Document GKpGNg1J2j12bjNjO0MnRenRv
FILE NAME Painters and Allied Trades PAINT
DATE 2006 July
DOC PAINT106
DOCUMENT DESCRIPTION UK Government Report on Chrysotile in Textured Coatings
Harpur Hill Buxton Derbyshire SK17 9JN T +44 1298 218000 F +44 1298 218590 W www.hsl.gov.uk
.
HEALTH & SAFETY
LABORATORY
Summary report on additional work carried out
on the monitoring of chrysotile containing textured decorative coatings
2006 .
Project Leader Garry Burdett
Author Garry Burdett and Graham Revell Science Group Science Group 5
Ms. R. Russell Dr K.Walkin K.Walkin Mr. T. Johnson Dr. M.J. Gibson Mrs. S Peace Mr. D. Dean Mr. R. Cooper
Dr. N. West
Mr. B. Tylee HSL Library
IF Section
DISTRIBUTION
HSE DR4 Customer Project Officer
:
HSE DR4 Customer Authorising Officer
HSE BHAW7 HSE SSGOCC
HSE FOD Nottingham
HSE FOD Leeds HSE FOD Sheffield
HSL Operations Director HSL IFS
HSL HSL
PRIVACY MARKING
Available to the public
HSL report approval
Date of issue Job number -
Registry file
Electronic file name
B.Tylee February 2006
JS20004675 024691 TDC 2 FINALREPORT
'Crown copyright 2006
ACKNOWLEDGEMENTS We would like to acknowledge the help of the asbestos licensing principle inspectors and their
support staff and colleagues at HSE's area offices at Leeds Sheffield Nottingham and Manchester who made the site selection possible We are also indebted to the site owners main contractors and asbestos removal contractors at the sites visited and in particular the help we received from the asbestos removal operatives We would also like to thank the asbestos removal contractors association for their helpful comments and recognise the efforts made by Mr Richard Houlihan and Alison Clarke of the Inorganics and Fibres section and Mr Peter Baldwin of the FSSU of HSL for their part in the collection and analysis of the samples which made this report possible
iii
CONTENTS
1 1.1 1.2
INTRODUCTION ......... 1
Background ...
ee
ceeccsssseseescsececsecscscsusassssassceesaesassusatsuvacsesacsavsceesenees
1
Objectives of the work .......cccccccsscscssssescssssssstsssceseasessessssstacsesatsecsseseesens 3
2 2.1 2.2
SITE SELECTION AND STRATEGY 555 Site selection and arrangements ..... 555 Site selection and sampling Biases 0.00... seccescccccsccesscssecesssceceececeeceseees 555
3 3.1 3.2 3.3 3.4
SAMPLING AND ANALYSIS METHOD AND ISSUES ......... 6
Sampling method ........... 6
Analytical
method
.....
cccccsccccssscsscscessessecsssceacsesecscsassessssssavscereecueceesess
6
PCM Sampling and analysis .......... 7
Determination of the Asbestos concentration 9 ......0...ccccccccccsccsessssesececcecesee
4
RESULTS AND DISCUSSION .......ssssscssssssssssscssssccaseceatsecsrsnsecsueessauesenees 10
4.1
The airborne releases from the removal of TDC from a wider range of
surfaces
....
ecsssccsscsseecseseesesssssecsesesevscscssseveesevsevssausaussessausesaesssassuvssessecterseseses
10
4.2 change in the personal airborne asbestos fibre concentrations inside the
enclosed area if no air extraction is used to keep a reduced pressure inside the
enclosure
eee ccs seseesseceseessSdececesecuucecsseeseuueceucceccecessueusaesesasesees .... 13
4.3
effectiveness of site clearance based on a visual assessment alone 14
4.4 4.5 used
The likely airborne releases from poorly controlled removal 16
The airborne concentration outside the enclosure if no air extraction is 18
4.6 the
the airborne
building .....
exposures that will be experienced by persons reoccupying
cee
ccccsesssscseeesscsevecasseseesavassacseessesuessssssaseesanentectecesceccce
19
ASSESSMENT .. 5 IMPLICATIONS FOR RISK
sesssanenenneneas 20
5.1
The airborne releases from the removal of TDCs 20
5.2 Theoretical Maximum Number of person exposed at the High estimate of
the exposure concentration 0.0...
cc
cceccssscscseessecsesesesesesessssesssevsserseseveveceececeesce.
20
5.3
validity of the average exposure for risk assessment ..........000-0000000000-... 20
5.4
Measured concentrations from the additional sites 21
6 APPENDICESseetsuessssansseers 22
6.1
Proposed Project to monitor personal fibre concentrations of workers
involved in the removal and renovation of textured decorative coatings PHASE
2
22
6.2
Response from ARCA .........cceccccecccsesssesscstsscsesceutsseeseseesseeececcescesecceccccee. 25
7 REFERENCES ........... 27 sessssssereessssssesacsrcasseserassererssveususersusecsesassessssecseeses
iv
EXECUTIVE SUMMARY
Objectives
The objectives of the research were to carry out further site monitoring to determine
1. Airborne fibre concentrations releases during the removal of textured decorative coatings TDCs from a wider range of surfaces to those reported in an earlier survey see IF2005
2. Change in the personal airborne asbestos fibre concentrations inside the enclosed area during the removal of TDCs if no air extraction is used to keep a reduced pressure inside the enclosure and
3. Effectiveness of the clearance following removal of TDCs based on a visual assessment
alone
In addition as the work progressed sampling was also carried out to address three additional questions raised by the Asbestos Removal Contractors Association ARCA
4. What are the likely airborne releases from poorly controlled removal of TDCs
5. What is the airborne concentration outside the enclosure during removal of TDCs if no air
extraction is used
6. What are the airborne exposures that will be experienced by persons reoccupying a building following the removal of TDCs
Method
Notifications for licensed removal of TDCs from four Health and Safety Executive HSE
regional offices were used to select sites where TDCs were being scraped or removed from
resistant surfaces The asbestos removal contractors at the candidate sites were contacted by staff from the Health and Safety Laboratories HSL and the proposed sampling work discussed If agreement for sampling was given HSL then arranged for the appropriate waivers and
contacted the main contractor and owners
HSL sampling personnel in liaison with the contractors attend sites during the removal to sample the following
personal
.
* personal fibre concentrations of operatives during peak removal and cleaning activities
cleaning ' personal gravimetric dust exposure of operatives during peak removal and activities
static fibre concentration in the airlock during removal and e static fibre concentration inside the enclosure during disturbance sampling of dust and
debris
The high airborne dust concentrations encountered meant that the collection filters would become overloaded and unusable for microscopy analysis if personal samples of 240 litres of air over a hour period were collected as required for compliance monitoring In most cases it
V
was only possible to sample for some 10 - 30 minutes at flow rates of the filters became too overloaded for microscopy analysis
/l1itre per minute before
The filters collected during the site sampling were analysed by HSL using UKAS accredited procedures for fibre counting and analysis Fibre count analysis was carried out on a portion of the filter using light microscopy at X500 magnification with phase contrast optics PCM to count the number of visible fibres particles that were > ...mlong < 3...mwide and had a length breadth ratio >
Variable amounts of calcium sulphate fibres can be released from the TDC and from underlying plasterboard or plaster These fibres cannot be distinguished from asbestos fibres when samples
are counted by using a light microscope The number of calcium sulphate fibres which are
released may be many times greater than the number of asbestos fibres released To remove this
interference part of the filters were water wicked to dissolve the calcium sulphate fibres
Only PCM counts on wicked samples have been included in this summary of the site sampling data Similarly only results using the World Health Organisation WHO counting rules have been used in this summary report unless it is expressly stated otherwise Although the PCM concentration of soluble fibres will not give a direct measure of the asbestos fibres as other asbestos fibres will still remain it gives an initial upper estimate of what the
asbestos fibre concentration could be
A limited number of samples were also analysed by analytical transmission electron microscopy TEM which uses electron diffraction and energy dispersive ray analysis to identify individual fibres to determine whether they are asbestos or asbestos Fibres of a size which would have been visible and met the PCM counting criteria fibres 5 ...mlong > 0.23 0.23 0.23 ...m wide and with an aspect ratio > were analysed This allowed PCM equivalent PCME
airborne asbestos fibre concentrations to be calculated as detailed in the International Standards
Organisation method ISO 10312 for asbestos in ambient air
Total and respirable dust concentrations were determined in accordance with MDHS14 by weighing filters from inhalable and cyclone personal samplers which were collected in addition to the asbestos samples
As it was only possible to sample small volumes of air to avoid overloading the filters this meant that fewer fibres were counted which reduced the precision of the result and few individual samples exceeded the limit of quantification LOQ
Results and Main Findings
Airborne releases from the removal of TDCs from a wider range of surfaces
Five sites containing TDCs were monitored four of which textured decorative plaster and one that contained an asbestos
type present was chrysotile white asbestos The removal
substrates included
contained asbestos containing
containing paint The asbestos
methods and the underlying
e Hand scraping TDC from concrete one site and hard finishing plaster two sites e Removing plaster and TDC from brickwork with a hammer and chisel one site
vi
* Removing a chrysotile containing paint on pebbledash from brickwork with a Kango powered chisel
Demolition and removal of TDC and the under laying plasterboard using a hammer and
crowbar
.
