June 27, 1968
cc Messrs. J. R. McClain
J. W. Molloy
Start-up Expense Budget for
R. D. Williams
Aroclor Expansion Project (CEA 1800)
R. S. Yates
R. M. Kountz
Jtfr'f'w. A. Kuhn (2) General Offices
Attached for your approval is the Start-up Expense Budget for the Aroclor Expansion Project including estimates of Preparation Expense and Operation Expense These estimates have been prepared to conform to policy given in Controller's Bulletin 12-06 and Organic Division Bulletin No. OA 5-1*
The totals for Preparation Expense and Operation Expense are summarized below.
Total Start-up Expense-$115,000
The total start-up Expense of $115,000 is approximately
of
the estimated capital provided on CEA 1800 for this project. The
basis for the timing of the start-up is Revision No. 5 of the Master
Project Schedule dated 5/20/68.
The attached pages give a detailed break-down of expense esti mates by type and an estimate basis for major expense items.
Service Account Number 916.55 will be used to collect Preparation Expense charges. These charges will be closed out to the division start-up account (715.00) monthly.
Starting in July, a variance report comparing actual start-up expenses with budget will be sent to you monthly.
ghw Approval
Mfg. Representative
TOWOLDMONOQ45021
Preparation Expense Budget Aroclor Expansion (CEft 1800)
Job No. 916.55
2
Budget Item
Factory Expense
Totals
Chemicals (505)
7,000
Utilities
5,150
Mfg. Wages (570)
5,790
Mfg. OH
(578)
810
Salaries (575) 16,450
Salaries OH (578) 2,950
Factory Supplies
(590)
8,000
Laboratory (610)
3,300
Clothing & Laundry
(614) 2,900
Safety Equipment
TSD
(6l3) (621)
400 3,000
Mech.Expens e(694) 20,000
Sub-Total -
75,750
3rd Qtr.
1967
4 th Qtr.
1967
1st Qtr. 1968
Phase I 2nd
June
Qtr.
1968
1968
Phase I July 1968
Phase I Phase II 3rd
Aug.
Sept.
Qtr.
1968
1968
1968
Phase II 4th
Oct.
Qtr.
1968
1968
000
0
0 0 0 1000
0 0 0 100
0 00
15
600 900 1500 1200
100 150
250 200
0 1000
100
15 2200
350
0 1000
965 140 1200 200
0 0 0 0 1650 300
0 0 0 0
4200 650
0 1000
965 140 7050 1150
7000
3150
4725
655 4200
650
7000 3150
4725 655
5200 300
000 000
0 0
0 1000 2000 3000 0 1000 1000 1300
6000 3300
2000 0
2000 0
000
0
0 100
0
0
100 2800
2800
000
0
0 100
0
100
200
200
200
0 0 500 500 500 1000
0
1000
2000
0
0
0 00
0
0 1000 1000 8000 10000 10000 10000
Other Expense
Vendor Fees (715) 5,000 0 0 0
Meetings (798) 1,000 0 0 0
Office Supplies (86^) 250
0
0
0
Sub-Total -
6,250
o
TOTAL -
82,000
0 0 0
0
0
1000
1000
2000 3000
3000
00
0 500
500 500
500
0 100
0
100
200 50
50
TOWOLDMONOQ45022
Estimated Preparation Expense for
Aroclor Expansion (CEA 1800) Job No. 916.55
-3-
1. Chemicals
$7,000
Phase I
STnce only storage tanks and associated equipment
are Involved, It is anticipated no start-up cost for
chemicals will be incurred.
$0
Phase II
Process simulation on new process equipment using
Aroclor 1242 -10,0000. @ $0.70/gal.
$7,000
2. Utilities Phase I
Steam @ 15% Std. Electricity @ 10% Std.
6/68
$100 $1555
7/68 $100 $105$
$5,150
Phase II
10/68
"Steam @ 40% Std. -
$2500
Electricity @ 25% -
250
Purchased Water @50% Std. $400
TO
3. Mfg. Wages Phase I
No.
