Document Gm7wxOzp3mwo3ddkvzBXEd7Qn

PLANT MANAGER'S SAFETY BOARD MINUTES OF MEETING July 18, 1984 Present were: E. P. Bailey G. W. Bostick G. W. Daues for S. G. Pappas R. A. Forsthoffer R. T. Hammann R. L. Hammond B. C. Lancaster D. W. Metten G. T. Ryan J. A. Stal - Guest J. G. Trafton G. L. Tromblee G. L. Wofford I. REVIEW OF STATISTICS - R. T. Hammann A. Texas City Plant Safety Performance Summary - June (A) INJURIES WITHOUT LOST WORKDAYS (medical treatment only) (B) LOST WORKDAYS CASES RESTRICTED ACTIVITY DAYS AWAY FROM WORK CASES (C) FATALITIES TOTAL RECORDABLE CASES 1983 JURE----- TTD 24 Q0 00 00 00 24 1984 JURE----- TTD 01 0Q 00 00 00 01 1984 TARGETS 7 1 -- -- 8 INJURY RATES PER 200,000 MANHOURS 1983 1984 JUNE-TTD JUNE YTD 1984 TARGETS 1984 MFIC ------- MAT TARGET YTD TOTAL INJURY-TIR TOTAL RECORDABLE-TRR TOTAL LOST WORKDAY-TLWR DAYS-AWAY-FROM-WORK-DAWR 13.92 10.94 1.64 0.55 0.00 0.00 0.00 0.00 9.32 0.00 0.00 0.00 9.72 0.15 0.00 0.00 0.67 0.08 __M 0.95 ----- ------ 0.88 0.25 0.19 B. Comments on Statistics - R. T. Hammann We are continuing to have an excellent record with no recordable injuries in June and none so far in July. SC 13793 STG 2430599 LAM015542 ( i- PMSB Meeting Minutes - July 18, 1984 Page 2 Areas having a high or increasing cumulative monthly injury rate are: Pumper/Gaugers Pipefitters Dept. 48/56 Areas showing good or improving injury rates are: Dept. 44/45/46 Stores Areas having excellent safety records are: Painters Insulators Dept. 513 - 7 months without an injury - 11 months without an injury - 22 months without an injury II. NON-MONSANTO SAFETY - B. C.Lancaster A. Contractor Safety There were no recordable injuries in June. The total recordable injury rate so far this year is considerably improved from 1983 (3.1 vs. 5.3). B. CEP Safety The recordable injury rate is extremely high due to the fact that only 2,000 hours were worked and there was a recordable injury in June to an employee of Continental Slip Form Builders. III. REPORT OF THE SAFETY ADVISORY COMMITTEE (SAC) - G. T. Ryan A. The revised emergency control center operations were reviewed. After the PMSB meeting, a walk-through was held in the emergency control center to discuss procedures and duties of various personnel. IV. REPORT OF THE PLANT SAFETY AND HOUSEKEEPING ACTION COMMITTEE (SHAC) E. P. Bailey A. Annual Safety and Housekeeping Inspection The inspection is scheduled for September 19-21, 1984, with a feed back session scheduled for Monday, September 24. Ray Forsthoffer and Joe Stal reviewed details of the inspection planning. The theme for the inspection will be "Safety Through Employee Involvement". No overall plant rating will be given but outstanding groups and areas will be highlighted. SC 13794 STG 2430600 LAM015543 PMSB Meeting Minutes - July 18, 1984 Page 3. B. 3rd Quarter Safety and Housekeeping Inspection This is scheduled to be conducted the week of August 6. It will be aimed at preparing the plant for the Annual Safety and Housekeeping Inspection. C. Contractors Safety Program The new procedure is being printed and should be issued soon. Purchasing is modifying their documents to fit this new procedure. A short safety film is also being prepared to orient truck drivers and other personnel entering the plant on business. V. REVIEW OF INCIDENTS Monsanto Incidents: Date Incident No. Description There were no Monsanto incidents. Contractor Incidents: Date Incident No. Description There were no contractor incidents. VI. PLANT MANAGER'S COMMENTS - G. L. Tromblee There are a couple of items for which information should be obtained for the next PMSB meeting: A. Status of recommendations from the incident concerning contamination of the plant air system, Report No. 84-4. B. Talk with plant personnel concerning their ideas on why we have an excellent safety record. /dgb SC 13795 R. T. Hammann STG 2430601 LAM015544