Document EvJGZ7Nrygg2gnXVrjZYg0q3R
PETRIN P. O. Box 330 Port Allen. LA 707117
CORPORATION
DATE: FEBRUARY 5, TO: JEFF BOCK
FROM: RON LEE RE: ASBESTOS
1991
THE FOLLOUING IS THE RESULTS OF A ASBESTOS SURVEY, RECENTLY COMPLETED IN THE METHANES BLOCK.
THIS ESTIMATE DOES NOT INCLUDE SCAFFOLDING OR MATERIAL RENTAL . BUT DOES INCLUDE ALL ASBESTOS RELATED MATERIAL.
UPON COMPLETION OF THIS REMOVAL PROJECT, YOUR RESPONSIBILITY FOR COMPLIANCE UITH DIVISION OSHA AND EPA POLICY REGARDING ASBESTOS REMOVAL UILL BE GREATLY IMPROVED.
MANHOURS- 797 MATERIAL- *9,258.00 REMOVAL & ENCAPSULATION- *15.655.00 TOTAL JOB COST- *24,913.00
IF UE MAY BE OF ANY FURTHER ASSISTANCE PLEASE FEEL FREE TO CONTACT ME AT EXTENSION 6300.
JTHANK YOU,
RONALD C. LEE.SUPERINTENDENT PETRIN CORPORATION, DOU CHEMICAL
1
DO 074790 CONFIDENTTAI
ii
,\
METHANES ASBESTOS SURVEY OF ASBESTOS TO BE REPAIRED
FEBRUARY 4, 1991
DISTILLATION AREA
* l. 1 1/2" STEAM LINE COMING OUT OF 235* HEADER TO DR-100 HAS 60 FEET OF ASBESTOS PAPER AND INSULATION TO BE REPAIRED.
2. 1 1/2" CONDENSATE LINE LEAVING FROM DR-100-A AND B HAS 15 FEET OF ASBESTOS PAPER AND INSULATION THAT NEEDS REPAIR.
3. E-1006 HAS 12 FEET OF 16" PIPE THAT NEEDS REPAIR.
4. 6" LINE ON MUFFLER NEXT TO E-1006 NEEDS 3 FEET REPAIRED.
5. 1 1/2" CONDENSATE LINE LEAVING FROM PIPE RACK GOING TOUARDS PERMIT OFFICE BUILDING HAS 21 FEET OF ASBESTOS PAPER AND INSULATION TO BE REPAIRED.
6. 2" 30* STEAM LINE LEAVING FROM PIPE RACK HAS 30 FEET THAT NEEDS REPAIR.
7- 2" LINE BY PERMIT OFFICE HAS 30 FEET THAT NEEDS REPAIR.
e. 1 1/2" OUTLET LINE RUNNING ON SIDE OF MCC BUILDING TO IN BETUEEN MCC AND 4601 HAS 20 FEET OF INSULATION THAT NEEDS REPAIR.
* 9. C-8033-3" FEED LINE RUNNING INTO PIPE RACK HAS IS FEET TO BE REPAIRED.
* 10. 8" 30* STEAM LINE IN PIPE RACK NORTH OF MCC BUILDING, RUNNING UP TO ACID AREA NEEDS 25 FEET REPAIRED.
11. 3" LINE COMING OF 30* LINE TO C-B03 CONTROL VALVE HAS 15 FEET OF INSULATION TO BE REPAIRED.
* 12. 2" LINE COMING OFF OF 30* STEAM LINE TO TOP DECK STEAM HEADER NEEDS 15 FEET TO BE REPAIRED.
* 13. 2" STEAM HEADER LINE COMING OUT OF 30* STEAM LINE RUNNING ON SIDE STAIR UAY NEEDS 10 FEET REPAIRED.
* 14. 10" 235* STEAM LINE RUNNING FROM NORTH OF MCC BUILD ING TO ACID AREA NEEDS 20 FEET REPAIRED.
15. 2" STEAM LINE COMING OUT OF 235* STEAM LINE TO
C805 HAS IS FEET TO BE REPAIRED.