The average individual personal PCM fibre exposures for the asbestos removal operatives at the five sites are summarised in table S1 The calculated limits of detection LOD and limit of
quantifications LOQ for the average volumes of air sampled are also shown The high concentrations of airborne dust release made sampling problematical and compromised the sensitivity of the analysis and only short peak concentrations are presented Although the average PCM fibre concentration was above 0.08 ml at three of the sites B Y the high concentrations of dust produced at these sites limited the sampled volumes so that at only one site D of these three sites exceeded the LOQ It is important to recognise that these averages include samples taken when there was no extraction from the enclosure and dry scraping with no dust suppression was taking place also at site Y power tools were used Note For PCM analysis LOD is defined in Annex 1 of HSG 248 as a count of 6.5 fibres in 200 fields of view
and the LOQ as a count of 20 fibres in 200 fields of view based on background counts on blank filter samples and statistical confidence limits
The gravimetric data showed that the average personal dust concentrations were nearly three times higher than the COSHH exposure limit at sites B and Y and at site D it was close to the
exposure limit The sites giving the higher PCM fibre concentrations were also the sites which had poor control of dust emissions and the high PCM counts were more to do with the low
volume of air sampled and the resultant LODs and LOQs than high fibre counts It was a surprise that site D gave significant PCM fibre concentrations as this type of site involving the careful removal of plasterboard with the TDC attached was monitored specifically because in the previous survey this removal method gave no detectable release of asbestos It should be
noted that the TEM analysis did not find any PCME asbestos fibres in the two samples with the highest PCM fibre concentration from this site
Samples from site D contained a large number of calcium sulphate fibres and other types of asbestos fibres that did not dissolve during wicking It was noted that a few samples from other sites retained significant numbers of calcium sulphate fibres after water wicking In general the individual samples with high PCM counts were from samples where the calcium sulphate may not have been efficiently dissolved during the wet wicking
Table S1 Summary of the site average of the personal PCM fibre concentration for non- .
soluble fibres and the calculated average LOD and LOQ
Site
Site
N of | Average volume concentration conetraion for
samplessamples sampled
soluble fibres
ml
B
14
23.00
0.13
D
11
18.00
0.29
R
8
84.25
0.065
S
24
38.60
0.057
Y
16
8.76
0.26
LOD
0.07 0.09 0.02
0.04
0.19
LOQ
0.22 0.28 0.06 0.13 0.57
At least two samples with the highest PCM fibre counts were selected from each site for TEM
analysis Although the limited volume of air sampled made it difficult to achieve the desired
vii
analytical sensitivity the TEM count was continued until the analytical sensitivity was at least
below 0.08 ml The TEM results were divided into two groups those that used some control
at source and those that used uncontrolled dry removal see table S2 Nearly all the TEM samples analysed were collected with no air extraction from the enclosure None of the selected individual personal samples which used some method to control the release at source were found to have PCME asbestos concentrations above 0.08 ml when analysed using TEM This result is in line with previous site sampling results of TDC removal IF2005 and IF2005
and supports the use of 0.08 ml as an upper estimate of the average exposure for the risk
assessment in the consultative document CD 205
Table S2 Summary of the TEM analysis of personal samples
Site
Site
Sample Number
PCM fibre
concentration ml
Removal with controls
PCME chrysotile fibres
ml [| N
B
00458/06
00474/06
00156/06
00164/06
R
11671
11675
0.58 0.34 0.41 0.46 0.06 0.07
0.07 0.08 0.07 0.07 0.01 0.02
ND ND
ND ND ND
2
S
00326/06
0.05
0.06
3
Removal with no controls
S
00321
0.05
0.21
7
R
11641
0.03
0.02
3
11643 11656
0.04 0.06
0.01 0.01
ND
11
11661
0.05
0.02
2
11667 11668
0.11 0.09
0.18
8
0.12
5
Y
00360/06
0.34
00368/06
0.54
ND = non detected NPU off dry
0.05 0.08
ND
ND
The highest personal PCM samples collected during uncontrolled dry removal gave short term peak exposures ranging from not detected to 0.21 ml Given the type of activities involved and the difficulty in dry scraping surfaces it was unlikely that the four hour control limit would be exceeded Also this type of activity was not compliant with the control of asbestos at work CAW regulations All the TEM samples had low asbestos fibre counts and hence poor
precision
if The change in the personal airborne asbestos fibre concentrations inside the enclosed area
no air extraction is used
It was found that on average when doing similar work the personal PCM fibre concentrations at
these sites were increased by some % when the extraction was switched off This was in line with the result from a simulation in a HSL test chamber see IF2005
viii
The effectiveness of the clearance based on a visual assessment alone
.
The low amounts of fibres released from TDCs means that visual clearance of dust and debris is
more than adequate to ensure that PCM fibre concentrations will remain below the clearance
indicator
The likely airborne releases from poorly controlled removal The PCM results showed no clear pattern of reduction between dry and wet removal of TDCs at the two sites sampled This is in complete contrast to effective wet removal of other licensed ACMs where uncontrolled dry removal produces a two to three order of magnitude increase in
airborne fibre exposures
The airborne concentration outside the enclosure ifno air extraction is used As most of the sites had one or more rooms as the enclosure it was not possible to sample outside the enclosure in a meaningful way The only place where escape of airborne dust was likely was at the airlock exit from the enclosure but as these were generally situated outside the building it was again thought to be of little use to sample around the exit in ambient air It is a current requirement that licensed removal sites use at least a three stage entry and exit airlock for person entering and exiting the enclosure with an inward flow of air In the
guidance a two stage airlock without any inward airflow has been suggested as sufficientdrTafot
test the effectiveness of the two arrangements air monitoring was carried out inside the airlock two flaps away from the source in the enclosure which is equivalent to the second airlock
chamber
The results showed that although the PCM airborne fibre concentrations inside the airlocks
lower with the negative pressure unit NPU on and drawing air into the
were
switched off the increased concentration was still relatively low Site was seanmcplloesdurweitwhhtehne
NPU off when the removal activity was directly over the entrance of the airlock and
ssiutruraotuinondianngdatrheeamaenadswurheednvoanlluye ownaesfaltapthweaLs OinQposition This might be considered a worst
Although it is hard to draw a conclusion from only two sites and when low wind
present outside of the airlock it would appear that
airborne fibre
speeds were
airlock would be low and readily diluted
any
concentrations outside the
The airlock flap system at these sites was designed to allow the ingress of air with a NPU running and there are more effective ways of producing a much more airtight seal to produce a true airlock entry if no NPU was in use
Taking into account that measurements were made inside the airlock it is unlikely that PCM
fibre releases from the enclosure would exceed 0.01 ml in the
entry
area surrounding the airlock
The airborne exposures that will be experienced by persons reoccupying the building
The airborne asbestos fibre concentrations inside enclosures
therefore there is unlikely to be a significant
during active removal were low
been
exposure to airborne fibres if the enclosure has
downthoroughly cleaned and the area inspected for visible debris before the enclosure is taken
Measurements made inside enclosures demonstrated that a PCM fibre
the LOQ 0.01 ml was produced from disturbance clearance
concentration of around
type sampling when sweeping
ix
several grams of visible debris and dust with a broom for at least 5 minutes and sampling for a period of 1 hour This would be a one off peak i.e. a poor clean up had been carried out by a contractor in breach of CAW and where and the occupier or maintenance personnel had to
sweep up the majority of the TDC debris left behind After the first clean up it is unlikely that the small amount of TDC dust and debris remaining would act as a significant future source of
airborne asbestos fibre emission
In order to investigate with greater precision the potential airborne release from the disturbance of debris remaining following removal of TDC a simulation was carried out in the HSL 9 m dust chamber see 2006 This used about 100g of dry friable dust and debris recovered from the dry removal of the TDC at site R. With an air exchange rate of 2.4 room volumes per hour 30 minutes walking over the debris produced personal PCM airborne fibre concentrations of 0.014 ml for all fibres no wicking was used Given that the amount of debris was more than two orders of magnitude higher than what would be easily seen in a visually clean area and the likelihood of disturbance of such a small amount of remaining debris is much lower it is unlikely that any remaining dust and debris following removal of TDCs would contribute significantly measurable airborne fibre concentrations to the indoor environment