Repairman
2
Second Operator 5
Std. Operator
2
. Swingman
1
Vac. & Hoi. @ 12.824%
Phase II Premium Operator Still Operator Second Operator Swingman Swingman
4 4 4 1 1
Vac. & Hoi. @ 12.824%
Rate 3.705 3-540 3-405 3-855
3-660 3-620 3-540 3-855 3.620
Hours "24"
180 48 12
Cost
90 635 165
45 "935
130
$1565
240 880
480 (1) 1735 48 170 60 230
320 (1) 1160 FI75 550
W^5
$5,790
(1) New classifications. Will receive training on straight time. All others are regular department
personnel and will be trained on overtime.
4. Mfg. Wages O.H. (13-993%)
$810
00l4*14b
TOWOLDMONOQ45023
5. Salaries (Training, Start-up Planning, Preparation for Start-up)
Phase I a. Mfg. Representative $300/mo. - 8/67 thru 12/67, $500/mo. 1/68 thru 8/68 -
b. Production Supervisor $250/mo. 6/68 thru 8/68
c. Production Foreman $450/mo. 6/68 thru 7/68
Phase II a. Mfg. Representative $500/mo. 9/68 thru 10/68
b. Start-up Foreman $900/mo. 8/68 thru 10/68
c . Production Supervisor $250/mo. 9/68 thru 10/68
d. Shift Supervision 3 men $850/mo. 9/68 thru 10/68
6. Salaries OH (17-75%)
7. Factory Supplies a) Housekeeping Equipment b) Safety Signs c) Equipment Tags dj Safety Equipment e) Laboratory Equipment f) Miscellaneous Start-up Supplies
8. Laboratory a) Develop routine methods for electrical property measurement based on Organic Research Work.
b) Analyst Training
9. Clothing & Laundry (5% of Wages)
10. Safety Equipment
11. Technical Services a) Training Assistance b) Materials Engineer c) IFO Review
-4-
$1,450
$5,500 $750 $900
$7,150
$1,000 $2,700
$500 $5,100 $97W $2,950 $8,000
$3,300
$2,900 $400
$3,000
001<i2<i7
TOWOLDMONOQ45024
12. Mechanical Expense
Phase I - ^ 2,000 Phase II - $18,000
-5-
$20,000
Includes: a) Equipment, Instrument and Electrical checkout prior
to start-up (beyond nominal service provided by Engineering).
b) Alterations to equipment prior to and during process simulation (water batching).
c) Maintenance coverage during start-up.
13. Vendor Fees 14. Meetings
$5,000 $1,000
15. Office Supplies $50/mo. - 6/8 thru 10/68
$250
Total -
$82,000
OOl't^a
TOWOLDMONOQ45025
-6-
Operation Expense Budget Aroclor Expansion
(Over-and-Above Standard)
Budget Items
Totals
Utilities Salaries Salaries OH Factory Supplies Laboratory Mechanical Expense
3,000 5,100
900 2,000 2,000 20,000
TOTAL -
33,000
Phase I Phase I 3rd Qtr. Phase I Phase II Phase II 4th Qtr,
Aug.'68 Sept.'68 '68
Oct.'68 Nov.'68 Dec. '68 1968
1000 0 0 0 0 0
1000 0 0 0 0
2000
2000 0 0 0 0
2000
1000 0 0 0 0 0
0 2,550
450 1,000 1,000 9,000
0 2,550
450 1,000 1,000 9,000
0 5,100
900 2,000 2,000 18,000
o NJ>-
TOWOLDMONOQ45026
-r-
Estimated Operation Expense for
Aroclor Expansion (CEA lBOO) (Over-and-Above Standard)
Following is the basis for estimating Operation Expense for the Aroclor Expansion Project. These costs are for over and above standard costs for chemical operation. All other costs were assumed at standard.
Utilities (Tank farm on line prior to Mfg. Plant)
Pli&SB
Steam @ 15$ Std. - 900 Elec. @ 10$ Std. - 100
TOOT/mo. 8/68, 9/68,
10/68
$3,000
Salaries (Shift supervision on start-up) Phase II ShiftSupervision 3 men @ $850/mo. 11/68 & 12/68
$5,100
Salaries OH (17.750$)
$900
Factory Supplies $1000/mo. over-and-above standard 11/68 & 12/68
$2,000
Laboratory $1000/mo. over-and-above standard 11/68 & 12/68
$2,000
Mechanical Expense Phase I Phase II -
$2,000 $18,000 $2O,00O
$20,000
Includes:
All mechanical expense required for minor modifications and correction of facilities to obtain smooth and trouble free operation at design rate, quality and cost.
TOTAL -
$33,000
0014*50