(CON'T PG. TWO)
JO S' '
DO 074294 CONFIDENTIAL
METHANES ASBESTOS SURVEY OF ASBESTOS TO BE REPAIRED
FEBRUARY 4, 1991
16. C803 HAS 3 FEET OF 10" THAT NEEDS TO BE REPAIRED.
17. C803 HAS 9 FEET OF 2" THAT NEEDS TO BE REPAIRED.
18. C805 HAS 3 FEET OF 10" THAT NEEDS TO BE REPAIRED.
19. C805 HAS 3 FEET OF 2" THAT NEEDS TO BE REPAIRED.
20. 3" VENT LINE FOR C806,C803 AND C802 HAS 3 FEET TO BE REPAIRED.
21. 2 EA. 3m LINES COMING OUT OF C8S0 REBOILERS NEEDS 20 FEET TO REPAIR.
22. 1" STEAM LINE RUNNING FROM PIPE RACK ABOVE 2ND DECK BY D800 HAS 10 FEET TO BE REPAIRED.
23. TOP DECK OF STRUCTURE SOUTH OF C806 HAS 9 FEET OF 4" TO BE REPAIRED.
24. 3" PIPE RUNNING FROM IN BETWEEN C806 REBOILER TO PIPE RACK HAS 21 FEET TO BE REPAIRED.
25. 10" CONDENSATE HEADER WHICH RUNS FROM DISTILLATION AREA EAST TO ROAD ON SIDE OF FIN FANS NEEDS 70 FEET TO BE REPAIRED.
M/H 205
LABOR COST $ 4,354.00
MAT yL COST S 2,494.00
TOTAL
* 6,848.00
A/C ROOM BUILDING 4601 DISTILLATION AREA
2" LINE IN ROOM NEEDS 18 FEET ENCAPSULATED.
1 ' LINE IN ROOM NEEDS 10 FEET ENCAPSULATED.
M/H 10
LABOR COST $ 210.00
MAT 'L COST $ 119.00
TOTAL
$ 329.00
DO 074795 CONFIDENTIAL.
methanes asbestos
SURVEY OF ASBESTOS TO BE REPAIRED
FEBRUARY 4, 1991
ACID AREA TO EAST PIPE RACK AT CAtt 2
1. S' 304 STEAM LINE NEEDS 75 FEET OF PAPER AND INSULATION TO BE REPAIRED.
2. 6m 2354 STEAM LINE NEEDS 125 FEET OF ASBESTOS PAPER AND INSULATION TO BE REPAIRED.
3. 1 1/2" 30 4 STEAM LINE RUNNING FROM PIPE RACK TOWARDS CONDENSING AREA ON 2ND LEVEL ABOVE SI 001 TO CORNER RIGHT BY LADDER HAS 20 FEET THAT NEEDS REPAIR.
4. 30 FEET OF 3" LINE RUNNING ABOVE STEPS NEXT ACID AREA NEEDS REPAIR.
5. FROM D1002 TO CONDENSATE HEADER. NEEDS 10 FEET OF 8" LINE TO BE REPAIRED.
M/H 105
LABOR COST 4 2,205.00
MAT'L COST 4 2,039.00
TOTAL
4 4,244.00
STORAGE TANK AREA
1. 1 1/2" STEAM LINE FROM 304 STEAM LINE TO TANK AREA NEEDS ISO FEET OF PAPER AND INSULATION REPAIRED.
DECK NEXT TO STORAGE TANK AREA
1. 15 FEET OF 1 ` LINE RUNNING FROM GROUND TO 304 STEAM HEADER NEEDS TO BE REPAIRED,
2. 1 1/2" STEAM LINE RUNNING FROM DECK TO TANK CAR LOADING HAS 180 FEET OF PAPER AND INSULATION THAT NEEDS TO BE REPAIRED AND ENCAPSULATED.
M/H 123
LABOR COST 4 1,449.00
MAT 'L COST 4 815.00
TOTAL
4 2,264.00
DO 0?4P96 CONF TOENTTAl
METHANES ASBESTOS SURVEY OF ASBESTOS TO BE REPAIRED
FEBRUARY 4, 1991
PIPE RACK GOING NORTH AND SOUTH TOUARDS R-60 AND LHC-2
1. 3- EA. 1 " LINES INSULATED TOGETHER NEEDS TO BE STRIPPED FOR DEMO.
