Table 1-1: Summary of Capital Costs for Units 3&4
CAPITAL COST ESTIMATE TALEN MONTANA
COLSTRIP POWER STATION FABRIC FILTER AND ESP COLSTRIP, MT
BMcD #163860
Area / Discipline
Engineered Equipment Civil, Structural & Architectural Mechanical Electrical & l&C
Total Direct Cost
Engineering, Start-up, Commercial Escalation Contingency Construction Management EPC Fee
Total indirect Cost
Total Project Cost Owner Cost - General, Taxes & Fees Owner Cost - Owner Continienc
Total Project Cost Incl. Owner Cost
Rev.
Rev. Date
0
04/05/24
REHEAT FABRIC FILTER
$102,894,000 $128,820,000
$7,270,000 $9,596,000
$248,580,000
$34,065,000 $14,377,000 $59,404,000 Not Included Not Included $107,846,000 $356,426,000 Not Included
Not Included $356,426,000
BURNS MEDONNELL,
REHEAT ESP
$86,794,000 $260,179,000 $34,888,000 $10,542,000 $392,403,000 $54,012,000 $27,520,000 $94,787,000 Not Included Not Included $176,319,000 $568,722,000 Not Included
Not Included $568,722,000
V"
A percentage of the direct costs are included for Engineering, Start Up and Commercial costs. An overall project contingency, 20% of the direct and indirect costs, is included in the indirect costs. The Escalation is based on the project starting in the fall of 2024 and the second unit coining on line 42 months later. An annual escalation rate of four percent (4%) on engineered equipment, five percent (5%) on materials and four percent (4%) on labor and subcontracts has been included.