The contribution to the airborne asbestos fibre concentration of small amounts of dust and
debris after the site was visually cleared are expected to be below 0.0005 ml
Implications for the risk assessment
For epidemiology and risk assessment the statistic used to represent exposure and dose is the
arithmetic average of the annual exposure which is used to derive the cumulative dose in
years
As nearly all measurements are based on short peak concentrations it is extremely
unlikely that removal of TDC could give rise to cumulative exposures for PCME chrysotile
fibres above 0.08 ml per year
Furthermore it is not expected that PCME chrysotile fibre concentrations would
proposed control limit of 0.1 ml over a hour measurement period
exceed the
Using HSE figures of the current rate of licensed removal of TDCs it is only theoretically possible for 83 workers per annum to disturb TDCs in a way that could approach the level of
activity needed to generate the 0.08 ml average exposure for an entire year as assumed in the
risk assessment
The small increase in airborne concentration when comparing licensed controlled removal with uncontrolled dry removal shows that unlike other licensed ACMs there is a limited amount of additional release that poor practice will generate when compared to the existing regimes used by licensed asbestos removal contractors
The difficulty in releasing fibres from TDCs mean that if any debris is left behind as a result of
poor clean up the contribution to the exposure of the occupants will be small Once the initial clean up of debris and dust has been carried out it is unlikely to be measurably higher than the
ambient background in buildings containing ACMs The additional work in this report supports the risk assessments in CD205 that if CAW regulations and control procedures are applied there will be no predicted premature deaths from asbestos related diseases arising from work
with TDCs
Conclusions
For risk assessment purposes 0.08 ml provides a high upper estimate for the average annual PCM airborne asbestos fibre exposure of asbestos workers removing TDCs It is important to note that a very conservative risk estimate would be obtained based on this figure particularly as it does not take account of any respiratory protective equipment worn by those undertaking
TDC removal work
The upper estimate of 0.08 ml is applicable to all TDC removal work meeting the CAW regulations
Abbreviations and units
um ACMs AIB ALPIS
micrometer
asbestos containing materials
asbestos insulation board
Asbestos Licensing Principal Inspectors HSE
ARCA
Asbestos Removal Contractors Association
ASLIC AWPD
Asbestos Licensing Regulations
Asbestos Worker Protection Directive
CAW
Control of Asbestos at Work
regulations
CD ERM
EU
consultative document
European Regulatory Method European Union
ml
FOD FSSU
HEPA
HSE
HSE
HSG HSL ISO IF
Fibre / millilitre
Field Operations Directorate HSE
Field Scientific Support Unit HSL
High efficiency particulate air refers to high efficiency air filters Health and Safety Executive Health and Safety Executive / Insurance Companies Health and Safety Guidance Health and Safety Laboratory
International Standards Organisation
Inorganics and Fibres HSL Section name
xi
LfiO-DLOD
litre limit of detection
limit of quantification
metre
Methods of Determination of
Hazardous Materials HSE milligramme
millimetre
not detected
number
negative pressure unit phase contrast microscopy phase contrast microscopy equivalent quality assurance Regular laboratory Counting Exchange
textured decorative coating
textured decorative plaster
transmission electron
microscope time weighted average United Kingdom United Kingdom
Accreditation Service
World Health Organisation
1
INTRODUCTION
1.1
BACKGROUND
The implementation of the amended EU asbestos worker protection directive AWPD 2003 means that changes have to be made to the existing control of asbestos at work CAW regulations 2002 The Health and Safety Commission is also taking this opportunity to propose changes to asbestos licensing and prohibition regulations The current asbestos
a licensing regulations ASLIC as amended in 1999 prescribe that work with certain of types
of asbestos containing products must be undertaken by licensed asbestos removal if more than a total of two hours work is to be carried out It is proposed that thicsonitsratoctboer amended in revised CAW r^'gulations2006 as amendments to the EU AWPD directive have introduced a new concept of Sporadic and low intensity exposure to determine whether the work is notified to the responsible authority In Great Britain notification is normally required for licensed asbestos containing materials ACMs and it is proposed in future to fully align notification and licensing using the Sporadic and low intensity exposure cut off
The amended EU AWPD specifically allows member states along with their social partners to
lay down practical guidelines for Sporadic and low intensity exposure The practical approach proposed in the consultation document CD205 to define sporadic and low intensity
exposure would mean that there will be a further reduction in the time currently 2 hours that high risk materials such as thermal insulation spray coatings and lagging can be worked on In general these materials contain both a high proportion of asbestos and the higher risk crocidolite and amosite blue and brown asbestos Also these materials can readily release airborne asbestos fibres especially if worked on without the use of controlled removal methods
a However one group of currently licensed material known as textured decorative coatings
TDC only contain the lower risk chrysotile white asbestos see figure ) and it is present in a much lower percentage than in other licensed see figure 2 materials As the chrysotile in TDCs is more tightly bound in resistant matrix compared to other licensed asbestos
it does not readily release airborne asbestos fibres when worked on These characptreordisutcitcss
separate TDC from other licensed asbestos materials in that it represents a much lower level of
asbestos exposure and risk to workers compared with other licensed materials see figure 3 As part of the consultation it was proposed that TDCs are removed from the licensing regime but will continue to come under the same set of stringent control requirements detailed in the CAW regulations and which apply to work with all asbestos containing materials ACMs
A number of changes to the practical control measures for removal of TDCs included in the
approved Code of Practice and guidance have also been proposed
* use of stage instead of a 3 stage entry airlock e decontamination in the airlock e use of visual inspection without air sampling to ensure that the site is ready for re-
occupation
HSE in response to early comments received during the consultation commissioned HSL to carry out further measurements of airborne fibre concentrations during the removal of TDCs to further assess the effects of the proposed changes in the control regime
risk
Relative
Crocidolite
blue
Amosite
brown
Chrysotile white
and Figure 1 Relative risk Logarithmic scale by asbestos type as assessed by Hodgson
Darnton 2000
TDC
:
TDC 6
Plastics aa
Floor tiles
f
Bitumen a
Cement
@
T
T
T
T
J
0
20
40
60
80
percentage of asbestos
|
100
Figure 2 Typical weight percentages of asbestos in licensed and licensed asbestos products
air conc ml
0.1-
0.01 Spray & lagging
AIB
Product type
TDC
dry
Iwet
Figure 3 Typical airborne personal exposure concentrations monitored at licensed asbestos
removal sites for wet and dry removal of various licensed asbestos products Logarithmic scale with the axis adjusted to the proposed 0.1 ml control limit
1.2
OBJECTIVES
The objectives of the work were to determine the
1. Airborne fibre concentrations releases during the removal of textured decorative coatings
TDCs from a wider range of surfaces to those reported in an earlier survey see IF2005
2. Change in the personal airborne asbestos fibre concentrations inside the enclosed area
during the removal of TDCs if no air extraction is used to keep a reduced pressure inside the enclosure and
3. Effectiveness of the clearance following removal of TDCs based on a visual assessment
alone
A draft sampling and analysis protocol was developed and sent to HSE for comment The draft
protocol was also distributed to the Asbestos Removal Contractors Association ARCA for
comment and operation in carrying out this additional work some of which they had
,
requested The protocol is given in annex 1 and the response from ARCA is given in annex 2
ARCA's response and further points raised by HSE lead to some additional questions being addressed by the research These included
4. What are the likely airborne releases from poorly controlled removal of TDCs 5. What is the airborne concentration outside the enclosure during removal of TDCs if no air
extraction is used
6. What are the airborne exposures that will be experienced by persons reoccupying a building following the removal of TDCs
This report summarises the results from the additional work carried out to meet the objectives and answer the questions listed above The more detailed individual site reports are referenced
2
SITE SELECTION AND STRATEGY
2.1
SITE SELECTION AND ARRANGEMENTS
