WORK REQUEST FORM
ANNISTON TECHNICAL SERVICES DEPARTMENT
INITIATED BY
R. A .' Haydel
COMPLETED BY
%
J
DATE
May 22, 1970
DATE
DEPT.
826-08
TITLE
PRODUCT
Aroclor
1221
'
JOB NO.
005-1090
ORIGINAL TOT.S.D. FILES
H. L. Williams R. A. Raydel wfr 3. C. Landwehr^ ------* ^ V. R. Haupt W. F. Taffee E. E. Bowles
Produce Aroclor 1121 by continuous method
STATEMENT OF PROBLEM AND OBJECTIVE (USE REVERSE SIDE IF NECESSARY)
'
Sales of Aroclor 1221 has soared in recent months with a good possibility of increasing even furthur to fill voids left by higher chlorinated arocler products being taken off the market. Present estimated monthly sales of 1221 are currently running abound 200M 16S a month. Substantial furthur increases may out.strip production capabilities on a batch basis. Also, since 1121 is chlorinated in 3-4 hours, manpower could become a problem in time required to pump out and charge chlorinators.
ESTIMATED SAVING ON OTHER BENEFITS
1) Meet increases in sales by increasing production capabilities.
2) Avoid adding additional personnel to dept.
SUGGESTED APPROACH, REFERENCES, ETC.
1) Consider putting 2 of batch chlorinators on a continuous scheme by tleing in series.
' 2) Check feasibility of taking a side stream off one of the present continuous
chlorinators at 1121 finishing gravity.
'
MANPOWER REQUIREMENTS
PR ELIMINARV EVALUATION (To b. completed by T.chnlccl Servlc. D.pt.)
NO. MEN
T.5.D. COST
ESTIMATED SAVINGS OR PROFITS
NEW FIXED CAPITAL
EVALUATION 32 MAN HOURS
CH. E. DES.
64 MAN HOURS
M. E. DES.
20 MAN HOURS
COMMENTS
T.B.D.
.
$25,000
E. E. DES.
20 MAN HOURS
Two chlorinators running continuously at 90% 0ST can
INSTR.
60 MAN HOURS . produce 30 M pounds a year of 1121.
DRAFTING
1 00 MAN HOURS
START-UP
40 MAN HOURS
To be scheduled 1st quarter 1971.
DSW 551981
STLCOPCB4090397