Final Status of Pollution and Community Relations - E. G. Wright TSD Objective F-l a. Installed continuous solids monitoring on waste treatment plant effluent. Completed attained b. Installed catch basin under Soda Ash slurry tank. Completed ATTAINED c. All treatment plant effluents are still being held for One week. Completed Attained d. Continuing to operate the Snow Creek sampling station.COMPLETE! . ATTAINED e* Project for sump catch basin at PgS,. transmitted. COMPLETED . attained TSD Objective F-2 a. Contacted Mr. Joe Crockett of A.W.I.C. Joe LandwehrCOMPLETEB and I visited with him in Montgomery. ATTAINED b. Attended a meeting of A.W.P.C.A. in Auburn c. Joined the A.W.P.C.A, COMPLETED ATTAINED COMPLETED ATTAINED d. Visited with Conservation people at Eastaboga Fish ^j^ned^ Hatchery 4 times during 1968. ' e Met with City Treatment Plant personnel at least 6 COMPLETED times in 1968. ATTAINED TSD Objective F-3 TSD Objective F-4 a. Some sampling was done in 1968. Plans for 1969 include evaluation of some types of automated equipment for S02 samp ling. INCOMPLETE CARRIED^? '4f A plan was developed for reporting non-routine air emission and spills by plant operating and maintenance personnel. The plan is working satisfactorily. [COMPLETED [ATTAINED TSD Objective F-5 Was unable to get Anniston Star to print an article. But, articles are being placed in each Bama Brief on the subject of pollution. We are also planning a special edition to be sent home which will feature pollution. COMPLETED ATTAINED TSD Objective F-6 TSD Objective F-7 TSD Objective F-8 Drs. Gunning and Suttkus from Tulane were hired to do one study in 1968. COMPLETED! . ATTAINED Choccolocco Creek was manually sampled approximately 45 times during 1968. Continuous sampling equipment is still being evaluated. ' Completed ATTAINED The trebler sampler has been installed and is providing more accurate composite samples of the treatment plant effluent solids. . completed ATTAINED DSW 551947 STLCOPCB4090363