction Orifice
Recovery Compressor 72-904 Double Mechanical Seal
Water Back Pressure Restriction Orifice
Recovery Compressor 72-905 Double Mechanical Seal
Water Back Pressure Restriction Orifice
AMS Short Stop Charge Pot 45-755 Water Flush Rotameter
AMS Short Stop Charge Pot 45-756 Water Flush Rotameter
AMS Short Stop Charge Pot 45-757 Water Flush Rotameter
AMS Short Stop Charge Pot 45-758 Water Flush Rotameter
Blowdown Tank 45-319 Level Cage Water Flush Rotameter
Recovered VCM Sampling System Bullseye
Recovered VCM Sampling System Bullseye
Steam to Reactor Module Flow Totalizer
Deleted
*
Deleted
Blowdown Tank Pump 72-900 Double Mechanical Seal Water
Rotameter
Blowdown Tank Pump 72-900 Inboard Seal Water Flush
Rotameter
Blowdown Tank Pump 72-900 Double Mechanical Seal Water
Back Pressure Restriction Orifice
Level Gauges
LG-701A, B, C, and D
LG-702A, B, C and D
LG-703A, B, C and D
LG-704A, B, C and D
LG-705
LG-706A, B, andiC
LG-707A, B and C
LG-708 LG-709
LG-710
Fresh VCM Storage Tank 45-745 Level Gauge
Recovered VCM Storage Tank 89-520 Level Gauge
Recovered VCM Storage Tank 45-317 Level Gauge
Hot Water Tank 45-748 Level Gauge
Deleted Colloid Storage Tank 45-752 Level Gauge
Colloid Charge Tank 45-753 Level Gauge
Recovery Knockout Drum 45-760 Level Gauge Recovery Knockout Drum 45-761 Level Gauge Hydroquinone Storage Tank 45-765 Level Gauge
DTH 000096841
APPENDIX B INSTRUMENT LIST - CONTINUED
Item No.
Service
Level Gauges (Continued)
LG-711 LG-712 LG-713 LG-714 LG-715 LG-716 LG-717
Seal Water Separator 45-762 Level Gauge Seal Water Separator 45-763 Level Gauge Recovered VCM Collect Tank 45-764 Level Gauge Seal Oil Storage Drum 45-754 Level Gauge Deleted Blowdown Tank 45-319 Level Gauge Mechanical Seal Purge Water Surge Drum 45-759
Level Gauge
Level Instruments
LI-701 LAH-701 LS-701A, B,
C and D LA-702 LA-703 LI-704 LA-705 LA-706 LI-707 LA-708 LA-709 LAH-710 LI-711 LS-711A LA-711B, C,
and D LA-712
LAH-713 LAH-714 LSL-715 LSH-716 LSL-717 LSH-718 LSL-719 LC-720 LAH-720 LAL-720 LA-721 LC-722 LAH-722 LAL-722 LA-723 LC-724 LIC-725 LAH-725
Fresh VCM Storage Tank 45-745 Level Indicator Fresh VCM Storage Tank 45-745 High Level Alarm Fresh VCM Storage Tank 45-745 Level Switches
Deleted Deleted Recovered VCM Storage Tank 89-520 Level Indicator Deleted Deleted Recovered VCM Storage Tank 45-317 Level Indicator Deleted Deleted Colloid Makeup Tank 45-751 High Level Alarm Hot Water Tank 45-748 Level Indicator Deleted Hot Water Tank 45-748 Level Switches
Deleted Colloid Storage Tank 45-752 High Level Alarm Colloid Charge Tank 45-753 High Level Alarm Colloid Charge Tank 45-753 Low Level Switch Recovery Knockout Drum 45-760 High Level Switch Recovery Knockout Drum 45-760 Low Level Switch Recovery Knockout Drum 45-761 High Level Switch Recovery Knockout Drum 45-761 Low Level Switch Seal Water Separator 45-762 Level Controller Seal Water Separator 45-762 High Level Alarm Seal Water Separator 45-762 Low Level Alarm Deleted Seal Water Separator 45-763 Level Controller Seal Water Separator 45-763 High Level Alarm Seal Water Separator 45-763 Low Level Alarm Deleted Recovered VCM Collect Tank 45-764 Level Controller Slurry Dump Tank 45-766 Level Controller
Slurry Dump Tank 45-766 High Level Alarm
Item No.
Temperature Gauges
TG-201 TG-202
APPENDIX B INSTRUMENT LIST - CONTINUED
Service Reactor 45-781 Jacket Cooling Water Return Temperature Reactor Condenser 55-358 Cooling Water Return Tempera
ture
Temperature Instruments
TIRC-201 TAH-201 A B TRC-202 TR-203 TW-205
Reactor 45-781 Polymerization Temperature Controller Reactor 45-781 High Temperature Alarms Reactor 45-781 Steam Stripping Temperature Controller Reactor Condenser 55-358 Temperature Recorder Reactor 45-781 Cooling Water Return Thermowell
DTH 000096843
Item No.
Pressure Gauges
PG-200 PG-202 PG-205 PG-206 PG-212 PG-213 PG-222
Pressure Instruments
PS-205
PAH-206 A 8 B PR-206 PT-206 PI-211 PS-212 PCV-216 PCi-
Rupture Disc
RD-200 RD-201 RD-204 RD-206 RD-207 RD-208 RD-209 RD-210 RD-211
Safety-Relief Valves
PSV-200 PSV-201 PSV-202 PSV-203 PSV-206 PSV-207 PSV-208 PSV-209
PSV-211 PSV-212 PSV-213
APPENDIX B
INSTRUMENT LIST - CONTINUED
Service
Reactor 45-781 Pressure Gauge Initiator Charge Pot 45-784 Pressure Gauge Reactor Condenser 55-358 Pressure Gauge Reactor 45-781 Steam Stripping Pressure Gauge Reactor 45-781 VCM Charge Pressure Gauge Reactor 45-781 Nitric Oxide Pressure Gauge Steam Tracina Manifold Pressure Gauge
Reactor 45-781 Pressure Switch (Prevents dump before recovery)
Reactor 45-781 High Pressure Alarm Reactor 45-781 Pressure Recorder Reactor 45-781 Pressure Transmitter Reactor 45-781 Pressure Indicator (Manometer) Initiator Charge Pot Pressure Switch Steam Tracing Pressure Reducing Valve AMS Emergency Kill System Nitrogen Pressure Regulator
Reactor 45-781 Rupture Disc Reactor Condenser 55-358 Rupture Disc Initiator Charge Pot 45-778 Rupture Disc Reactor 45-781 Rupture Disc Reactor 45-781 Rupture Disc Reactor 45-781 Rupture Disc Reactor 45-781 Rupture Disc AMS Emergency Kill Pot 45-786 Rupture Disc Reactor Condenser 55-358 Rupture Disc
Reactor 45-781 Relief Valve Reactor Condenser 55-358 Relief Valve AMS Emergency Kill Pot 45-786 Relief Valve Reactor 45-781 VCM Charge Header Relief Valve Reactor 45-781 Relief Valve Reactor 45-781 Relief Valve Reactor 45-781 Relief Valve Reactor 45-781 Relief Valve
Reactor Condenser 55-358 Shell Relief Valve Reactor 45-781 Jacket Relief Valve Reactord Condenser 55-358 Relief Valve
DTH 000096844