HSL contacted HSE Asbestos Licensing Principle Inspectors ALPI's in three of the HSE's Field Operations Directorate FOD regions The request was first to locate sites at which TDCs
had been notified for removal and secondly to establish the way in which an appropriate waiver could be issued so that variations from normal licensing conditions could take place HSE personnel at several regional offices were then asked to send any notification for TDC removal
to HSL who assessed the site for its relevance to the objectives of the work Possible sites were then discussed with the supervising HSE Inspector and ALPI and if agreed the asbestos removal
contractor was contacted by HSL staff The purpose of the research was then discussed with the
asbestos removal contractor and a copy of the protocol was sent Following further discussion HSL asked the contractor whether they could sample and then secured the operation of the
main contractor and site owner
Sites of interest were those where asbestos was being scraped or removed in some other way
from a resistant surface e.g. from concrete hard finishing plaster pebbledash and brickwork
One site was also visited where it was reported that careful removal of plasterboard from a ceiling was taking place In the previous survey funded jointly by the HSE and some insurance
companies referred to as HSE study IF2005 it was found that at the three sites that had
reported careful removal of the TDC no measurable chrysotile asbestos was found in the
samples analysed by TEM and further confirmation of this was sought Only one removal from
concrete was present in the notifications received and conversations with removal contractors
confirmed that removal of TDC from this type of substrate was relatively rare
2.2
SITE SELECTION AND SAMPLING BIASES
The previous HSE survey of TDC removal had been arranged so that no involvement of HSE or HSL was apparent to the asbestos contractor only three of the 35 sites were monitored by HSL's FSSU staff for QA purposes The only difference from normal was that instead of the
laboratory representative arriving near the end of the job to clear the site and issue a
certificate of occupation they arrived earlier in order to conduct personal monitoring of the workers carrying out the removal inside the enclosure Personal monitoring is a requirement of the assessment process and would be a familiar occurrence to asbestos operatives The absence
of HSE and HSL staff was intended to ensure that workers carried out their work in an unbiased
way whilst personal sampling was being carried out
In this study it was necessary for HSL staff to go onto site to sample and to make detailed
_ arrangements with both HSE and the contractor to arrange a waiver Although no HSE personnel visited the site or contacted the site supervisor and operatives directly the purpose of the sampling and involvement of HSL was known to all site operatives This might be expected to promote the use of best practice but at all the sites sampled for various reasons the
operatives were up against tight deadlines and the pace of the work observed was usually fast with additional operatives being used It could equally be argued that the knowledge that the
sampling was being carried out specifically to investigate a proposal to remove TDCs from
licensing could provide an incentive for the licensed asbestos removal contractor to ensure high concentrations of asbestos fibres Although some of the HSL requests for sampling were refused by asbestos removal contractors a number of suitable sites were found and sampled It is not verifiable whether the participation at some sites produced a biased sample set but as intended the sites selected covered a range of different substrates
5
3
SAMPLING AND ANALYSIS METHOD AND ISSUES
3.1
SAMPLING METHOD
The sampling method is outlined in Annex 1 and more detailed information is given in the individual site reports see reference section The main purpose of the sampling was to collect the airborne dust on mm diameter membrane filters 0.8 ...mpore size mixed esters of
cellulose to determine airborne fibre concentrations Fibre sampling was carried out using conductive cassettes with flow rates set at between 0.5 - 10 minute based on field
1 conditions The sampling was carried out in accordance with MDHS 39/4
and also HSG 248 annex the new revised method
the current method
Additional sampling of the mass concentration of airborne particulates inhalable and respirable was also carried out using a mm entry diameter inhalable sampler and / or
respirable selecting cyclone operating at 2.0 and 2.2 minute respectively
3.2
ANALYTICAL METHOD
Airborne fibre concentrations were determined in accordance with MDHS 39/4 and HSG248
using both the current European Reference Method ERM and the WHO counting rules The WHO counting rules are scheduled to replace the ERM counting rules in 2006. Quarter filters were prepared in the normal way and counted using both sets of counting rules The counting rules were applied to the same fields of view so the poor precision associated with fibre counting did not mask differences A second set of quarter filters was also prepared and placed on wet blotting paper in a Petri dish to remove any soluble particles / fibres After wicking for approximately one hour and then leaving to dry the filters were prepared and counted by PCM using both sets of counting rules
All four of the PCM analyses on each filter were carried out using light microscopy at X500
magnification with phase contrast optics PCM to count the number of visible fibres i.e.
particles that are > mlong < 3...mwide and with a length to breadth ratio > There are
two main differences between the ERM and WHO counting rules One is the
in which
fibres that attached to or covered by particles are counted The
way
1 of the AWPD 1983 only counts a fibres or a fibre bundles meceutrrienngt tmheetshiozde arelqsuoirseemeeanntsneixf
they are not attached to other greater than 3 ...min diameter i.e. respirable fibres only The
newer World Health Organisation WHO method counts all fibres meeting the size criteria
regardless of other particles
The second major change introduced by the WHO method is to allow for fibre identification / discrimination to take place once the initial PCM count has been made Previously for regulatory determination of the control limit it was required to accept the PCM count as a
sampling measure of the actual asbestos fibre concentration While this was broadly correct for
exposure during manufacturing of ACMs it has been recognised that there are many sources of
asbestos fibres which can be released
during maintenance and removal work
Previous experience has shown that many of the particles released from the disturbance and
removal of TDCs are calcium sulphate In particular texture decorative plaster such as Artex
contains 2-4 chrysotile asbestos with calcium sulphate as filler Plastered surfaces
plasterboard onto which TDCs are
and
commonly applied are also largely made from calcium
sulphate Unfortunately calcium sulphate gypsum particles regularly occur in a fibrous form
with dimensions that meet the PCM fibre counting criteria
6
This means that most of the PCM fibre counts for TDC removal work are calcium sulphate fibres and asbestos fibres usually represent only a small and variable percentage of the fibres counted The variability will also depend on the amount of the underlying plaster that is
disturbed
HSL has pioneered two methods of discrimination
e A method based on dissolving the calcium sulphate fibres and particle before analysis
to remove them from the count The PCM count is then one for soluble fibres
For selected samples the use of an additional analysis based on analytical transmission
electron microscopy with water dissolution if necessary
Both methods have been applied to a selection of the samples to help determine the asbestos fibre concentration The units of measurement are directly relevant for the risk estimation and are based on historical counting conventions for asbestos in industrial manufacture going back
to the 1960s
The additional analysis by analytical transmission electron microscopy TEM uses electron diffraction and energy dispersive ray analysis to identify the individual fibres and the type of asbestos A third quarter filter was prepared for the TEM counting sizing and identification Fibres of a size which would have been visible and counted by PCM fibres > ...mlong > 0.2 3 ...mwide and with an aspect ratio > were analysed This allowed PCM equivalent PCME airborne asbestos fibre concentrations to be calculated as detailed in the international standards Organisation method ISO 10312 for asbestos in ambient air
The United Kingdom Accreditation Service UKAS accredits HSL for all the fibre analyses mentioned above except the wicking preparation
concentrations The total and respirable dust
were determined by weighing the filters in
accordance with MDHS14 The cyclones were fitted with membrane filters suitable for PCM
analysis and these filters were also analysed for their PCM fibre count
3.3
PCM SAMPLING AND ANALYSIS ISSUES
