Document EvXOX278dr23KyV775qDEOG8x
1997 CMP SAFETY AND ENVIRONMENTAL PROGRAM
SAFETY TEAMS
SAFETY TEAM RESPONSIBILITIES
The program will be based on team responsibility.All personnel will participate fully in the Safety and Environmental Program.
All personnel in the plant will be assigned to specific safety teams. Team members will receive incentives if their team meets all of the following:
No team member held responsible for or involved in causing a behavior based injury.
No team member held responsible for or involved in causing a behavior based PSA (Potentially Serious Accident) incident of any kind.
No team member held responsible for a compliance item not being complete, C9/E9
No team member responsible for a Red Tag infraction of any kind.
All team members attend all quarterly safety meetings. Any team member unable to attend one of the scheduled meetings must make-up that quarter's meeting.
All teams will be represented at the quarterly Safety Committee Meetings by the team's committee representative or a substitute when necessary.
The team must complete the housekeeping audit for the months assigned to the team.
There will be no Waste Pak infractions attributed to any team member.
There will be no behavior based spills attributed to any team member.
All team members will have their Safety and Environmental Training done on time.
The shift teams will coordinate and document one emergency drill in the assigned quarter.
1st Quarter A Team 3rd Quarter C Team
2nd Quarter B Team 4th Quarter D Team
If all of the above items are fully complied with, each member of the qualifying team will receive and award yet to be determined.
If any member on a given team does not fully satisfy all of the criteria set forth above, then none of the fellow team members will be eligible for an award.
Program Developed By: The CMP Safety Committee
Date: 12/11/96
1
CONFTDFNTTAl DO 008379
1997 CMP SAFETY AND ENVIRONMENTAL PROGRAM
SAFETY TEAMS (continued)
SAFETY TEAM MAKE-UP
STAFF
A TEAM
Russell Jackson Donald Harrison Oliver Jack Dennis Wolfe Darren Metrejean (Relief Operator)
B TEAM
Freddie Cook Neal Cavalier John Ekey Jason Bourg
James Cook Brian Donatto Donnie Dugas Jim Haney Jimmy Johnson Kevin Kelley Adam Michel Gary Rizzo Colleen Storm Don Taylor Terry Vavasseur Judi Witt
CTEAM
Brent Beieler Clarence Bickham Randy Looney Ron Millender
D TEAM
Curt Grant Richard Breaux Emerson Bishop Clarence Davis Dale Gravouilla (Relief Operator)
SITE LOGISTICS
Julie Clebert Fritz Simonson Ken Doucet Luke Armand
Program Developed By: The CMP Safety Committee
Date: 12/11/96
2
CONFTDFNTTAl.
DO 00R3B0
1997 CMP SAFETY AND ENVIRONMENTAL PROGRAM
SAFETY MEETINGS
Safety meetings will be held quarterly
January, April, July, and October
Limited to one hour in length
Safety coordinator to prepare meeting agendas with input from teams for content.
Safety stats, safety incidents, and environmental concerns will be included in all
meetings.
Staff will assist in facilitating safety meetings
Meetings to be held in the control room at 12:15 on scheduled dates
SAFETY COMMITTEE
MEMBERS
Membership for the committee will follow the guidelines of the ISB Methanes
Team Organization. Through ISB this will be the THROX/PSA/Zones/Safety &
Environmental committee with membership as follows:
Richard Rolke Engineer
James Cook
Technologist
Mike Brown
Environmental
Brian Donatto Safety
Russell Jackson A-Shift
Neal Cavalier B-Shift
Randy Looney C-Shift
Clarence Davis D-Shift
It is each committee member's responsibility to attend all safety committee meetings. In cases of vacation, business travel, emergencies, etc. the committee member must get another member of his team to represent the team.
Program Developed By: The CMP Safety Committee
Date: 12/11/96
3
OONPTDFNTIAI. DO 008081.
1997 CMP SAFETY AND ENVIRONMENTAL PROGRAM
SAFETY COMMITTEE (continued!
MEETINGS
Meetings will be held quarterly. Extra meetings will be scheduled if necessary.
Meetings will be on the 3rd Wednesday of each quarter
1st Quarter, January 15
2nd Quarter, April 16
3rd Quarter, July 16
4 th Quarter, October 15
Meetings will start at 6:15 AM to better accommodate the person working dogs
Meeting agenda will be posted by the Richard Rolke
Meeting agenda and minutes will be forwarded to Roddey Peebles and Greg Shultz
Juice and doughnuts or biscuits will be provided
COMMITTEE RESPONSIBILITIES
Implement the CMP Safety and Environmental Program Review CMP safety/environmental incidents review significant safety/environmental USCR's and suggestions and communicate to
work teams Administer safety standard testing as required Administer environmental testing/training as required Provide forum for discussion of safety and environmental issues Form sub-committees to address issues not resolved in the committee meetings Develop 1998 Safety and Environmental Program
MEMBER DUTIES
Will attend all meetings or find substitute in cases of vacation, business travel, emergencies, etc.
Come Prepared Poll team for discussion topics Work with sub-committees when necessary Complete assignments and report back to the committee
Review meeting minutes with team Training compliance Coordinate / Remind / Inspire group to participate in program activities
Program Developed By: The CMP Safety Committee
Date: 12/11/96
4
CONFTDFNTTAl DO 00B382