PLAINTIFF'S EXHIBIT INDUSTRIAL CONTRACTORS AND RIGGERS, INC. Formerly: CONSTRUCTION DIVISION, SOUTHWESTERN TRANSFER CO., INC. 1730 Bointl Avt. r. O. Box Titt El Paso, Texas 79948 (915) J32-3491 February 10, 1970 American Smelting and Refining Company P. 0. Box 1111 El Paso, Texas 79999 Attn: Hr. Bill Kasmyth Gentlemen: Based on our time and material rates furnished to you on February 6, 1970, we estinate that the setting of your turbinegenerator under the supervision of a General Electric installer will be approximately as follows: Time Required -- Five 40 hour weeks: Millwright Supt. Millwright Foreman Millwright I/M Foreman Ironworker 50 ton Crane Tractor & Trailer Pickup 200 hrs (a 10.68 200 hrs <3 10.00 400 hrs (3 8.04 40 hrs @ 9.30 80 hrs @ 8.47 40 hrs (3 45.00 20 hrs @ 12.50 200 hrs (3 1.50 $ 2,136.00 2,000.00 3,216.00372.00 677.60 1,800.00 250.00 300.00. $10,751.60 7;T Very truly yours, SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. GRH:iz G. R. Hatch