Previous experience has shown that sampling of TDCs is extremely difficult as many sites produce high concentrations of airborne dust This is partly the result of poor dust control at source and the difficulty to effectively wetting both the TDC and the underlying substrate e.g. plaster or plaster board The effect of high airborne dust release is to readily overload the membrane filters with particles in relatively short sampling times This means that not only must multiple sequential samples be collected to try and measure the hour exposures required for comparison to the control limit but also each individual filter has a low sample volume usually between 5L and 100 L during work activity and consequently a reduced analytical sensitivity This problem is illustrated using the results from the previous survey shown in figure 4 see 2005 The limit of detection LOD and limit of quantification LOQ used
was derived from several thousand filter blank counts carried out for the UK RICE PCM fibre
counting proficiency testing scheme See Annex 2 of HSG248
mlLTMNLTTMNT
LTMNConcLTMNLTTMNT LTMNT
fibre LTMNT
NS LTMNT LTMNT
PCM 0
0
:
1 PCMConc ml = LOD ii
i
50
100
150
200
Volume of air sampled )
250
Figure 4 PCM fibre concentrations of treated samples from the HSE
against the calculated limit of detection
study superimposed
LOD v volume of air sampled
ml
Conc
fibre
NS PCM
0
50
100
150
200
Volume of air sampled )
250
Figure 5 PCM fibre concentrations of treated samples from the HSE study superimposed
against the calculated limit of quantification LOQ v volume of air
sampled
8
222
samples 25
SF
samples 222
samples 15 E
of 10
#1 /h
=
No eye
10--19 20-29 11010-0---119920-2390-3930-39 5400-49-5960-660-699 70-7790-79
90-99
80-89
90-99
100-2 149 01500 -199 -22 00-249 49
300
30-39 30-39
40-49 40-49
50-59 50-59
60-69 60-69
70-79 70-79
80-89 80-89
90-99
100-149
150-199
250-299
250-299
100-149 150-199 200-249 250-299 90-99
>
Volume of air sampled
Figure 6 Distribution of sampled air volumes used for PCM counting in the HSE study
requiring treatment before counting was possible
Clearly with poor control at source and hence high dust concentrations and simplistic
assessment of the results of short term low volume samples can lead to biased averages and seemingly high airborne fibre concentrations at or above the control limit However the
statistical relevance and precision of the results renders such interpretations suspect especially
when the control limit is defined over a hour time weighted average TWA N.B. it is an 8hour TWA in the AWPD directive In short peak short results based on low volumes of sampled air are likely to produce much higher results than those which would be obtained during the regulatory hour control limit
Both the ERM and WHO PCM methods recommend that 240 litres of air is filtered to measure
personal exposure Site conditions meant that this was only possible for ~ % of samples in the previous TDC survey usually when low dust activities were being carried out e.g. final clean up
3.4
DETERMINATION OF THE ASBESTOS CONCENTRATION
At best wet wicking PCM samples before analysis will remove most of the readily soluble
fibres and particles e.g. calcium sulphate but there is no certainty that the remaining non-
soluble fibres will be asbestos To assess the asbestos concentration it is necessary to use
analytical electron microscopy to count size and identify fibres of the equivalent size These are
referred to as PCM equivalent PCME asbestos fibres TEM analysis as set out in ISO
10312 takes a lot longer than simple PCM counting as higher magnification are used X5
000 - 11,500 In practice at the magnifications used by HSL the area of the filter scanned
the PCM 200 fields of view is equivalent to 20,000 fields of view in the TEM at tbhye
magnification 11,500X used for sizing Therefore the TEM identification of the asbestos is
used selectively and does not achieve the same analytical sensitivity as the PCM Due to the
high dust concentrations at some of the sites and the very low volumes of air
that the TEM analysis was extended at most sites until
sampled meant
an analytical sensitivity of < 0.1 ml was
achieved This means the results have poor precision
4
RESULTS AND DISCUSSION
Variable amounts of calcium sulphate fibres can be produced depending on how much the
plasterboard or plaster is being scraped As this may change over time only the water wicked
samples giving counts excluding easily soluble fibres have been included in this
report Similarly only results using the WHO counting rules which will be
summary
onwards have been given unless expressly stated otherwise Although the PCuMsecdonfcrenotmra2t0i0o6n
of soluble fibres will not give a direct measure of the asbestos fibres it gives an upper estimate
of what the asbestos fibre concentration could be
a A limited number of TEM analysis of PCME asbestos fibres have also been
site As can be seen in figure 7 it was only possible to
low
reported for each
filter became overloaded Few individual
sample
volumes of air before the
samples exceeded the LOQ and these results should be
reported as the calculated LOQ However it was felt that reporting many of the results as less
than the LOQ based on statistical expectations would be unhelpful and would mask
trends in the data Therefore even though the statistical precision was
the actual
any
of fibres seen was used to calculate the fibre
poor
number
above the LOQ or LOD
concentration regardless as to whether this was
4.1
THE AIRBORNE RELEASES FROM THE REMOVAL OF TDC FROM A
WIDER RANGE OF SURFACES
a HSL report IF2005 summarised the exposure information known to HSL for
TDCs from a variety of surfaces and substrates
removal of
However the study was criticised for
using a number of different removal methods
having a limited sample set especially with respect to the
lack of sites where removal by scraping from resilient under layer e.g. concrete plaster and
brickwork had taken place as it was considered that hard surfaces have the
generating significantly higher airborne asbestos fibre
potential for
summarised in this
concentrations The additional sites
report are described in table 1. Site Y offered a rare
powered chisels removal of textured decorative paint from the outside subsotprpaotretuonfiatybutiolmdoinngito- r
Table 1 Description of activity at the additional sites monitored
Site reference
Description and controls
Scraping painted TDC from finishing plaster on walls and the use of a hammer
B
and bolster to remove painted TDC and plaster from a chimneybreast Tex
was used to soften the TDC being applied on the previous day and at the
gel
work
start of
A hammer was used to punch holes in TDC on
crowbar was used to
a plasterboard ceiling and a
remove plasterboard in large pieces Occasional hand
spraying of the plasterboard to reduce dust concentration
TDC R
Scraping from underside of a ceiling both dry and
using steam removal
S DScaryap1inWgeTtDaCndfrdroym sccornacprietneg ceilings sprayed with remover
Day 2 Wet scraping only
Y Use of a Kango powered chisel to remove TDC paint on the pebbledash on the
outside of a building no controls
10
4.1.1
PCM results
PCM personal airborne fibre concentrations are given in table 2 which includes the calculated
LOD and LOQ for the average volume sampled The high concentration of airborne dust at
some of the sites meant that the sampled air volumes were of necessity very low to prevent overloading the filter see figure 7 At site Y where powered chisels were used the maximum air volume that could be sampled was 10 litres some 24 times lower than recommended in HSG248 Consequently the average airborne fibre concentration was barely above the LOD at this site as defined from blank filter counts and the seemingly high concentration have no statistical significance Sites B and S also gave average PCM fibre concentrations between the LOD and LOQ and the statistical relevance of these results are also questionable Only at sites D and R were the average site PCM concentrations marginally above LOQs based on the average volume of air sampled Site D had the highest PCM fibre concentration and contained much higher concentrations of calcium sulphate and other asbestos fibres than those from the other sites sampled This was surprising in that this was meant to be gentle removal of the TDC and substrate using a method which had previously given low PCM counts and no detectable asbestos fibres by TEM At site B one relatively high PCM fibre concentration 0.58
ml had a large influence on the PCM average
Table 2 Summary of the site average of the personal PCM
soluble fibres and the calculated average LOD and LOQ
N of | Average volume
Concentration of
Site personal
sampled
soluble PCM
samples
B
14
L
23.00
WHO fibres ml
0.13
11
18.00
0.29
R
8
84.25
0.065
S
24
38.60
0.057
Y
16
8.76
0.26
fibre concentration for non-
LOD
0.07 0.09 0.02 0.04 0.19
LOQ
0.22 0.28 0.06 0.13 0.57
25
samples
of
1b]
No
No
5+
0
i
;
Hel
ES
Hb
Blo
of 7
Volume of air sampled L Figure 7 Distribution of sampled air volumes for personal samples counted by PCM
11
4.1.2
TEM results
divided into samples where some
uncontrolled dry removal The
attempt to control dust releases were taken and into
TEM analysis of site D which gave the highest PCM fibre
sought effective removal method was
hour control limit would be exceeded
Therefore it is considered unlikely than the proposed 4-
Table 3 Results of TEM analysis of PCME asbestos
samples with high PCM fibre
fibres on selected personal
counts from each site
Site B R S S R
Y ND = non
Sample Number
PCM fibre
concentration ml
Removal with controls
PCME
ml
00458/06 00474/06 00156/06 00164/06 11671 11675 00326/06
0.58 0.34 0.41 0.46 0.06 0.07 0.05
0.07 0.08 0.07 0.07 0.01 0.02 0.06
Removal with no controls
00321
0.05
11641
0.03
11643
0.04
11656
0.06
11661
0.05
11667
0.11
11668
0.09
00360/06
0.34
00368/06
0.54
detected NPU off dry
0.21 0.02 0.01 0.01 0.02 0.18 0.12 0.05 0.08
chrysotile fibres
N.