2. 3" 304 STEAM LINE LEAVING FROM B" 304 STEAM LINE BY D10Q GOES TO T-900 AND STOPS HAS 75 FEET THAT NEEDS REPAIR.
3. 3" CONDENSATE LINE FROM PIPE RACK TO T-900 HAS SO FEET OF PAPER AND INSULATION THAT NEEDS REPAIR.
4. 1 1/2" LINE FROM T-960 IN PIPE RACK TOUARDS LHC-2 IN BETUEEN T-101 AND T-102 NEEDS 70 FEET OF PAPER AND INSULATION REPAIRED.
5. 1 1/2" STEAM HEADER IN BETUEEN T-101 AND T-102 HAS 25 FEET OF PAPER AND INSULATION THAT NEEDS REPAIR.
6. 1 1/2" LINE FROM T-102 UEST TO PUMPS 255 A&B HAS SO FEET OF PAPER AND INSULATION THAT NEEDS REPAIR.
7. 1 1/2" LINE FROM T-102 TO T-261 INCLUDING STEAM HEADER HAS 80 FEET OF PAPER AND INSULATION THAT NEEDS REPAIR.
8. 1 1/2" LINE FROM T-261 TO T-104 HAS 70 FEET OF ASBESTOS PAPER AND INSULATION THAT NEEDS REPAIR.
9. 1 1/2" LINE FROM THE MIDDLE OF T-261 UEST TO PUMPS 259 A&B HAS 25 FEET OF PAPER AND INSULATION TO BE REPAIRED.
10. 1 1/2" LINE FROM STEAM HEADER BY 259 A&B TO THE OF T-814 A AND THEN TO THE BOTTOM HAS 100 FEET OF PAPER AND INSULATION NEEDS TO BE REPAIRED.
M/H 200
LABOR COST 9 4.202.00
MAT `L COST 9 2.635.00
TOTAL
9 6.837.00
DO 074297 OONFTOFNTTAL
METHANES ASBESTOS SURVEY OF ASBESTOS TO BE REPAIRED
FEBRUARY 4, 1991 FIN FANS TOUARDS R-300
1. 3" LINE COMING OUT OF 30# STEAM LINE GOING TOUARDS FIN FANS IN PIPE RACK TOUARDS R-300 HAS 20 FEET OF PAPER AND INSULATION TO BE REPAIRED, THEN REDUCES TO A 2" UHICH HAS 100 FEET TO BE REMOVED AND RE-INSULATED.
2. 3 FEET OF 3` LINE RUNNING IN BETUEEN R-300 AND F1000 NEEDS REPAIR.
3. STEAM HEADER BY AH-3 HAS 9 FEET OF 2" LINE THAT NEEDS TO BE REMOVED.
M/H 99
LABOR COST $ 2,090.00
MAT'L COST $ 539.00
TOTAL
$ 2,619.00
DO 074D9B CONFIDENTIAL
METHANES BLOCK ASBESTOS SURVEY ALL ASBESTOS IN BLOCK
FEBRUARY 5,1991
DISTILLATION AREA
1. 1 1/2" STEAM LINE COMING OUT OF 235# STEAM LINE TO
DR 100A.
2. DR lOO A&B HAS 2 STEAM HEADERS ABOUT 30'OF 6" AND
15 FEET OF 2" PAPER AND INSULATION.
3. 1 1/2" CONDENSATE LINE LEAVING FROM DR 100 A &B HAS
48 FEET OF PAPER AND INSULATION.
4. MUFFLERS NEXT TO El006 HAS 9 FEET OF 6" PAPER AND
INSULATION.
5. 2" LINE NEXT TO E1006 HAS 9 FEET OF PAPER AND
INSULATION.
6. 1 1/2" CONDENSATE LINE LEAVING FROM PIPE RACK GOING
TOUARDS PERMIT OFFICE BUILDING HAS 90 FEET OF PAPER
AND INSULATION.
