Document DDzx7vjDr99DD8q46vL3m9D3Q
Monsanto
(HAKE ft LOCATION) Sauget^ IH jnOjS
' March 20, 1970
CT :
Aroclor Lobe to Sewer
PREFERENCE
J V .V.
TO :
c F. Buckley
G. L. Bratsch V. F. Brawl ej
T. W. Dalton
An Aroclor 1142 loss to the sewer occurred on March 13 between 3:30 and 4:30 p.m. The continuous blow tank overflowed to the drowning jet. The loss amounted to an estimated 38*000 pounds.
This Is the same tank that overflowed twice before, but it happened In a different manner. The first two times the level controller on the blow tank malfunctioned. .After the second occurrence the controller was put on a 2 week PM schedule. Project #1493 was being developed to eliminate the risk of sewering Aroclor from the blow tank.
On March 13* two factors caused the loss. First, the department operator left a valve open that should have' been closed, cuasing the tank to overflow. Second, the alarm signalling a high level did not sound. The level controller itself was in working condition however.
On March l8 Project #1493 was installed and put into service. A major loss from the continuous blow tank through the drowning jet cannot occur again.
R. M. MeCutchan Dept. 246
*
DSW 345374