ND ND ND ND ND
23 23
7 3
ND
11 2 8 5
ND ND
12
4.1.3
Gravimetric dust concentrations
The average airborne dust concentrations at the sites are summarised in table 4. Usually at a given site either the inhalable or respirable dust concentrations were monitored It can be seen that there was a direct relationship between dust concentration and the average time of sampling for the fibre concentration with sites B and Y exceeding the COSHH exposure
level 4 mg for respirable dust and 10 mg for inhalable dust
Table 4 Summary of average gravimetric airborne dust concentrations
Site
Average inhalable dust
Average respirable dust
concentration mg
concentration mg
B
28.2
-
D3.1
R 2.24 0.45
S
2.66
-
Y11.4
4.1.4
Summary of site data
Overall only two of the five sites gave statistically relevant LOQ average PCM fibre
counts for insoluble fibres Only one of these was higher than the overall
for
individual
personal
samples
from
the
HSE
survey
0.09
ml
The
samples
average from this
site
D contained many asbestos fibres and TEM counts to date show that low numbers of
a chrysotile fibres were present in them It should be noted that the data includes periods of
dry removal and periods where the NPU was switched off Site Y which used Kango chisels to remove chrysotile containing paint and substrate was particularly difficult to monitor as was site B where a hammer and bolster was used to remove both the TDC and
the underlying material from the chimneybreast
Although the analytical sensitivity of the TEM analysis was very limited by the low volume of air sampled analysis of selected samples with high PCM fibre counts showed that low
concentrations of PCME asbestos fibres were present and these were below 0.08 ml
4.2
CHANGE IN THE PERSONAL AIRBORNE ASBESTOS FIBRE
CONCENTRATIONS INSIDE THE ENCLOSED AREA IF NO AIR
EXTRACTION IS USED TO KEEP A REDUCED PRESSURE INSIDE THE
ENCLOSURE
The use of air extraction is primarily to prevent spread of airborne fibres from the enclosure to
adjoining areas Its effectiveness in lowering personal exposures will be both limited and
variable Personal exposures are usually multiple times higher than static
the
airborne fibres and dust is generated by the actions of the removal operativeexupsousaullryesinasclose
proximity to their respiratory region The sampling protocol called for measurements to take
place with the filtered air extraction also referred to as negative pressure units NPU both on
and off As far as possible this was done for similar work and levels of disturbance during both
regimes to allow direct comparison between the two
The average for the five sites listed in table 5 show that overall the personal concentrations were some 23 greater with the NPU switched off This was similar to that reported for
laboratory simulations see IF2005 Although the increase is well within the 95 confidence interval this was a consistent trend for 4 of the 5 sites and was an average for many
13
samples so this is taken to be broadly representative of the
personal exposure
expected average increase in
soluble Table 5 PCM WHO fibre concentration ml for
on and off at the 5 sites sampled
fibres with air extraction
Site
B D R
S
Y
Average
NPU on
ml
0.14 0.67 0.04 0.05 0.26 0.232
NPU off
ml
0.1 0.96 0.06 0.05 0.26 0.286
Difference
%
71 143 150 100 100 123
4.3 EFFECTIVENESS OF SITE CLEARANCE BASED ON A VISUAL
ASSESSMENT ALONE
The PCM results from the site clearance
tests were all carried out with visible
monitoring are given in table 6. The disturbance air
debris and dust on the floor with the aim to
likely maximum concentrations that could be
replicate the
performed and the
generated if a partial or improper clean up was
occupants were left to clean up the mess The disturbance method used was
sites a second disturbance was carried out around the
minutes and the debris was swept into small
point of the sampling after about 30
piles photographed and collected for weighing
collected froma floor area of about 14 m
Some clearance samples were also analysed by TEM and the
in table 7. The results were similar to the PCM
asbestos concentrations are given
concentrations around the clearance level
results and showed that PCME asbestos fibre
0.01 ml can be generated when significant visible
debris and dust remain and are vigorously disturbed
All the sites where HSL staff carried out disturbance air
form of visual assessment as debris
monitoring would have failed any
was readily visible on the floor All three sites where HSL
staff was still present failed the visual
inspection and required further
assessment during the formal certificate of reoccupation
sometimes extensive cleaning
It was also noted that the degree of disturbance used
air monitoring was far greater than that
by HSL staff to carry out the disturbance
analyst simulated disturbance
used by the commercial laboratories In one case the
area
Only marginal contact activity using a nail brush small scrubbing brush to disturb the with the surface was being made during some of the time
The
will result in low fibre and dust concentrations in the air and renders the clearance air testing of
little value
'
a Overall there was no doubt that a reasonable clean up which leaves no easily visible dust and
debris will not give rise to airborne chrysotile concentrations above the clearance indicator even when valid disturbance air test is carried out The low amounts of fibres released from TDCs means that visual clearance of dust and debris is more than adequate to ensure that fibre concentrations will remain below the clearance indicator One analysts stated that he had
not had to fail a TDC removal site on the initial clearance air test concentration for some 50 sites
Ultimately the low fibre release from this material means that removal sites are unlikely to exceed the clearance indicator unless a very poor clean up has been done The requirement in the CAW regulations is for the area to be thoroughly cleaned before taking down the enclosure
If after the enclosure is removed small amounts of dust and debris remain these will
rise to high concentration of airborne fibres and can be cleaned up by the contractornuostinggivea
HEPA vacuum or wet wiping with minimal exposure
Table 6 Summary of PCM results for clearance samples using different preparation
methods and counting rules .
Description of clearance and activity
Site B Room swept for 5 minutes with broom on walls and floor visible debris easily swept into small piles The external laboratory carrying out certificate of re-
occupation monitoring swept the room a small scrubbing brush for a further 5
minutes after about 40 minutes of sampling Samples with many particles
Site D Two separate rooms swept with broom for 5 minutes at the start of the
sampling period visible debris was visible on the floor during Additional clean up ordered by independent analyst attending site later
sweeping
Site S Four individual rooms swept for 5 minutes from ceiling downwards at start of sampling and for a further 2.5 minute after 30 minutes of sampling samples with many particles All four rooms had significant visible debris
Site Y Inside enclosure outside building visible debris
PCM
0.004
0.005 0.005 0.011 0.011
0.005
0.010 0.010
0.010
0.010
0.013 0.013 0.014 0.014
0.004
Table 7 TEM results from disturbance air sampling
PCM fibre
Site
Sample Number
concentration
ml D
00167
0.01
S
00355 |
0.009
NPU off dry sweeping
00356
0.010
PCME chrysotile fibres
#
ml
N
0.002
1
0.0099
5
0.012
6
15
4.4 TRHEEMOLVIKAELLY AIRBORNE RELEASES FROM POORLY CONTROLLED
The control of emission at source is a key requirement of all
reducing personal exposure Effective
health and safety legislation in
method to reducing dust emission
wetting the material being worked upon is the key
Other secondary containment methods such as local exhaust
collection and barrier methods such as wrap and cut and glove bags are also used
4.4.1
PCM results from site monitoring
The effectiveness of the control measures in
was taking place and by carrying out
ofutshee was tested at two of the sites where scraping
part
removal with no attempt at dust suppression
e.g. dry The PCM results are given in table 8
Table 8 Comparison of PCM WHO airborne
and dry removal
concentrations of soluble fibres for wet
Site
suppression method
S
sprayed solvent
R
Steam removal
Dry
PCM WHO with NPU
off
0.05 0.12 0.06 0.06
airborne concentrations of soluble
Wet with NPU
Dry with NPU
off
on
0.03
0.05
0.06 0.07
0.04 0.03 0.04
fibres ml
Wet with NPU
on
0.05 0.07 Not done Not done
It can be seen that the PCM results showed no clear
removal of TDCs at these two sites This is in
pattern of reduction between dry and wet
other licensed ACMs where
complete contrast to effective wet removal of
wetting produces a two to three orders of magnitude reduction in
airborne fibre exposures
where the dry layer begins Although the build up of softened
may have some effect in
material on the end of the scraper
suppressed removal for both suppressing airborne release the difference between dry and
scraping and demolition of TDC seems to be small
weaker layer demolition However completely dry scraping is particularly difficult do
attached to a substrate has a
to
unless the TDC is
removal is needed for
that easily detaches see site R Therefore some aid to
scraping which softens the TDC and
release from the dry surface along which the
partially suppresses the airborne
scraper runs
As the control at source during scraping appears
treatment
only to be partially effective and some
removal
localised steam softening and removal While it is possible that more energetic methods such as powered tools powered sanders and dry grit blasting could be used their use will almost
certainly result in a breach of the CACW AW regulations
4.4.2
TEM results from site R during uncontrolled dry removal and steam
removal
Site R gave an opportunity to monitor in detail the airborne fibre concentrations produced by uncontrolled dry scraping The TDC had been applied to a distempered plaster ceiling and the friability of the paint layer meant that the TDC layer was poorly adhered and could readily be scraped away even when dry The PCM and TEM results for personal samples are given in table 9. The activity carried out was intended to be an example of poor practice where uncontrolled dry removal took place with no extract air inside the enclosure It can be seen that chrysotile asbestos PCME fibre concentrations were above 0.1 ml during the peak removal and sweeping activity Although the airborne fibre concentrations were calculated from the
CAW small numbers of PCME chrysotile fibres that were found 0 - 11 this gives poor precision
but shows that short term peak concentrations of around 0.1 ml can be produced by uncontrolled dry removal or sweeping of friable material These activities which are not allowed under the CAW regulations and did not exceed the proposed minute limit 0.6 ml