7. 2" STEAM LINE LEAVING FROM PIPE RACK 30# STEAM LINE
HAS 80 FEET OF PAPER AND INSULATION; ALSO ANOTHER
35 FEET OF INSULATION.
8. 2" LINE COMING OFF OF LINE BY PERMIT OFFICE BUILDING
HAS 30 FEET OF PAPER AND INSULATION.
9. 4" LINE AND VALVE HAS 40 FEET OF PAPER AND INSULATION.
(NEXT TO PERMIT OFFICE)
10. 1 1/2" OUTLET LINE RUNNING FROM SIDE MCC BUILDING TO
IN BETWEEN MCC AND 4601 HAS 45 FEET OF PAPER AND
INSULATION.
11. 8" 30# STEAM LINE IN PIPE RACK NORTH OF MCC BUILDING
HAS 120 FEET RUNNING UP TO ACID AREA.
12. 3" LINE COMING OFF OF 30# STEAM LINE TO C803 CONTROL
VALVE HAS 90 FEET OF PAPER AND INSULATION.
13. 2" LINE COMING OFF OF 30# STEAM LINE TO TOP DECK STEAM
HEADER HAS 45 FEET OF PAPER AND INSULATION.
14. 2" STEAM HEADER LINE COMING OUT OF 30# STEAM LINE
RUNNING ON SIDE OF STAIRWAY HAS 25 FEET OF PAPER AND
INSULATION.
15. 10' 235# STEAM LINE RUNNING FROM NORTH OF MCC BUILDING
TO ACID AREA HAS lOO FEET OF PAPER AND INSULATION.
16. 2" STEAM LINE COMING OUT OF 235# STEAM LINE TO C805
HAS 90 FEET OF PAPER AND INSULATION.
17. C803 HAS 12 FEET OF 10" LINE WITH PAPER AND
INSULATION.
18. C803 HAS 9 FEET OF 2" LINE WITH PAPER AND INSULATION.
19. C805 HAS 12 FEET OF 10" WITH PAPER AND INSULATION.
20. C805 HAS 3 FEET OF 2" LINE WITH PAPER AND INSULATION.
21. 3" VENT LINE FOR C806 ,C803,C802 HAS 70 FEET OF PAPER
AND INSULATION.
22. 2 EA. 3" LINES COMING OUT OF C8SO REBOILERS HAS 21
FEET OF PAPER AND 40 FEET OF PAPER AND INSULATION.
23. 1" STEAM LINE RUNNING FROM PIPE RACK ABOVE 2ND DECK
BY 0800 HAS 20 FEET OF PAPER AND 30 FEET OF
INSULATION.
24. DR 100A HAS 56 SQUARE FEET OF INSULATION.
25. DR 100B HAS 56 SQUARE FEET OF INSULATION.
no m0-,7,,o4Q29Q9
CONFTDFNTTAl
/oir'
//
METHANES BLOCK ASBESTOS SURVEY ALL ASBESTOS IN BLOCK
FEBRUARY 5,1991
26. 3" PIPE RUNNING FROM IN BETWEEN C 806 HAS 9 FEET OF PAPER AND INSULATION.
27. 10" CONDENSATE HEADER RUNS FROM DISTILLATION AREA EAST TO ROAD ON SIDE OF FIN FANS HAS 175 FEET OF PAPER AND INSULATION.
A/C ROOM BUILDING 4601
1. 2 EA. 2" LINE FROM A/C ROOM TO MCC PERMIT OFFICE BUILDING HAS 60 FEET OF INSULATION.
2. 3" LINE IN ROOM HAS 25 FEET OF INSULATION. 3. 2" LINE IN ROOM HAS 40 FEET OF INSULATION. 4. 1" LINE IN ROOM HAS 175 FEET OF INSULATION.
ACID AREA EAST TO PIPE RACK AT CA-2
1. 8" 304 STEAM LINE HAS 225 FEET OF PAPER AND INSULATION.
2. 6" 2354 STEAM LINE HAS 325 FEET OF PAPER AND INSULATION.
