June 4, 1970 Minutes of Meeting on Aroclor Replacement Program
Attendees:
H. S. Bergen R. E. Howard M. P. Lux R. L. Neary 0. S. Ratterman R. L. Wiese
J. 0. Bright N. T. Johnson R. M. Kountz E. D. Malone (part-time) D. A. Olson D. B. Redington (part-time) W. r. Richard J. R. savage
A meeting was held May 27, 1970, to review the Aroclor replace ment program, review process status of replacement products, establish quantities of new products needed, assign responsibili ties, and establish rough time schedules.
cumyl-nonyl phenyl diphenyl phosphate
Conclusions were:
1. Production needs are 13.8m lb/yr if Aroclor 1242B is not acceptable and use only excess capacity of E-E Building if 1242B is acceptable. (A decision was made on May 28 that 1242B will be used in Pydrauls as needed.)
Maximum production capacity in E-E Building was estimated at 700M to 1M lb/mo rate. We could probably get 7 months operation in'71. This rate must be verified.
2. interim production of 200M lb is needed in 1970 to:
a) Demonstrate process, and b) Develop markets.
3. Full-scale operation needed as soon as possible, with target of April 1971.
Action plan*
1. Research resolve process problems in 6-8 weeks.
2. Research rework 1m lb of material from previous trial, work to be complete in 2 weeks.
TRAN 093167
( ef L-f-n
WATER PCB-SD0000044376
Minutes of Meeting on Aroclor Replacement Program
June 4, 1970 page 2
3. TSD with Research would define and install necessary
facilities for interim operation. Work to be complete by October 1, 1970.
4. Engineering define needs for full-scale operation and have facilities installed by April 1971 with tributyl phosphate.
Cumyl phenol
Conclusions were:
1. There would be a need of 80-100M lb in 1970.
2. Production rates for_the future were estimated at: 1971 - 2.5M lb/yr Long range - 6M lb/yr
Action plan:
1. Jim Savage would make arrangements by July for 1970
production.
, '
2. Elmer Malone will see if interim cumyl phenol distillation can be done in the W-W Building. If acceptable. Research will automate facilities.
3. Engineering with Research will evaluate by August 1,
1970, alternates for full-scale production. Target for full-scale facilities is April 1971.
Aroclor 1242B
Conclusions were:
/
i
1. Full-scale facilities to produce 50m lb/yr are neede(ynowy
2. There is no need for interim operation.
3 Aroclor 1242b would be provided for all capacitors, Therminol and Pydraul blends if acceptable. (A decision has been made that it is to be used.)
4. By the lb of
the Industrial Fluids group needs 10.4M year's end.
TRAN 093168
WATER PCB-SD0000044377
Minutes of Meeting on Aroclor Replacement program June 4, 1970 page 3 Action plan:
Engineering evaluate, establish, and provide project needs as quickly as reasonably possible. Research expressed a strong preference to have facilities compatible with production of Aroclor 1230. Since the two operations have virtually no similarity, the probability of being compatible is remote.
R. M. Kountz eb