Document Ev2dZ6OgD753X93gEdk5j0eeb
Monsanto
FROM < NAME ft L OCATION )
H. J. Lay - G. 0.
,DATE December 16 1968
SUBJECT
vSolid <^roclor<^ /
Manufac^u3?--n Liquid
REFERENCE
Aroclor System at Anniston
TO
cc: J. E. Smith
H. W. Tippee
E. S. Robson
Paul Benignus
J. J. Kagan
D. A. Olson
W. E. Schalk
M. T. White
R. E. Bilger
W. G. Sturm
W. A. Kuhn
W. F. Waychoff
N. L. Sample
C. Paton
Harry Ray - WGK
Roland Haydel - Anniston
Virgil Brawley - WGK
Hill Williams - Anniston
3 extra
On 12/13/68 a meeting was "held at the General Offices to deter mine "needs" to handle the almost 5 M lbs. solid aroclor deficit in 1969. Those present were:
Roland Haydel Harry Ray Virgil Brawley Toby White Bill Sturm Herb Day
Before the above objective can be accomplished, the following needs must be met.
1. Move 4 - 5 M lbs. non-1242 liquid aroclors to WGK. This can be accomplished on Jan. 1, 1969 when additional blend facilities are available at WGK.
2. Move 18 M lbs. 1242 to WGK. Approximately 5 M lbs. can be moved on Jan. 1, 1969., but we need at least 13 M lbs. of the electrical capacitor 1242 business switched. This 'heed11 must be accomplished by Functional Fluids Marketing.
3. A jacketed line must be installed from #1 still to the new flaker. Present plan calls for this to be accomplished by Feb. 1, 1969.
4. Extra drumming labor is needed at WGK and will be available by 1/15/69. Still more labor can be added if necessary upon 30-days notice.
5. Second blend tank required at WGK. This will be operational by Jan. 1, 1969.
6. Vaporization rate of chlorine needs to be checked at WGK.
7. Penalty of switches needs to be calculated.
DSW 200533
STLCOPCB4058597
H. S. Bergen
Page 2
December 16, 1968
Responsibility for each need is as follows:
1. White, Sturm, Day. 2. Olson, Benignus 3. Haydel 4. Ray 5. Hay 6. Ray 7. White, Sturm
Each of these "needs" must be fulfilled as soon as possible, otherwise the program will not be successful.
HJD/sjw
H. J. Day
DSW 200534