3. 11/2' 304 STEAM LINE RUNNING FROM PIPE RACK TOWARDS CONDENSING AREA ON 2ND LEVEL ABOVE SI 001 TO CORNER RIGHT BY LADDER HAS 80 FEET OF PAPER AND INSULATION.
4. 3" LINE RUNNING ABOVE STEPS NEXT TO ACID AREA HAS 30 FEET OF PAPER AND INSULATION.
5. FROM 01002 TO CONDENSATE HEADER 8" LINE HAS 25 FEET OF PAPER AND INSULATION.
FIN FANS TOWARDS R-3Q0
1. 3" LINE COMING OUT OF 304 STEAM LINE GOING TOWARDS FIN FANS IN PIPE RACK TOWARDS R-300 HAS 42 FEET OF PAPER AND INSULATION, THEN TURNS INTO A 2" LINE HAS 100 FEET OF PAPER AND INSULATION.
2. 3" LINE RUNNING IN BETWEEN R-300 AND FIOOO HAS 15 FEET OF PAPER AND INSULATION.
3. STEAM HEADER BY AH-3 HAS 9 FEET OF 2" LINE WITH PAPER AND INSULATION.
13 3? 1
DO 074300 CONFIDENTIAL
methanes block
ASBESTOS SURVEY ALL ASBESTOS IN BLOCK
STORAGE TANK AREA
FEBRUARY 5,1991
1. 1 1/2" STEAM LINE FROM 30# STEAM LINE TO TANK AREA HAS 225 FEET OF PAPER AND INSULATION.
DECK NEXT TO STORAGE AREA
1. 1" LINE RUNNING FROM GROUND TO 30# STEAM LINE HAS 40 FEET OF PAPER AND INSULATION.
2. 1 1/2" STEAM LINE RUNNING FROM DECK TO TANK CAR LOADING.
PIPE RACK GOING NORTH AND SOUTH TOUARDS R-60 AND LHC-2
1. 3" 30# STEAM LINE LEAVING FROM 8" 30# STEAM LINE BY 0108 GOES TO T 900 AND STOPS HAS 200 FEET OF PAPER AND INSULATION.
2. 3" CONDENSATE LINE FROM PIPE RACK TO T900 HAS 225 FEET OF PAPER AND INSULATION.
3. 11/2" LINE FROM T900 IN PIPE RACK TOUARDS LHC-2 HAS 180 FEET OF PAPER AND INSULATION.
4. 11/2" STEAM HEADER IN BETUEEN T 101 AND T 102 HAS 80 FEET OF PAPER AND INSULATION.
5. 1 1/2" LINE FROM T 102 UEST TO PUMPS 255 A&8 HAS 120 FEET OF PAPER AND INSULATION.
6. 1 1/2" LINE FROM T 102 TO T 261 INCLUDING STEAM HEADER HAS 120 FEET OF PAPER AND INSULATION.
7. 11/2' LINE FROM T 261 TO T 104 HAS 120 FEET OF PAPER AND INSULATION.
8. 1 1/2" LINE FROM MIDDLE OF T 261 UEST TO PUMPS 259 A&B HAS 60 FEET OF PAPER AND INSULATION.
9. 1 11/2" LINE FROM STEAM HEADERS BY 259 A&B TO T 814A TOP TO BOTTOM HAS 160 FEET OF PAPER AND INSULATION.
C--8SO HAS 1.272 SQUARE FEET OF ASBESTOS.
C-806 HAS 1,711 SQUARE FEET OF ASBESTOS.
/13c I
DO 074301 CONFIDENT TAl
METHANES BLOCK ASBESTOS SURVEY ALL ASBESTOS IN BLOCK
FEBRUARY 5,1991
transite next to acid area by stairuay going up has
600 SQUARE FEET OF ASBESTOS.
TRANSITE ON UAREHOUSE HAS 9984 SQUARE FEET OF ASBESTOS.
TRANSITE ON BUILDING BY TANK CAR LOADING AREA HAS 448 SQUARE FEET OF ASBESTOS.
TRANSITE ON ANALYZER SHACK BY C806 HAS 448 SQUARE FEET OF ASBESTOS.
U (*ko tr
DO 07430? CONFIDENTIAL