The airborne PCME asbestos concentrations for controlled removal using steam to soften and wet the coating were lower than the uncontrolled dry removal but the low numbers of fibres counted make it difficult to show whether this was statistically significant in terms of 95
confidence intervals All the PCME asbestos fibres found were identified as chrysotile
Table 9 TEM PCME airborne asbestos fibre concentrations at site R during uncontrolled dry removal
Sample Number
Activity
11641/05 11643/05
R dry scrape M dry scrape
11656/05
R dry scrape
11661/05
M dry scrape
11667/05 11668/05 11671/05
M cleaning and dry sweeping R cleaning and dry sweeping
R steam scrape
11675/05
M steam scrape
Total / average
* NPU was on only for these samples
No of
asbestos fibres
3 0 11 2 8 5 0 2 31
TEM PCME | chrysotile
concentration
ml
0.019
PCM fibre
concentration
ml
0.03
0.000
0.04
0.115
0.06
0.019
0.06
0.184
0.11
0.124
0.09
0.000
0.06
0.019
0.07
0.060
0.065
17
4.5
THE AIRBORNE CONCENTRATION OUTSIDE
AIR EXTRACTION IS USED
THE ENCLOSURE IF NO
open for prolonged periods The reasons for this
with the supervisor outside the
were due to operatives trying to communicate
placement of equipment and
enclosure
bags at the
waiting
for
further
supplies
and
inappropriate
operatives were active double
entrance to the airlock It was also the area were the
time a single flap was all that bagging asbestos waste etc. Therefore for some of the sampling
separated the middle chamber from the enclosure
The PCM results of the static
sampling carried out inside the airlock with the NPU on and
NPU off are summarised in table 10
the
Table 10 Results of the static
monitoring of the PCM WHO airborne fibre
concentrations of untreated fibres inside the airlock and the enclosure at two sites
Sample details
Volume of
PCM fibre
air sampled | concentration
During removal Site S During removal in 2nd bag airlock NPU on
Site S
in 3rd stage of airlock NPU on
Site S During removal with activity very close to airlock 2nd stage of airlock with NPU off Note an
operative was
ostfatnhdeisngamipnltihnegfpiresrt isotadge and holding a flap open during most
litre
*
1124 264
90
ml
0.001 0.004
0.05
Site B During removal NPU on
During removal NPU on
During removal NPU off
95 188
0.018 0.001
During removal NPU off
560
0.002
Removal activity was far from airlock and low
240
0.007
airborne fibres in the vicinity of the airlock
The sampling evidence available showed that PCM
airlocks were low when the NPU
airborne fibre concentrations inside the
the removal activity was
are switched off Site S was sampled with the NPU off when
directly over the entrance of the airlock and
only one flap was in position The measured airborne fibre
surrounding area and when
considered a worst situation was at the
concentration in what might be
LOQ Although it is hard to draw conclusion from
a to produce true airlock entry if no NPU
into account that measurements were made was in use Using the existing design and taking
releases from the enclosure would
inside the airlock it is unlikely that PCM fibre
was situated
exceed 0.01 ml in the area close to where the airlock
entry
4.6
THE AIRBORNE EXPOSURES THAT WILL BE EXPERIENCED BY
PERSONS REOCCUPYING THE BUILDING
a As the airborne asbestos fibre concentrations inside enclosures during active removal are low
_ then there is unlikely to be significant exposure to airborne fibres if the enclosure has been
thoroughly cleaned and the area inspected for visible debris before it is taken down Measurements inside enclosures which had visible debris and dust demonstrated that a clearance level is produced 0.01 ml when sweeping with a broom for 5 minutes This would be a one off peak if poor clean up had been carried out by the contractor in breach of CAW regulations and the occupier or maintenance personnel had to sweep up the TDC debris left behind After the first clean up it is likely that little asbestos containing material will be left to act as a significant source of airborne emission
Inspecting sites for the spread of debris outside the enclosure is relatively easy If operatives carrying out the work leave the enclosure and airlock still wearing contaminated footwear and overalls it is possible to spread debris outside of the work area At the sites visited there was
some evidence of debris spreading inside the airlock and reducing the airlock from three to two chambers will increase the potential for debris to spread outside the airlock However as we are unable to assess the difference between the two and three stage airlocks in this current study we have INSTEAD looked at the potential effect that any debris will have on the airborne
exposures
In order to investigate the potential airborne release from the disturbance of debris left following a removal of TDC with greater precision a simulation was carried out in the HSL 9 m3 dust
chamber see 2006 This used over 100g of dry and friable dust and debris gathered from site R where dry removal of the TDC had been carried out With an air exchange rate of 2.4 room volumes per hour 30 minutes walking over the debris gave personal PCM airborne fibre concentrations of 0.014 ml for all fibres no wicking was used Given that the amount of debris was more than two orders of magnitude higher than what would be easily seen in a visually clean area and the likelihood of disturbance of such a small amount of remaining debris
is much lower it is unlikely that any remaining dust and debris would contribute significantly
measurable airborne fibre concentrations to the indoor environment The contribution to the
airborne concentration of small amounts of dust and debris after the site was visually cleared are expected to be below 0.0005 ml
19
5 IMPLICATIONS FOR RISK ASSESSMENT
5.2
THEORETICAL MAXIMUM NUMBER OF
HIGH ESTIMATE OF THE
PERSON EXPOSED AT THE
EXPOSURE CONCENTRATION
decontamination The data available from HSE licensed removal database showed
days per year spent on TDC work is
that the current number of job
20,000 with approximately 47,000 worker days per
year
Assuming as above a person was working on TDC for 8 hours
would only be possible for
a day for 240 days a year it
removal is
196 people to be exposed in this way before all licensed
accounted for Even then this is a substantial overestimate of the time
TDC
physically disturbing removing the material as
spent actually
also carried out e.g. travel to site site set
a variety of non- or low exposure activities are
wetting agents final clean
up changing and
application of
that depending on the sizeuopf tehnecljoosbusrettheaatrodvoerwna equipment maintenance etc It is estimated
one half of the time could
year only something between one third and
realistically be spent physically disturbing the TDC i.e. 42 if
midpoint is used Therefore the actual exposure of 0.08 ml could
only theoretically take place
concentrations two to three times lower than the
realised and a larger number of workers will be conservative average of 0.08 ml could be exposed for a shorter time
normally distributed broadly representative of the
substance of concern Unfortunately all of the above activities taking place and based on the
do not apply to the TDC data
Removal of TDCs gives rise to low airborne
the
LOD
and
LOQ
even
if 240
litres
exposures of PCM fibres which are often close to
of
air can be sampled Also the filter blanks
measurable background counts which contribute to the
measured PCM
give
concentration Failure to
20
adequately control dust emissions at source makes the situation far worse in that the LOD and LOQ approach or even exceed the value of the control limit Therefore the distribution of the individual samples is constrained and biased and is no longer a normal distribution Although no corrections for the bias has been made nor for the fact that the PCM counts of soluble fibres is an overestimate of the asbestos fibre concentration it is clear that the PCM average is likely to be an overestimate of the peak short term concentrations
The current and updated EU AWPD directives define the exposure limit over an hour working period UK practice has been to use a 4- hour time weighted average for the control limit which already provides a more stringent control limit of up to twice that required by the
directive if work is undertaken over a hour period
5.4
MEASURED CONCENTRATIONS FROM THE ADDITIONAL SITES
Taking into account the sampling and analytical limitations and the statistical precision and relevance of results below the limit of quantification there is no evidence from the additional monitoring of the short term peak concentration carried out on surfaces where the TDC is being scraped and chiselled off that the estimated average of 0.08 ml for the annual exposure will be exceeded by any worker over a period of a year engaged in TDC removal provided the CAW regulations are applied
21
6
APPENDICES
6.1 AIM
PROPOSED PROJECT TO MONITOR PERSONAL FIBRE
CONCENTRATIONS OF WORKERS INVOLVED IN THE
RENOVATION OF TEXTURED DECORATIVE
REMOVAL AND
COATINGS PHASE 2
The aim of this work is to collect data on fibre emission from
textured decorative coatings removed under licensed
work with asbestos containing
build on the experience of phase 1
and unlicensed conditions It is intended to
The results will be used to inform further the
consultation by HSE on whether decorative
coatings should continue to be a licensed asbestos material
INTRODUCTION
The work in phase 1 showed that
removal contractors
very high dust concentrations were produced by licensed
number of
during the removal of chrysotile containing textured decorative
countable
sampling and analytical strategies were developed for and during phase
coatings A
1 to
samples which were not overloaded This however meant that
try to get
times and low volumes of air had to be
very short sampling
to above the proposed control limit collected that often reduced the limit of quantification
characterise the fibre
of 0.1 ml This required pooling of several samples to
-0.5 -0.5 min it
concentration Also in the later samples using much lower flow rates 0.2
was decided to monitor for longer periods
The release problem This caused the PCM fibre count to
include calcium sulphate fibres and to
The same principles are to be extended to this further
been produced below As sites will be
work and a generic project design has
made to accommodate the
different it is expected that variations will have to be
types of work taking place and local
conditions
PROJECT DESIGN The proposed project is designed to
22
* Collect personnel exposure data fibre and mass concentration during the repair renovation or removal of damaged ceilings or walls coated with asbestos containing textured decorative coatings
Compare the personal exposures from licensed and simulated unlicensed appropriate controls as required by CAWR and the proposed ACOP .
