Document EvK59Q29X2wNkVjYD8BEYN3zb

Monsanto TO Sauget, 111. June 27, 1968 cc Messrs. J. R. McClain J. W. Molloy Start-up Expense Budget for R. D. Williams Aroclor Expansion Project (CEA 1800) R. S. Yates R. M. Kountz Jtfr'f'w. A. Kuhn (2) General Offices Attached for your approval is the Start-up Expense Budget for the Aroclor Expansion Project including estimates of Preparation Expense and Operation Expense These estimates have been prepared to conform to policy given in Controller's Bulletin 12-06 and Organic Division Bulletin No. OA 5-1* The totals for Preparation Expense and Operation Expense are summarized below. Total Start-up Expense-$115,000 The total start-up Expense of $115,000 is approximately of the estimated capital provided on CEA 1800 for this project. The basis for the timing of the start-up is Revision No. 5 of the Master Project Schedule dated 5/20/68. The attached pages give a detailed break-down of expense esti mates by type and an estimate basis for major expense items. Service Account Number 916.55 will be used to collect Preparation Expense charges. These charges will be closed out to the division start-up account (715.00) monthly. Starting in July, a variance report comparing actual start-up expenses with budget will be sent to you monthly. ghw Approval Mfg. Representative TOWOLDMONOQ45021 Preparation Expense Budget Aroclor Expansion (CEft 1800) Job No. 916.55 2 Budget Item Factory Expense Totals Chemicals (505) 7,000 Utilities 5,150 Mfg. Wages (570) 5,790 Mfg. OH (578) 810 Salaries (575) 16,450 Salaries OH (578) 2,950 Factory Supplies (590) 8,000 Laboratory (610) 3,300 Clothing & Laundry (614) 2,900 Safety Equipment TSD (6l3) (621) 400 3,000 Mech.Expens e(694) 20,000 Sub-Total - 75,750 3rd Qtr. 1967 4 th Qtr. 1967 1st Qtr. 1968 Phase I 2nd June Qtr. 1968 1968 Phase I July 1968 Phase I Phase II 3rd Aug. Sept. Qtr. 1968 1968 1968 Phase II 4th Oct. Qtr. 1968 1968 000 0 0 0 0 1000 0 0 0 100 0 00 15 600 900 1500 1200 100 150 250 200 0 1000 100 15 2200 350 0 1000 965 140 1200 200 0 0 0 0 1650 300 0 0 0 0 4200 650 0 1000 965 140 7050 1150 7000 3150 4725 655 4200 650 7000 3150 4725 655 5200 300 000 000 0 0 0 1000 2000 3000 0 1000 1000 1300 6000 3300 2000 0 2000 0 000 0 0 100 0 0 100 2800 2800 000 0 0 100 0 100 200 200 200 0 0 500 500 500 1000 0 1000 2000 0 0 0 00 0 0 1000 1000 8000 10000 10000 10000 Other Expense Vendor Fees (715) 5,000 0 0 0 Meetings (798) 1,000 0 0 0 Office Supplies (86^) 250 0 0 0 Sub-Total - 6,250 o TOTAL - 82,000 0 0 0 0 0 1000 1000 2000 3000 3000 00 0 500 500 500 500 0 100 0 100 200 50 50 TOWOLDMONOQ45022 Estimated Preparation Expense for Aroclor Expansion (CEA 1800) Job No. 916.55 -3- 1. Chemicals $7,000 Phase I STnce only storage tanks and associated equipment are Involved, It is anticipated no start-up cost for chemicals will be incurred. $0 Phase II Process simulation on new process equipment using Aroclor 1242 -10,0000. @ $0.70/gal. $7,000 2. Utilities Phase I Steam @ 15% Std. Electricity @ 10% Std. 6/68 $100 $1555 7/68 $100 $105$ $5,150 Phase II 10/68 "Steam @ 40% Std. - $2500 Electricity @ 25% - 250 Purchased Water @50% Std. $400 TO 3. Mfg. Wages Phase I No. Repairman 2 Second Operator 5 Std. Operator 2 . Swingman 1 Vac. & Hoi. @ 12.824% Phase II Premium Operator Still Operator Second Operator Swingman Swingman 4 4 4 1 1 Vac. & Hoi. @ 12.824% Rate 3.705 3-540 3-405 3-855 3-660 3-620 3-540 3-855 3.620 Hours "24" 180 48 12 Cost 90 635 165 45 "935 130 $1565 240 880 480 (1) 1735 48 170 60 230 320 (1) 1160 FI75 550 W^5 $5,790 (1) New classifications. Will receive training on straight time. All others are regular department personnel and will be trained on overtime. 