Document GK9Omp0p3w3BjDE0wMgNzX5pr
T q\b
( The GEON Company One Geon Center
Board of Incident Review Vinyl Chloride Monomer Release Building 413,3 Liter Laboratory
12/5/96
Summary of the Incident At approximately 3pm on December 5, 1996 the Resin R&D 3 liter pilot
operations experienced a clamp failure on reactor #1. Approximately 1 hour into the reaction the reactor retaining clamp failed which allowed the reactor to separate at its mating flange. Upon separation a combination of polyvinyl chloride resin and vinyl chloride monomer was released to the atmosphere in the room. It was calculated that approximately 2.1 pounds ofvinyl monomer was released. There were no injuries and no
exposures over the OSHA reporting criteria.
Board ofReview A Board ofReview was convened on Thursday the 5th of December 1996 at 4:15
PM with the following in attendance:
c Jerry Bialko Bob Tebbutt
Facility Manager Director R&D Resin & Intermediates
A1 Kalzewski
R&D Senior Process Specialist
Resin Pilot Plant Lead Operator
Kevin Maggioli
Resin Pilot Plant Engineer
Resin Pilot Plant, 3 Liter Operator
Ben Homas
Research Technician, Resin R&D
Dale Wahl
Maintenance Supervisor
Shane Ryan
Maintenance Supervisor
Jason Barnes
Environmental, Health & Safety Engineer, OGC
Narrative
The discussion began with a review of the incident and the circumstances leading
up to it.
. 3 liter operator, had prepared reactor #1 according to standard
operating procedures. As part of the preparation, pressure and vacuum tests were
performed on reactor #1 prior to charging. The reactor held pressure and vacuum within
specified limits and he began the experimental charge. Approximately 1 hour into this
process
observed that the charge was beginning to solidify instead of normal
polymerization, he then began to cool the reactor down as per procedure. 2 to 5 minutes
after the cooling began, 1
: suspension resin technician were discussing
the reaction characteristics by the computer control console in the lab when they heard
and felt a pressure concussion. Both men observed that the reactor had failed, they
immediately left the laboratory.
redacted
NGC 13571
c
The VCM warning alarm lights activated at the 1 and Sppm levels almost immediately
with the lOOppm warning alarm hom sounding approximately 20 seconds later.
Phil Bak a resin scientist who was standing outside the lab when the reactor failed,
immediately went to the fire alarm pull station and pulled the alarm to evacuate the
building as per emergency protocol. However, the alarm did not function. Phil then
proceeded to begin a manual evacuation of the building. E,H&S personnel and the
Facility Manager were contacted by radio and immediately responded to the scene. The
Emergency Response Team (ERT) was also activated via radio. The operators involved
were checked for injuries by ERT personnel and the areas outside the laboratory were
monitored for VCM. No VCM was detected outside ofthe 3 liter lab. Building personnel
were then allowed back into the building. After determining that over 1 pound of VCM
had been released we immediately began the emergency notification protocols as outlined
in site environment policies E-101 through 103. All notifications were made within the
required time frames.
were sent to the dispensary for medical
evaluation for potential chemical exposure, no problems were found.
Once the VCM levels in the lab were below 1 ppm, personnel were allowed to
reenter the room to begin the investigation. Upon investigating, it was determined that the
reactor had failed at approximately 196 psi of internal pressure, which is well below the
vessel pressure rating of 300 psi. Normal operating pressures vary from 160 to 230 PSI.
The reaction was a typical reaction performed in the 3 liter pilot plant.
( The investigation revealed that the bottom portion of the vessel had blown down
and slightly back bending the support structure and hydraulic system as well as tearing the
cooling water outlet line from the vessel. A more detailed inspection showed that the
cooling jacket had been fractured as well. 3 pieces of the vessel retaining damp, the T
bolt assembly and the damp ring (in 2 pieces) were found near the failed reactor.
Upon examination it was determined that the flexible banding steel on the clamp
had fatigued directly along a spot weld which lead to the clamp failure. Normal procedure
is to visual inspect the clamp prior to securing the vessel. The T bolt was examined, the
threads were intact and the bolt assembly was found to be within specification. The age of
the clamp is not known. It appears when the clamp burst that one ofthe pieces flew
towards the computer console striking it with enough force to snap several pieces off of
its casing.
The Avon Lake fire department came to the scene to inspect the damage and
assess if any remaining hazards existed.
Systems Investigation: The fire alarm system did not function properly.
Upon investigating it was determined that the mechanical reset switch on the master control box did not engage fully the last time the system was reset. This has been remedied.
The VCM detection and lab ventilation systems functioned as designed.
Cause The cause of the incident was determined to be mechanical fatigue failure of the
reactor retaining clamp flexible banding ring
NGC
13572
c
Corrective Actions: 1) Remove all present clamps from service and inspect them for evidence ofwear.
Bialko 12/6/96 Complete
2) Replace all present clamps with new clamps. Maggioli 12/10/96 Complete
3) Replace present flexible, T bolt locking clamp design with a 2 piece dual locking clamp for all 3 liter reactors. Maggioli 1/10/97
4) Assess ways of preventing clamps from becoming projectiles should failure ever happen again, i.e. shielding, tethering ect. Maggioli 12/20/96
5) Assess damage and repair costs to 3 liter reactor #1. Maggioli 12/20/96
6) Check and repair faulty fire alarm system. Ryan/Wahl/Bames 12/5/96 Complete
7) Check and replace damaged computer control monitor in 3 liter lab. Kalzewski 12/6/96 Complete
8) Clean lab of all resin particles.
12/6/96 Complete
^ 9) 3 liter laboratory operations are to be suspended until replacement clamps are received.
Bialko 12/5 Complete
Facts Surrounding the Incident There were no injuries The notifications to all outside agencies were made as required Internal management notifications were made as required The laboratory ventilation system worked well The VCM monitoring system worked well OGC sustained a reportable release of vinyl chloride The operator has been an employee of Geon for 8 years The operator followed all procedures as required
Conclusion It was the conclusion of the board that the environmental release was a result of
mechanical failure of the reactor retaining clamp and no operator error or recipe related factors contributed to the release. The 3 liter operations are suspended until such time that new clamps can be secured.
Jason E. Bames Environmental, Health & Safety Engineer, OGC
ngc iss'ts