* Compare the clearance levels from licensed and unlicensed removal
work
with
To achieve this where possible the full enclosure built for licensed removal will be divided into two halves one for licensed removal and the other for unlicensed type removal with a temporary plastic barrier in between with a doorway entrance flap cut to allow persons and air to pass through but can be sealed up later to limit the dust spread see below The licensed removal type work will be carried out first in the half with the NPU with the NPU unit on and dust suppression techniques used as normal Both the removal and clean up should be
completed so the Contractor is happy with the area passing a visual assessment
Then turn off the NPU and tape up the entrance to the middle barrier to seal the area and
carry out removal and clean up in the unlicensed area This will mean no extraction or ventilation in
most cases but normally the use of water sprays gel removers and steam units etc. should be used as we would expect these control measures to be used by anybody who removes asbestos
under CAWR
If separation into two areas with a physical barrier is not possible the sampling with NPU on and NPU off should be arranged with a lunch break or overnight gap between
Polythene barrier
oo Extract
<+ __|NPU <
flap
entrance flap
3 stage airlock
LICENSED WORK
NPU on
wy UNLICENSED WORK
NPU off
<q
SAMPLING STRATEGY DURING WORK
Use up to 3 samplers per person 1 for mass concentration and 2 for fibre concentration depends on number of workers The sampling personnel will have to apply a judgement on what sampling rate and time of sampling to use based on the expected amount of airborne dust Sample the two main work phases removal and clean separately by
23
Use a cowled sampler head with 0.8
...m sampling minute for entire
pore size filter
set at between 0.2 - 0.5
period of removal and then change head for entire
period of clean up
fi Use a cowled sampler with 0.8 um cowl every 10 minutes during dusty pore size filter sampling at 1 minute and change periods or if lower concentration leave for longer The sampling person will have to judge this as best they can
* Measure respirable dust on at least 1
e.g. 2.2 min for removal
person using a cyclone sampler at the appropriate rate
be fitted with a 1.2
period and then change over for the clean up The cyclone
...mpore size membrane filter to allow for PCM
can
reweighing
counting after
Measure total dust on 1
person using IOM inhalable sampler operating at 2 min for removal period and then change over for the clean period
SAMPLING STRATEGY DURING CLEARANCE
personnel will carry out stage 2 and 3 of the
248 in each part of the enclosure
stage clearance test as documented in HSG
licensed and unlicensed individually
For each separate part
' The stage 2 visual clearance will note whether dust
area The Contractor will not be
and debris are visible inside the work
adequately cleaned in either sectioanskbeudt atodectaarirlyedounottfeuratnhder clean if not found to be
the amount and location of the debris seen
photographs will be made of
The stage 3 disturbance
detailed
in
HSG
248
in
sampling
each half
using
a
new
broom
will
be
carried
out
separately
as
of the enclosure when dry to collect 480 litres of air
static membrane filter samplers
onto
licensed ' The
area should be cleared first with NPU off
a The full stage procedure for certificate of
laboratory after the HSL clearance Results to breeofcocruwpaartdieodn twoilHl SbLe carried as usual by another
ANALYSIS
Quarter filter should be mounted for PCM
examined
analysis and counted by WHO rules
200 fovs
Quarter filters should be carefully wicked in water
when dry left overnight mounted for
to remove calcium sulphate particles and
examined
PCM analysis and counted by WHO rules 200 fovs
24
Quarter filters should be prepared for TEM analysis and counted by ISO method for PCME fibres asbestos and asbestos fibres identified If lots of calcium sulphate present grids can
be placed in a water washer for 60 minutes to dissolve fibres see appendix H ISO 10312 95
A quarter filter should be retained and stored
Mass concentration filters should be weighed before and after sampling with 3 control blank
filters
REPORTING
Individual site reports detailing the work and results will be produced by HSL
6.2
RESPONSE FROM ARCA
Dear Gary
Please find below the ARCA Technical Committee comments on the proposed further trials to
tdeextteurrmeidnceoatthiengasppropriateness of the proposed method of removing asbestos containing
The sites should be large enough so that removal of textured coating can take place during the
entire sampling period This will allow the measurement data from the study to be assessed
in terms of actual airborne fibre concentrations rather than in terms of
airborne fibre concentrations
weighted average
The range of textured coatings removed during the first study was too limited to permit a full assessment of the likely risks associated with textured coating removal Any conclusions derived from the study results can therefore only be applied to the coating types and removal techniques observed All sites during further trials should include proper removal from concrete not removal of plasterboard and plaster that happens to have Artex on it
No measurements were made during the first study to determine whether there had been
spread of asbestos contamination to outside the enclosures and no measurements were made
of airborne asbestos fibre concentrations at the location of demolished enclosures Robin
Howies method of micro vacuuming to identify fibres that have left the enclosure and settled on
surfaces should be employed after completion of jobs during further trials to assess whether
fibres are present
any
The failure to address the potential for asbestos contamination generated by the removal of textured decorative coatings to spread into areas occupied by unprotected adults and children is a critical omission from the first study and should be addressed this time
All work during the first study including enclosure construction was carried out
trained and licensed contractors which will bias the results towards best pbryacetxipceerienTcheed
proposal is to allow the work to be carried out by unlicensed contractors therefore the
trials should assess the new
further
proposal by using unlicensed contractors
study HSL were on site during the first
to manage the work which will have ensured
better than normal practice This will have biased the results towards best practice
25
and this casts doubt on the validity of the
representative of likely world
measurement results obtained as being
of tests
exposures This will also apply to the second series
http://www.arcaweb.org.uk/ARCA A Permission for HSL to carry out further studies
permission of the client therefore
on removal sites will require the
directly in order to obtain
we would recommend that HSL contact our members
sites at which to carry out further studies list of ARCA
members can be found at
members1024.asp
cFoinnsaullltyawtiilolnthpeerniecoedssity to carry out the further trials result in the need to extend the
Regards
Steve Sadley
26
7
REFERENCES
IF 2005/03
An Investigation into the airborne fibre releases during the removal of textured
coating from Domestic Premises G.Revell HSE project report
IF2005 IF2006
Airborne fibre concentration during the removal of asbestos containing textured
decorative plasters and paints and the risk to workers G.Burdett
Removal of chrysotile containing textured decorative coatings additional work report 1 - Site R G. Burdett and G Revell HSE Project report
IF2006 IF2006 IF2006
Removal of chrysotile containing textured decorative coatings additional work
report 2 Simulation tests G. Burdett and G Revell HSE Project report
Removal of chrysotile containing textured decorative coatings additional work
report 3 - Site Y G. Burdett HSE Project report
Removal of chrysotile containing textured decorative coatings additional work report 4 - Site S G. Burdett HSE Project report
IF2006
Removal of chrysotile containing textured decorative coatings additional work report 5 - Site B G. Burdett HSE Project report
IF2006
Removal of chrysotile containing textured decorative coatings additional work report 6 - Site D G. Burdett HSE Project report
CD205 Amendments of the Control of asbestos of work regulations 2002 Regulatory Impact Assessment HSE 2005
CAWR 2002 Control of asbestos at work regulations 2002 SI 2002/2675 The Stationary
Office ISBN 0 7176 2382 3
EU Directive 2003 Protection of workers from the risks related to exposure to asbestos at
work amending Council Directive EEC OJEU L97 2003 ERM MDHS 39/4 Asbestos fibres in air Sampling and evaluation by phase contrast microscopy PCM under the Control of Asbestos at Work Regulations HSE Books 1997 ISBN
0-7176-1113-2
MDHS14 Methods of Determination of Hazardous Materials General methods for
and gravimetric analysis of respirable and inhalable dust HSE books
sampling
7176-1749-1
February 2000 ISBN 0-
HSG248 Asbestos The analyst's guide for sampling analysis and clearance
HSE 01/05 ISBN 0-7176-2875-2
procedures
22