4. Mfg. Wages O.H. (13-993%) $810 00l4*14b TOWOLDMONOQ45023 5. Salaries (Training, Start-up Planning, Preparation for Start-up) Phase I a. Mfg. Representative $300/mo. - 8/67 thru 12/67, $500/mo. 1/68 thru 8/68 - b. Production Supervisor $250/mo. 6/68 thru 8/68 c. Production Foreman $450/mo. 6/68 thru 7/68 Phase II a. Mfg. Representative $500/mo. 9/68 thru 10/68 b. Start-up Foreman $900/mo. 8/68 thru 10/68 c . Production Supervisor $250/mo. 9/68 thru 10/68 d. Shift Supervision 3 men $850/mo. 9/68 thru 10/68 6. Salaries OH (17-75%) 7. Factory Supplies a) Housekeeping Equipment b) Safety Signs c) Equipment Tags dj Safety Equipment e) Laboratory Equipment f) Miscellaneous Start-up Supplies 8. Laboratory a) Develop routine methods for electrical property measurement based on Organic Research Work. b) Analyst Training 9. Clothing & Laundry (5% of Wages) 10. Safety Equipment 11. Technical Services a) Training Assistance b) Materials Engineer c) IFO Review -4- $1,450 $5,500 $750 $900 $7,150 $1,000 $2,700 $500 $5,100 $97W $2,950 $8,000 $3,300 $2,900 $400 $3,000 001<i2<i7 TOWOLDMONOQ45024 12. Mechanical Expense Phase I - ^ 2,000 Phase II - $18,000 -5- $20,000 Includes: a) Equipment, Instrument and Electrical checkout prior to start-up (beyond nominal service provided by Engineering). b) Alterations to equipment prior to and during process simulation (water batching). c) Maintenance coverage during start-up. 13. Vendor Fees 14. Meetings $5,000 $1,000 15. Office Supplies $50/mo. - 6/8 thru 10/68 $250 Total - $82,000 OOl't^a TOWOLDMONOQ45025 -6- Operation Expense Budget Aroclor Expansion (Over-and-Above Standard) Budget Items Totals Utilities Salaries Salaries OH Factory Supplies Laboratory Mechanical Expense 3,000 5,100 900 2,000 2,000 20,000 TOTAL - 33,000 Phase I Phase I 3rd Qtr. Phase I Phase II Phase II 4th Qtr, Aug.'68 Sept.'68 '68 Oct.'68 Nov.'68 Dec. '68 1968 1000 0 0 0 0 0 1000 0 0 0 0 2000 2000 0 0 0 0 2000 1000 0 0 0 0 0 0 2,550 450 1,000 1,000 9,000 0 2,550 450 1,000 1,000 9,000 0 5,100 900 2,000 2,000 18,000 o NJ>- TOWOLDMONOQ45026 -r- Estimated Operation Expense for Aroclor Expansion (CEA lBOO) (Over-and-Above Standard) Following is the basis for estimating Operation Expense for the Aroclor Expansion Project. These costs are for over and above standard costs for chemical operation. All other costs were assumed at standard. Utilities (Tank farm on line prior to Mfg. Plant) Pli&SB Steam @ 15$ Std. - 900 Elec. @ 10$ Std. - 100 TOOT/mo. 8/68, 9/68, 10/68 $3,000 Salaries (Shift supervision on start-up) Phase II ShiftSupervision 3 men @ $850/mo. 11/68 & 12/68 $5,100 Salaries OH (17.750$) $900 Factory Supplies $1000/mo. over-and-above standard 11/68 & 12/68 $2,000 Laboratory $1000/mo. over-and-above standard 11/68 & 12/68 $2,000 Mechanical Expense Phase I Phase II - $2,000 $18,000 $2O,00O $20,000 Includes: All mechanical expense required for minor modifications and correction of facilities to obtain smooth and trouble free operation at design rate, quality and cost. TOTAL - $33,000 0014*50 TOWOLDMONOQ45027